This is a Task Assignment Notification Form under Florida Department of Environmental Protection (FDEP) Contract No. HW554, issued to APTIM Environmental & Infrastructure, Inc. The task assignment, numbered DC021C, designates APTIM as the contractor with Eric Kramer, P.E., serving as the contractor representative. The work location is the former Palm Bay Laundry and Dry Cleaners facility located at 5275 Babcock Street, Suite 13, Palm Bay, Brevard County, Florida (DEP Site No. ERIC_4028). Miranda McClure serves as the acting DEP Contract Manager overseeing the assignment.
The scope of work requires APTIM to prepare and submit an Interim Source Removal (ISR) Work Plan for a Soil Vapor Extraction (SVE) system to address soil contamination from the former dry cleaner operations. The final deliverable, an ISR Work Plan for the SVE system (Stages 1 & 2), is due December 4, 2020, with the overall task assignment completion date of February 5, 2021. The contract is structured as a fixed price engagement with a total task assignment value of $8,545.86, comprised of 55 hours of labor across multiple engineering and technical staff categories, including direct labor costs of $2,804.22, fringe benefits, overhead, general and administrative expenses, and a completion fee. No retainage is applied. Invoicing occurs upon submittal and FDEP approval of the ISR Work Plan for SVE System, with payment of the full amount due upon deliverable acceptance.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW554
D000 NADC021C
APTIM
Eric Kramer, P.E.
850.245.8941Miranda McClure (acting)
ERIC_4028
Palm Bay and Laundry Dry Cleaner 5275 Babcock St., Suite 13, Palm Bay, Brevard County Interim Source Removal (ISR)
This Task Assignment is for APTIM to prepare and submit an ISR Work Plan for and Soil Vapor Extraction system according to the attached Scope of Work and Cost Proposal dated October 9, 2020.
ISR Work Plan
12/04/2020
02/05/2021
$ 8,545.86 $ 0.00 $ 0.00 $ 0.00
$ 0.00
Miranda McClure Digitally signed by Miranda McClure Date: 2020.11.02 17:21:28 -05'00'
Miranda McClure Digitally signed by Miranda McClure Date: 2020.11.02 17:21:40 -05'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2020.11.03 08:29:59 -05'00'
Kramer, Eric K Digitally signed by Kramer, Eric K Date: 2020.11.04 09:28:17 -05'00'
$ 8,545.86
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
ISR Work Plan for SVE System--st 1 & 2 12/04/2020
Submittal and DEP Approval of the ISR Work Plan for SVE System - st 1 & 2 $ 8,545.86
$ 8,545.86
HW554
DC021C
FFLORIDA DEPARTMENT OFF
EEnvironmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DDeSantis Governor
Jeanette NNuñez
Lt. Governor
NNoah Valenstein Secretary
Memorandum TO: Palm Bay Laundry & Dry Cleaners (ERIC_4028) DSCP Site File FROM: Miranda McClure, Project Manager SUBJECT: Negotiation Summary, HW554, TA DC021C DATE: November 2, 2020
APTIM will prepare and submit an Interim Source Removal (ISR) Work Plan for the design of an SVE system for the above facility in accordance with the APTIM Scope of Work dated October 9, 2020.
Subtask 2:
This subtask is for the preparation and submittal of the ISR Work Plan for the design of the SVE system to be installed to address the contamination from the former drycleaner. The cost estimate and level of effort is comparable with other ISR Work Plans for SVE systems.
Final LOE and CE for this TA are 55 hours and $8,545.86, fixed price. This LOE and CE are reasonable for the associated scope.
ERIC_4
DC021C
FDEP COST ESTIMATE
Contractor: Aptim Environmental & Infrastructure
Date: 10/9/2020
Task #: HW554-DC021C SubTask 1 Project Management
Site: Palm Bay Laundry and Dry Cleaner ERIC_4028 SubTask 2 2-ISR/RAP
Activity/Phase: ISR SubTask 3
Project Manager: Eric Kramer SubTask 4
SubTask 5
TTotals 1 2 3 4 5 Labor Rate Category
$61.78 CClient Program Manager 1 E. Kramer 5 5 $61.78 Engineer/Scientist 5 E. Kramer 13 13 0 0 0 $59.42 Engineer/Scientist 5 G. Roberts 1 1 0 0 0 $41.62 Engineer/Scientist 3 A. Blackford 35 35 0 0 0 $31.07 Designer 2 S. Ferianc 4 4 0 0 0 $24.55 Tech Publications Specialist 2 H. Vining 2 2 0 0 0
$0.00 0 0 0 0 0 $0.00 0 0 0 0 0
Total Hours 60 5 55 0 0 0
Direct Labor $2,804.22 $311.58 $2,492.64 $0.00 $0.00 $0.00
Fringe 119.00% $3,337.02 $370.78 $2,966.24 $0.00 $0.00 $0.00 Overhead 20.90% $586.08 $65.12 $520.96 $0.00 $0.00 $0.00 Gen & Admin 32.60% $914.18 $101.58 $812.60 $0.00 $0.00 $0.00 Total Labor $7,641.50 $849.06 $6,792.44 $0.00 $0.00 $0.00
Other Direct Costs $140.21 $15.58 $124.63 $0.00 $0.00 $0.00 Travel
Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $7,781.71 $864.64 $6,917.07 $0.00 $0.00 $0.00 Completion Fee $764.15 $84.91 $679.24 $0.00 $0.00 $0.00
Total Estimated Cost $8,545.86 $949.55 $7,596.31 $0.00 $0.00 $0.00
Cost Estimate Page 1 of 2 DC021C est.xlsx
LEVEL OF EFFORT / EXPENSE WORKSHEET
SITE :
SUBTASK:
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
TITLE STAFF WORK DESCRIPTION HOURS
Engineer/Scientist 5 G. Dever Engineer/Scientist 5 D. Rodgers
Engineer/Scientist 5 E. Kramer
Engineer/Scientist 5 G. Roberts 1 Engineer/Scientist 4 B. Bates Engineer/Scientist 4 S. Flynn Engineer/Scientist 3 D. Mosher Engineer/Scientist 3 B. Dempsey
Engineer/Scientist 3 A. Blackford
Engineer/Scientist 2 T. Gregory Engineer/Scientist 2 K. Howard Engineer/Scientist 2 J. Hall Engineer/Scientist 1 K. McDonald Engineer/Scientist 1 J. Harris Engineering Technician 4 A. Escobar Engineering Technician 3 D. Young Engineering Technician 2 R. Grenville Engineering Technician 2 C. Ramey Engineering Technician 1 D. McConnaughey General Foreman/Supervisor V. Marlar Designer 2 S. Ferianc ISR Drafting (4 hrs) 4 Tech Publications Specialist 2 H. Vining 2 Equipment Operator 3 D. Hernandez
TOTAL LABOR: 55
EQUIPMENT ITEM RATE UNIT USAGE
Expendables $32.50 Day 0 $0.00
TOTAL EQUIPMENT: $0.00
VEHICLE TYPE RATE UNIT USAGE
Automobile $68.00 Day 0 $0.00 Truck $97.00 Day 0 $0.00 Equipment Van $97.00 Day 0 $0.00
TOTAL VEHICLE: $0.00
PER DIEM STAFF RATE UNIT USAGE
Hotel $99.00 Day 0 $0.00 Day One leave before 06:00 AM $36.00 Day 0 $0.00 Day $36.00 Day 0 $0.00 Return Day $80.00 Day 0 $0.00
TOTAL PER DIEM: $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB: $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE Rate UNIT USAGE TOTALS
TOTAL SUB: $0.00
Preparation of Task Assignment Scope of Work and Level of Effort
2-ISR/RAP
Bay Laundry and Dry Cleaner ERIC
Review Available SAR data (2 hrs), Conceptual layout (2 hrs), Conference Call with FDEP for Review of Layout (2 hrs), Review & revise conceptual layout (1 hr), Calculate losses (1 hrs), Size equipment (2 hrs), Draft Plan & Text (3 hrs)
October 9, 2020
Review Available SAR data (2 hrs), Conceptual layout (4 hrs), Conference Call with FDEP for Review of Layout (2 hrs), Review & revise conceptual layout (3 hrs), Calculate losses (3 hrs), size equipment (4 hrs), draft plan & text (16 hrs), Complete RAP Checklist (1 hr)
ISR Administration Processing, Document Production and Formatting (2 hrs)
2-ISR Page 2 of 2 DC021C est.xlsx]
Proposed Scope of Work Palm Bay Laundry and Dry Cleaners Task Assignment DC021C ERIC_4028 (Former FAC ID #59502190) APTIM Environmental & Infrastructure, Inc.
October 9, 2020
The following proposed scope of work under Task Assignment (TA) DC021C has been prepared for the Former Palm Bay Laundry and Dry Cleaner located at 5275 Babcock Street, Suite 13, Palm Bay, Brevard County, Florida. The scope was prepared for the development of an Interim Source Removal (ISR) Work Plan using soil vapor extraction (SVE) as the presumptive remedial strategy at the request of the FDEP based on discussion of the Site Assessment Report (SAR) results.
The following explains the scope of work included in the Task Assignment (TA):
1. Subtask 2 – Interim Source Removal Plan (SVE):
Includes the estimated cost for the preparation of an SR Work Plan for the Former Palm Bay Laundry and Dry Cleaner site. The costs include the design of a SVE system specifically for the Former Palm Bay Laundry and Dry Cleaner based on the findings of the assessment work performed during completion of the SAR. Construction and operation of a SVE system should remove the residual adsorbed contamination in the unsaturated zone that acts as a source of the soil contamination that could continue to volatize under the building slab and/or leach into the groundwater. The ISR will be submitted to the FDEP for review and approval.
The ISR Preparation is estimated to require 4 weeks from approval of the task assignment, therefore the report submittal is estimated be November 20, 2020. The TA completion date should allow for FDEP review and approval of the ISR report, and therefore should be set around January 29, 2021.
APTIM proposes to perform this scope of work in accordance with the terms and conditions of the contract executed between APTIM Environmental & Infrastructure, Inc. and Florida Department of Environmental Protection No. HW554. APTIM will begin the proposed scope of work upon written authorization.
In the event you have any questions, please contact us for clarification.
File details come from the government source that posted it. Updated .