CLIN Pricing Schedule 22-0016 Fuel Farm Repairs UN36 and TC366.pdf

PDF 118 KB Posted

Attached to
Fuel Farm Repairs UN360 and TC366
Solicitation number
N4008525R2644
Issued by

About this file

The document is a Contract Line Item (CLIN) Pricing Schedule for a project at Marine Corps Base Camp Lejeune to expand containment and install generators at Defense Fuel Support Points (DFSP) located at Camp Geiger and Camp Johnson. The pricing schedule includes three primary line items: a basic item for Camp Geiger (Item 0001), an option item for a fuel dispenser lane at Camp Geiger (Item 0002), and a basic item for Camp Johnson (Item 0003). Each item is priced as a single job with an unspecified unit price, and the document notes that funds are currently unavailable for the acquisition, with no contract award to be made until funding is secured. Offerors are required to insert prices for all numbered items, with a warning that failure to do so may result in an unacceptable offer.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract Line Item Pricing Schedule (00 10 00) - 3

Project No: [22-0016 / P.2024.00043] Title: Expand Containment/Install Generators Location: MCB Camp Lejeune (Camp Geiger and Camp Johnson Defense Fuel Support Points (DFSP))

CONTRACT LINE ITEM PRICING SCHEDULE

Item No. Description of Item Estimated

Quantity Unit Unit Price Amount

BASIC ITEM FOR CAMP GEIGER DFSP

0001 Camp Gieger Basic Item - Includes all materials and work complete to perform all of the scope of work of this contract at MCB Camp Lejeune Camp Geiger that is not covered under the scope of work of the Item 0002 option item listed below.

JOB

XXX

OPTION ITEM FOR CAMP GEIGER DFSP

Item No. Description of Item Estimated

Quantity Unit Unit Price Amount

0002 Fuel Dispenser Lane at Camp Geiger – Includes all materials and work complete to provide the Drawing CS100 Sheet Keynote 2 and 4 concrete and asphalt fuel dispenser lane and all material and work complete that allows this fuel dispenser lane to be complete and useable including all associated demolition, the Drawing CS100 Sheet Keynote 5 chain link fence installation, Drawing CS100 Sheet Keynote 12 and Drawing CG100 Sheet Keynote 6 oil water separator installation, Drawing CG100 Sheet Keynote 5 northernmost drop inlet (i.e. DI #9) installation, Drawing CG100 Sheet Keynote 7 grade to provide positive drainage, Drawing CG100 Sheet Keynote 8 stabilize disturbed areas on northern side of site, Drawing CG100 Sheet Keynote 10 8-inch storm drain pipe installation, Drawing CG100 Sheet Keynote 11 connect to exiting sewer manhole with outside drop, maximum drop 30 inches, Drawing CG100 Sheet Keynote 12 install concrete headwall, and Drawing CG100 Sheet Keynote 13 install sluice gate mounted to headwall.

BASIC ITEM FOR CAMP JOHNSON DFSP

Item No. Description of Item Estimated

Quantity Unit Unit Price Amount

0003 Camp Johnson Basic Item - Includes all materials and work complete to perform all of the scope of work of this contract at MCB Camp Lejeune Camp Johnson.

TOTAL AMOUNT BASIC ITEMS 0001 AND 0003 $

TOTAL AMOUNT OPTION ITEM 0002 $

TOTAL AMOUNT (BASIC PLUS OPTION ITEM (I.E.ITEMS 0001 THRU 0003))

Notes:

1. Offerors must insert a price on all numbered items of the CLIN pricing schedule. Failure to do so may result in the offer being unacceptable. Additions will be subject to verification by the Government. In case of variation between the Job (lump-sum) prices and the total amount, the lump-sum prices will be considered the price.

Abbreviations: Minor Construction (MC); Maintenance and Repair (MR); Demolition (DEMO).

2. Funds are not presently available for this acquisition. No contract award will be made until funds are made available.

File details come from the government source that posted it. Updated .