Clarification on how many bulbs and fixtures needing swapped.docx
DOCX document 13 KB Posted
- Solicitation number
- 22-444DHS-ISDIS-B-26042
- Issued by
- Mercer County, Illinois
About this file
This document appears to be a clarification on the quantity and locations of light bulbs and fixtures that need to be replaced as part of a state or local government contract opportunity. The document provides specific details on the number and types of fixtures that should be left in place and have the bulbs replaced, as well as the quantities and locations of fixtures that should be fully replaced. It also includes guidance on adding emergency lighting in certain areas and adjusting the quantities for several line items. The scope of work indicates this will be a 1:1 swap of both fixtures and light bulbs in certain areas.
The document does not include information on pricing, set asides, incumbents, funding sources, or other salient contract details. It appears to be focused solely on clarifying the specific requirements related to the light fixtures and bulbs that need to be addressed as part of this contract opportunity.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Covid Notice~9.docx | DOCX document | |
| RMU50~90.docx | DOCX document | |
| Mandatory Onsite Visit Guidance for Vendors_36~4.docx | DOCX document | |
| FormsBSectionV201 blank~10.docx | DOCX document | |
| RFQ LED lighting ~2.docx | DOCX document | |
| StandardTermsConditions~20.pdf | ||
| StandardCertifications~19.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1) There are a few fixtures that would be better to leave in place , by pass ballast and install LED lamps rather than replacing entire fixture. Locations such as kitchen basement boiler room, building 2 mechanical room, green house hanging fixtures, building 2 - 4 office rooms, utility and closets in #2, 2). Add an emergency light in building 2 mechanical room
3) building 2 basement stairs, 4 of 6 2x2 replacements should be emergency back up.
4) building 2, attempt to replace lamps in 5 chandeliers.
5). Dietary - many of the 2 lamp fixtures in kitchen and bakery areas have 4 lamp ballast in one fixture with a whip to second fixture.
6) building 2. 3B qty is 18 not 22
7) building 2 3C qty is 12 not 8
8) building 2- 3E qty is 46 fixtures to be replaced
9) On Scope of work 3E this will be a 1:1 swap both fixtures and lightbulbs.
10) on Scope of work 8D this will be a 1:1 swap both fixtures and lightbulbs.