The document is a project schedule for the City of Sulphur Springs Senior Center, detailing a comprehensive timeline for a pre-engineered metal building (PEMB) construction project. The schedule spans from May 26, 2021, to June 14, 2022, and is divided into two main phases: Pre-Construction (120 days) and Construction (236 days). Key milestones include PEMB bid processes, concrete bidding, submittal phases, and specific work activities such as foundation preparation, steel erection, and roof installation. The project involves multiple bidding stages for different work categories, with specific deadlines for advertising, requesting information, receiving bids, recommendations, awards, and contract issuance.
The project schedule indicates a structured approach to project management, with detailed dependencies and sequential activities. The construction timeline includes critical path activities like concrete work, pre-engineered metal building erection, foundation concrete placement, steel delivery, and roof installation. The project appears to be funded by the City of Sulphur Springs and involves a senior center facility totaling approximately 9,053 square feet, including 8,331 square feet of conditioned space and a 722 square foot covered drive. The schedule suggests careful coordination between different construction phases and subcontractors, with precise start and end dates for each major project component.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 22021.00 Senior Center Sulphur Springs - PEMB Set.pdf | ||
| 850 Senior Center PEMB.pdf | ||
| Division 13 PEMB Scope 5-20-2021 (1).pdf | ||
| CIQ (1).pdf | ||
| fw9.pdf | ||
| PEMB Proposal Form.pdf | ||
| Invitation to Bid Senior Center PEMB.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project name City of Sulphur Springs Senior Center
Outline number Name Duration Depends on Start Finish 1 Pre-Construction 120 days 5/26/2021 11/9/2021
1.1 PEMB Bid 39 days 5/26/2021 7/19/2021
1.1.1 Advertise 5 days 5/26/2021 6/1/2021
1.1.2 RFI's 18 days 5/26/2021 6/18/2021
1.1.3 Receive Bids 1 day 6/29/2021 6/29/2021
1.1.4 Recommend 5 days 6/29/2021 7/5/2021
1.1.5 Award 1 day 7/6/2021 7/6/2021
1.1.6 Send Contracts/Bonds 8 days 7/7/2021 7/16/2021
1.1.7 Notice to Proceed 1 day 8 - Send Contracts/Bonds 7/19/2021 7/19/2021
1.2 Concrete Bid 47 days 8/10/2021 10/13/2021
1.2.1 Completed Project Plans 21 days 48 - Foundation Reactions 8/10/2021 9/7/2021
1.2.2 Advertise 1 day 11 - Completed Project Plans 9/8/2021 9/8/2021
1.2.3 RFI's 18 days 12 - Advertise 9/9/2021 10/4/2021
1.2.4 Receive Bids 1 day 13 - RFI's 10/5/2021 10/5/2021
1.2.5 Recommend 2 days 14 - Receive Bids 10/6/2021 10/7/2021
1.2.6 Award 1 day 15 - Recommend 10/8/2021 10/8/2021
1.2.7 Send Contracts/Bonds 2 days 16 - Award 10/11/2021 10/12/2021
1.2.8 Notice to Proceed 1 day 17 - Send Contracts/Bonds 10/13/2021 10/13/2021
1.3 All Other Work Categorys 66 days 8/10/2021 11/9/2021
1.3.1 Completed Project Plans 21 days 48 - Foundation Reactions 8/10/2021 9/7/2021
1.3.2 Advertise 1 day 20 - Completed Project Plans 9/8/2021 9/8/2021
1.3.3 RFI's 18 days 21 - Advertise 9/9/2021 10/4/2021
1.3.4 Receive Bids 1 day 22 - RFI's 10/22/2021 10/22/2021
1.3.5 Recommend 5 days 23 - Receive Bids 10/25/2021 10/29/2021
1.3.6 Award 1 day 24 - Recommend 11/1/2021 11/1/2021
1.3.7 Send Contracts/Bonds 5 days 25 - Award 11/2/2021 11/8/2021
1.3.8 Notice to Proceed 1 day 26 - Send Contracts/Bonds 11/9/2021 11/9/2021
2 Construction 236 days 7/20/2021 6/14/2022
2.1 Sumbital 91 days 7/20/2021 11/23/2021
2.1.4 Concrete 10 days 19 - All Other Work Categorys, 10 - Concrete Bid 11/10/2021 11/23/2021
2.1.4.1 Re-Bar Shop Drawings 5 days 11/10/2021 11/16/2021
2.1.4.2 Re-Bar Approval 5 days 39 - Re-Bar Shop Drawings 11/17/2021 11/23/2021
2.1.4.3 Mix design 1 day 11/10/2021 11/10/2021
2.1.7 Pre Engineered Metal Building 75 days 9 - Notice to Proceed 7/20/2021 11/1/2021
2.1.7.1 Approval Drawings 10 days 9 - Notice to Proceed 7/20/2021 8/2/2021
2.1.7.2 Foundation Reactions 5 days 47 - Approval Drawings 8/3/2021 8/9/2021
2.1.7.3 Detail Steel 30 days 48 - Foundation Reactions 8/10/2021 9/20/2021
2.1.7.4 Detail Shop Drawings 25 days 49 - Detail Steel 9/21/2021 10/25/2021
2.1.7.5 Approval 5 days 50 - Detail Shop Drawings 10/26/2021 11/1/2021
2.2 Work Activites 161 days 11/2/2021 6/14/2022
2.2.1 Concrete 29 days 38 - Concrete 11/24/2021 1/3/2022
2.2.1.1 Layout 2 days 38 - Concrete 11/24/2021 11/25/2021
2.2.1.2 Tie Pier Cages 4 days 92 - Layout 11/26/2021 12/1/2021
2.2.1.3 Pier Drilling 4 days 93 - Tie Pier Cages 12/2/2021 12/7/2021
2.2.1.4 Set Forms 4 days 94 - Pier Drilling 12/8/2021 12/13/2021
2.2.1.5 Grade Beam Excavation 4 days 95 - Set Forms, 117 - Underslab Rough In 12/17/2021 12/22/2021
2.2.1.6 Install Grade Beam Re-Bar 2 days 96 - Grade Beam Excavation 12/23/2021 12/24/2021
2.2.1.7 Install Slab Re-Bar 2 days 97 - Install Grade Beam Re-Bar 12/27/2021 12/28/2021
2.2.1.8 Set Anchor Bolts 2 days 98 - Install Slab Re-Bar 12/29/2021 12/30/2021
2.2.1.9 Place Foundation Concrete 1 day 99 - Set Anchor Bolts, 149 - Termite Spray 1/3/2022 1/3/2022
2.2.2 Pre Engineered Erection 89 days 46 - Pre Engineered Metal Building 11/2/2021 3/4/2022
2.2.2.1 Delivery of Fabrication & Misc. Steel 50 days 46 - Pre Engineered Metal Building 11/2/2021 1/10/2022
2.2.2.2 Erection 20 days 100 - Place Foundation Concrete 1/17/2022 2/11/2022
2.2.2.3 Roof Installation 15 days 103 - Erection 2/14/2022 3/4/2022