CIS Commissioning RFP Addendum Q&A.pdf
PDF 520 KB Posted
- Attached to
- Commissioning Agent
- Solicitation number
- S-X24129-00011496
- Issued by
- Clackamas County, Oregon
About this file
This document is an Addendum to a Request for Proposals (RFP) issued by CIS to solicit offers from qualified firms for the selection and retention of a Commissioning Agent (CxA) to perform commissioning services for CIS' new Collaboration Center project currently under construction. The RFP schedule includes an issuance date of September 9, 2024, a deadline for questions on September 16, 2024, and a proposal due date of September 23, 2024. This Addendum provides responses to written questions received from potential proposers and modifies the original RFP only to the extent indicated, with all other areas of the RFP remaining in effect.
The RFP outlines the expectations for the CxA's review of cost-effectiveness and trade coordination, the commissioning of the fire protection system, and the utility management plan requirements. The project schedule is also provided, including milestone dates from the design phases through turnover. Proposers who have already submitted a proposal may either submit an addendum or withdraw the original and submit a new one by the September 23, 2024 deadline.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| CIS Commissioning RFP 2024.pdf | ||
| Vault 2.jpg | JPG image |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Proposals (RFP) Addendum
CIS Collabora on Center Project Commissioning Agent
RFP Schedule
Issuance of RFP: September 9, 2024
Submission of QuesƟons about the RFP: September 16, 2024, 5:00 p.m. (PT)
Proposal Due: September 23, 2024, 5:00 p.m. (PT)
1 | P a g e
ADDENDUM
A. BACKGROUND
On September 9, 2024, CIS issued a Request for Proposals (RFP) to solicit offers from qualified firms for selecƟon and retenƟon of a qualified Commissioning Agent (CxA) to perform a variety of commissioning services for CIS' new CollaboraƟon Center, currently under construcƟon.
CIS is issuing this Addendum to the RFP to respond to wriƩen quesƟons we received from potenƟal proposers. The Addendum modifies the original RFP document only to the extent indicated. All other areas of the original RFP remain in effect and can only be modified in wriƟng by CIS. This Addendum is made an integral part of the original RFP. It is the responsibility of all proposers to conform to this Addendum. Proposers who have already submiƩed proposals may either: 1. Submit an addendum to their proposal; or 2. withdraw the original proposal and submit a new one. Any addendum or revised proposal must be submiƩed no later than the Proposal Due Date of 5:00 p.m. (PT) on September 23, 2024.
B. RESPONSES TO QUESTIONS
1. What is the anƟcipated schedule for the project? (What are the anƟcipated milestone dates? From design phases through turnover.)
A: Please see the schedule included with this addendum.
2. What are the expectaƟons for review around cost-effecƟveness and coordinaƟon of trades?
A: Typically, the commission process will idenƟfy conformance or non-conformance with the design documents and noƟfy the trades if correcƟons are required. This review is related to performance vs cost-effecƟveness.
3. What are the expectaƟons for commissioning of the fire protecƟon system and how might that differ from the Fire Marshal inspecƟon?
A: The fire marshal will do a minimum of tests to ensure that the system is funcƟoning.
Commissioning should go more in depth to make sure all the system components are working correctly not only individually but in tandem with the other building systems. With commissioning, more Ɵme is spent looking at the individual components as well as the funcƟonality of the system. For a small project commissioning would not be as important, but for a larger project it could certainly find some disconnects that may not be immediately apparent.
4. Our experience with UƟlity Management Plans is closely related to criƟcal-care healthcare faciliƟes.
Are their uƟliƟes expected for this project beyond standard office environment systems?
A: Our understanding is that this is related to the energy code review. This project is a standard office environment, with typical funcƟons, private office, open office, conference, breakroom, training, etc.
ID Task Name Duration Start Finish
0 CIS 391 days Fri 3/29/24 Thu 10/9/25
1 Pre-Construction 314 days Fri 3/29/24 Fri 6/20/25
2 Design 37 days Fri 3/29/24 Tue 5/21/24
3 50% CD 0 days Fri 3/29/24 Fri 3/29/24
4 Bid Documents (Approved 90% CDs) 0 days Tue 5/14/24 Tue 5/14/24
5 Permit Documents 0 days Tue 5/21/24 Tue 5/21/24
6 Permitting 78 days Tue 5/21/24 Mon 9/9/24
7 Early Grading Permit 68 days Tue 5/21/24 Fri 8/23/24
8 Permit Review 20 days Tue 5/21/24 Mon 6/17/24
9 Plan Check Comment Response 5 days Tue 6/18/24 Mon 6/24/24
10 Pre-Issuance 38 days Tue 6/25/24 Fri 8/16/24
11 Erosion Control Premit 1 day Mon 8/19/24 Mon 8/19/24
12 Early Grading Permit Release 1 day Fri 8/23/24 Fri 8/23/24
13 Building Permit 78 days Tue 5/21/24 Mon 9/9/24
14 Permit Review 40 days Tue 5/21/24 Tue 7/16/24
15 Plan Check Comments 15 days Wed 7/17/24 Tue 8/6/24
16 Pre-Issuance 23 days Wed 8/7/24 Mon 9/9/24
17 Building Permit Release 0 days Mon 9/9/24 Mon 9/9/24
18 Buyout & Contracting 37 days Tue 5/14/24 Wed 7/3/24
19 Subcontractor Bidding 15 days Tue 5/14/24 Mon 6/3/24
20 Bid Analysis / Assemble GMP 5 days Tue 6/4/24 Mon 6/10/24
21 Owner Review 10 days Tue 6/11/24 Mon 6/24/24
22 Board Review & Approval 5 days Tue 6/25/24 Mon 7/1/24
23 GMP Amendment 2 days Tue 7/2/24 Wed 7/3/24
24 Notice to Proceed 0 days Fri 8/23/24 Fri 8/23/24
25 Procurement 228 days Tue 7/30/24 Fri 6/20/25
178 Construction 271 days Fri 8/16/24 Wed 9/10/25
179 Milestones 265 days Fri 8/23/24 Wed 9/10/25
180 Mobilization 0 days Fri 8/23/24 Fri 8/23/24
181 First Footing Pour 0 days Tue 10/8/24 Tue 10/8/24
182 SOG Pour 0 days Tue 10/29/24 Tue 10/29/24
183 Tilt Panels 0 days Mon 12/16/24 Mon 12/16/24
184 Roofing Structure 0 days Fri 1/17/25 Fri 1/17/25
185 Roofing Complete 0 days Mon 2/10/25 Mon 2/10/25
186 Start Interior Framing 0 days Thu 2/20/25 Thu 2/20/25
187 Start Drywall Hanging 0 days Tue 4/8/25 Tue 4/8/25
188 Permenant Power 0 days Fri 7/25/25 Fri 7/25/25
189 Paving 0 days Tue 4/22/25 Tue 4/22/25
190 Start Polished Concrete 0 days Tue 6/10/25 Tue 6/10/25
191 Substantial Complete 0 days Wed 9/10/25 Wed 9/10/25
192 Mobilization 5 days Wed 8/21/24 Tue 8/27/24
193 Temporary Fence 1 day Wed 8/21/24 Wed 8/21/24
194 Temporary Power 1 day Tue 8/27/24 Tue 8/27/24
195 Temporary Water 1 day Tue 8/27/24 Tue 8/27/24
196 Utility Locates 1 day Mon 8/26/24 Mon 8/26/24
197 1200C / Erosion Control 5 days Fri 8/16/24 Thu 8/22/24
3/29
3/29 50% CD
5/14 Bid Documents (Approved 90% CDs)
5/21 Permit Documents
5/21 Permit Review
6/18 Plan Check Comment Response
6/25 Pre-Issuance
8/19 Erosion Control Premit
8/23 Early Grading Permit Release
5/21 Permit Review
7/17 Plan Check Comments
8/7 Pre-Issuance
9/9 Building Permit Release
5/14 Subcontractor Bidding
6/4 Bid Analysis / Assemble GMP
6/11 Owner Review
6/25 Board Review & Approval
7/2 GMP Amendment
8/23 Notice to Proceed
8/23 Mobilization
10/8 First Footing Pour
10/29 SOG Pour
12/16 Tilt Panels
1/17 Roofing Structure
2/10 Roofing Complete
2/20 Start Interior Framing
4/8 Start Drywall Hanging
7/25 Permenant Power
4/22 Paving
6/10 Start Polished Concrete
9/10 Substantial Complete
8/21 Temporary Fence
8/27 Temporary Power
8/27 Temporary Water
8/26 Utility Locates
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
CIS 3-week Construction Schedule 8.27.24 Wed 8/28/24
198 Erosion Control 2 days Wed 8/21/24 Thu 8/22/24
199 Erosion Control Inspection 1 day Tue 8/20/24 Tue 8/20/24
200 Existing Tree Protection Inspecton 1 day Fri 8/16/24 Fri 8/16/24
201 Initial Sitework 13 days Fri 8/23/24 Wed 9/11/24
202 Demo Existing Hardscapes 2 days Fri 8/23/24 Mon 8/26/24
203 Clear & Grub 3 days Mon 8/26/24 Wed 8/28/24
204 Excavate Existing Fill & Import Structural Fill at SOG
5 days Tue 9/3/24 Mon 9/9/24
205 Temp Construction offices 1 day Thu 8/29/24 Thu 8/29/24
206 Site Surveying 2 days Wed 9/4/24 Thu 9/5/24
207 Rough Grade building pad 6 days Wed 9/4/24 Wed 9/11/24
208 Site Utilities 37 days Tue 9/10/24 Wed 10/30/24
218 Sitework 96 days Tue 1/28/25 Wed 6/11/25
219 Rough Grade 15 days Tue 1/28/25 Mon 2/17/25
220 Curbs/Walks 20 days Tue 2/18/25 Mon 3/17/25
221 Form Bollards 2 days Tue 2/18/25 Wed 2/19/25
222 Bollard Structural Reinforcement 2 days Thu 2/20/25 Fri 2/21/25
223 Bollard Inspection 1 day Mon 2/24/25 Mon 2/24/25
224 Bollard Pour 1 day Tue 2/25/25 Tue 2/25/25
225 Bollard Strip 2 days Wed 2/26/25 Thu 2/27/25
226 Light Pole Base Form 3 days Tue 3/18/25 Thu 3/20/25
227 Light Pole Base Reinforcing Steel 2 days Fri 3/21/25 Mon 3/24/25
228 Light Pole Base Inspection 1 day Tue 3/25/25 Tue 3/25/25
229 Light Pole Base Pour 1 day Wed 3/26/25 Wed 3/26/25
230 Light Pole Base Strip 2 days Thu 3/27/25 Fri 3/28/25
231 Light Pole Install 5 days Mon 3/31/25 Fri 4/4/25
232 Form Trash Enclosure Footing 1 day Tue 3/18/25 Tue 3/18/25
233 Trash Enclosure Footing Structural Reinforcement1 day Wed 3/19/25 Wed 3/19/25
234 Trash Enclosure Footing Inspection 1 day Thu 3/20/25 Thu 3/20/25
235 Trash Enclosure Footing Pour 1 day Fri 3/21/25 Fri 3/21/25
236 Trash Enclosure Footing Strip 1 day Mon 3/24/25 Mon 3/24/25
237 Form Trash Enclosure SOG 1 day Tue 3/25/25 Tue 3/25/25
238 Trash Enclosure SOG Structural
Reinforcement
1 day Wed 3/26/25 Wed 3/26/25
239 Trash Enclosure SOG Inspection 1 day Thu 3/27/25 Thu 3/27/25
240 Trash Enclosure SOG Pour 2 days Fri 3/28/25 Mon 3/31/25
241 Trash Enclosure SOG Strip 1 day Tue 4/1/25 Tue 4/1/25
242 Trash Enclosure CMU 5 days Wed 4/2/25 Tue 4/8/25
243 Trash Enclosure Canopy 3 days Wed 4/9/25 Fri 4/11/25
244 Trash Enclosure Gate 2 days Mon 4/14/25 Tue 4/15/25
245 Trash Enclosure Radial Curbs Form/Pour 1 day Wed 4/16/25 Wed 4/16/25
246 Paving 4 days Thu 4/17/25 Tue 4/22/25
247 Precast Wheel Stop 2 days Wed 4/23/25 Thu 4/24/25
248 EV Charging Station 5 days Wed 4/23/25 Tue 4/29/25
249 Monument Signs 2 days Wed 4/23/25 Thu 4/24/25
250 Site Signage 2 days Wed 4/23/25 Thu 4/24/25
251 Bike Racks 1 day Wed 4/23/25 Wed 4/23/25
8/21 Erosion Control
8/20 Erosion Control Inspection
8/16 Existing Tree Protection Inspecton
8/23 Demo Existing Hardscapes
8/26 Clear & Grub
9/3 Excavate Existing Fill & Import Structural Fill at SOG
8/29 Temp Construction offices
9/4 Site Surveying
9/4 Rough Grade building pad
1/28 Rough Grade
2/18 Curbs/Walks
2/18 Form Bollards
2/20 Bollard Structural Reinforcement
2/24 Bollard Inspection
2/25 Bollard Pour
2/26 Bollard Strip
3/18 Light Pole Base Form
3/21 Light Pole Base Reinforcing Steel
3/25 Light Pole Base Inspection
3/26 Light Pole Base Pour
3/27 Light Pole Base Strip
3/31 Light Pole Install
3/18 Form Trash Enclosure Footing
3/19 Trash Enclosure Footing Structural Reinforcement
3/20 Trash Enclosure Footing Inspection
3/21 Trash Enclosure Footing Pour
3/24 Trash Enclosure Footing Strip
3/25 Form Trash Enclosure SOG
3/26 Trash Enclosure SOG Structural Reinforcement
3/27 Trash Enclosure SOG Inspection
3/28 Trash Enclosure SOG Pour
4/1 Trash Enclosure SOG Strip
4/2 Trash Enclosure CMU
4/9 Trash Enclosure Canopy
4/14 Trash Enclosure Gate
4/16 Trash Enclosure Radial Curbs Form/Pour
4/17 Paving
4/23 Precast Wheel Stop
4/23 EV Charging Station
4/23 Monument Signs
4/23 Site Signage
4/23 Bike Racks
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
252 Landscape/Irrigation 25 days Wed 4/23/25 Wed 5/28/25
253 Striping 5 days Thu 5/29/25 Wed 6/4/25
254 Site Clean 5 days Thu 6/5/25 Wed 6/11/25
255 Structure 103 days Mon 9/16/24 Tue 2/11/25
256 Deep Underslab Electrical 6 days Mon 9/16/24 Mon 9/23/24
257 Underslab Plumbing 10 days Mon 9/16/24 Fri 9/27/24
258 Interior Footings (11) 95 days Thu 9/26/24 Tue 2/11/25
259 Layout 1 day Thu 9/26/24 Thu 9/26/24
260 Excavation 3 days Fri 9/27/24 Tue 10/1/24
261 Layout 1 day Mon 9/30/24 Mon 9/30/24
262 Form 3 days Tue 10/1/24 Thu 10/3/24
263 Rebar & Inspection 2 days Fri 10/4/24 Mon 10/7/24
264 Pour 1 day Tue 10/8/24 Tue 10/8/24
265 Strip 1 day Wed 10/9/24 Wed 10/9/24
266 SOG 15 days Thu 10/10/24 Wed 10/30/24
267 Fine Grade 3 days Thu 10/10/24 Mon 10/14/24
268 Vapor Barrier 3 days Tue 10/15/24 Thu 10/17/24
269 Layout 1 day Fri 10/18/24 Fri 10/18/24
270 Form 3 days Mon 10/21/24 Wed 10/23/24
271 Rebar & Inspection 3 days Thu 10/24/24 Mon 10/28/24
272 Pour 1 day Tue 10/29/24 Tue 10/29/24
273 Saw Cut 1 day Wed 10/30/24 Wed 10/30/24
274 Strip 1 day Wed 10/30/24 Wed 10/30/24
275 Tilt Panels 31 days Thu 10/31/24 Mon 12/16/24
276 Layout 1 day Thu 10/31/24 Thu 10/31/24
277 Form,Reveal & BF liner 5 days Fri 11/1/24 Thu 11/7/24
278 Rebar & Inspection 3 days Fri 11/8/24 Tue 11/12/24
279 Embed Install 2 days Wed 11/13/24 Thu 11/14/24
280 Pour 1 day Fri 11/15/24 Fri 11/15/24
281 Strip 1 day Mon 11/18/24 Mon 11/18/24
282 Panel Cure Time 28 edays Mon 11/18/24 Mon 12/16/24
283 Set Tilit Wall Panels 1 day Mon 12/16/24 Mon 12/16/24
284 Exterior Footings 22 days Fri 11/1/24 Wed 12/4/24
285 Layout For Excavation 1 day Fri 11/1/24 Fri 11/1/24
286 Excavation 2 days Mon 11/4/24 Tue 11/5/24
287 Layout 1 day Wed 11/6/24 Wed 11/6/24
288 Form 3 days Mon 11/18/24 Wed 11/20/24
289 Rebar & Inspection 3 days Thu 11/21/24 Mon 11/25/24
290 Rebar Template For Stem Walls 1 day Tue 11/26/24 Tue 11/26/24
291 Embed Install 2 days Wed 11/27/24 Mon 12/2/24
292 Pour 1 day Tue 12/3/24 Tue 12/3/24
293 Strip 1 day Wed 12/4/24 Wed 12/4/24
294 Stem Walls 11 days Thu 12/5/24 Thu 12/19/24
295 Layout 1 day Thu 12/5/24 Thu 12/5/24
296 Form "One Side" 3 days Fri 12/6/24 Tue 12/10/24
297 Rebar & Inspection 3 days Wed 12/11/24 Fri 12/13/24
4/23 Landscape/Irrigation
5/29 Striping
6/5 Site Clean
9/16 Deep Underslab Electrical
9/16 Underslab Plumbing
9/26 Layout
9/27 Excavation
9/30 Layout
10/1 Form
10/4 Rebar & Inspection
10/8 Pour
10/9 Strip
10/10 Fine Grade
10/15 Vapor Barrier
10/18 Layout
10/21 Form
10/24 Rebar & Inspection
10/29 Pour
10/30 Saw Cut
10/30 Strip
10/31 Layout
11/1 Form,Reveal & BF liner
11/8 Rebar & Inspection
11/13 Embed Install
11/15 Pour
11/18 Strip
11/18 Panel Cure Time
12/16 Set Tilit Wall Panels
11/1 Layout For Excavation
11/4 Excavation
11/6 Layout
11/18 Form
11/21 Rebar & Inspection
11/26 Rebar Template For Stem Walls
11/27 Embed Install
12/3 Pour
12/4 Strip
12/5 Layout
12/6 Form "One Side"
12/11 Rebar & Inspection
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
298 Form "Close Up" 2 days Mon 12/16/24 Tue 12/17/24
299 Pour 1 day Wed 12/18/24 Wed 12/18/24
300 Strip 1 day Thu 12/19/24 Thu 12/19/24
301 Perimiter Pour Strip 6 days Fri 12/20/24 Mon 12/30/24
302 Fine Grade 1 day Fri 12/20/24 Fri 12/20/24
303 Drill & Epoxy Dowels 4 days Mon 12/23/24 Fri 12/27/24
304 Pour 1 day Mon 12/30/24 Mon 12/30/24
305 Saw Cut 1 day Mon 12/30/24 Mon 12/30/24
306 Column Pour Backs 1 day Mon 12/30/24 Mon 12/30/24
307 Pour Column Block Outs 1 day Mon 12/30/24 Mon 12/30/24
308 Remove Tilt Braces ? 6 days Tue 2/4/25 Tue 2/11/25
309 Remove Braces 6 days Tue 2/4/25 Tue 2/11/25
310 Tilt Panels Milestone 0 days Mon 12/16/24 Mon 12/16/24
311 VIF Storefront RO 1 day Tue 12/17/24 Tue 12/17/24
312 Structural Steel 10 days Tue 12/17/24 Tue 12/31/24
313 Roof Structure 15 days Fri 12/27/24 Fri 1/17/25
314 Roof Structure Milestone 0 days Fri 1/17/25 Fri 1/17/25
315 Backfill SOG Pourback 2 days Mon 1/20/25 Tue 1/21/25
316 Vapor Barrier SOG Pourback 1 day Wed 1/22/25 Wed 1/22/25
317 Structural Reinforcement SOG Pourback 1 day Thu 1/23/25 Thu 1/23/25
318 Structural Reinforcement SOG Pourback
Inspection
1 day Fri 1/24/25 Fri 1/24/25
319 Place SOG Pourbacks 1 day Mon 1/27/25 Mon 1/27/25
320 Envelope 113 days Mon 1/20/25 Thu 6/26/25
321 Form Rooftop Mechanical SOMG 1 day Mon 1/20/25 Mon 1/20/25
322 Rooftop Mechanical SOMG Structural Reinforcement 1 day Tue 1/21/25 Tue 1/21/25
323 Rooftop Mechanical SOMD Inspection 1 day Wed 1/22/25 Wed 1/22/25
324 Pour Rooftop Mechanical SOMD 1 day Thu 1/23/25 Thu 1/23/25
325 Strip Rooftop Mechanical SOMD 1 day Fri 1/24/25 Fri 1/24/25
326 Rooftop Mechanical Units - RTU-1-2 4 days Wed 6/11/25 Mon 6/16/25
327 Rooftop Mechanical Enclosure 8 days Tue 6/17/25 Thu 6/26/25
328 Roof Hatch 1 day Mon 1/20/25 Mon 1/20/25
329 Vapor Barrier 2 days Tue 1/21/25 Wed 1/22/25
330 Rigid Insulation 3 days Thu 1/23/25 Mon 1/27/25
331 Metal Roofing 10 days Tue 1/28/25 Mon 2/10/25
332 Single Ply Roofing 10 days Tue 1/28/25 Mon 2/10/25
333 Roofing Complete Milestone 0 days Mon 2/10/25 Mon 2/10/25
334 Walkway Pads 2 days Tue 2/11/25 Wed 2/12/25
335 PV Install 10 days Tue 2/11/25 Mon 2/24/25
336 Exterior Infill Framing 8 days Tue 1/28/25 Thu 2/6/25
337 Sheathing 8 days Tue 2/4/25 Thu 2/13/25
338 WRB 6 days Fri 2/14/25 Fri 2/21/25
339 RO Prep/Flashings 5 days Mon 2/24/25 Fri 2/28/25
340 Storefront Install 20 days Mon 3/3/25 Fri 3/28/25
341 Air/Water Testing 1 day Mon 3/31/25 Mon 3/31/25
342 Exterior Furring/Insulation 7 days Mon 3/31/25 Tue 4/8/25
12/16 Form "Close Up"
12/18 Pour
12/19 Strip
12/20 Fine Grade
12/23 Drill & Epoxy Dowels
12/30 Pour
12/30 Saw Cut
12/30 Pour Column Block Outs
2/4 Remove Braces
12/16 Tilt Panels Milestone
12/17 VIF Storefront RO
12/17 Structural Steel
12/27 Roof Structure
1/17 Roof Structure Milestone
1/20 Backfill SOG Pourback
1/22 Vapor Barrier SOG Pourback
1/23 Structural Reinforcement SOG Pourback
1/24 Structural Reinforcement SOG Pourback Inspection
1/27 Place SOG Pourbacks
1/20 Form Rooftop Mechanical SOMG
1/21 Rooftop Mechanical SOMG Structural Reinforcement
1/22 Rooftop Mechanical SOMD Inspection
1/23 Pour Rooftop Mechanical SOMD
1/24 Strip Rooftop Mechanical SOMD
6/11 Rooftop Mechanical Units - RTU-1-2
6/17 Rooftop Mechanical Enclosure
1/20 Roof Hatch
1/21 Vapor Barrier
1/23 Rigid Insulation
1/28 Metal Roofing
1/28 Single Ply Roofing
2/10 Roofing Complete Milestone
2/11 Walkway Pads
2/11 PV Install
1/28 Exterior Infill Framing
2/4 Sheathing
2/14 WRB
2/24 RO Prep/Flashings
3/3 Storefront Install
3/31 Air/Water Testing
3/31 Exterior Furring/Insulation
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
343 Awnings 10 days Tue 5/6/25 Mon 5/19/25
344 Siding 19 days Wed 4/9/25 Mon 5/5/25
345 Soffits 10 days Tue 5/20/25 Tue 6/3/25
346 Exterior Paint 13 days Tue 5/6/25 Thu 5/22/25
347 Gutters/Downspouts 5 days Tue 5/6/25 Mon 5/12/25
348 Interior Build Out 134 days Tue 2/4/25 Tue 8/12/25
349 Electrical 139 Housekeeping Pad 1 day Tue 2/4/25 Tue 2/4/25
350 Mechanical 127 Housekeeping Pad 1 day Tue 2/4/25 Tue 2/4/25
351 Early Overhead MEPS rough-in 8 days Tue 2/11/25 Thu 2/20/25
352 Start Interior Framing Milestone 0 days Thu 2/20/25 Thu 2/20/25
353 Electrical 139 Framing 1 day Wed 2/5/25 Wed 2/5/25
354 Electrical 139 Pre Rock Interior Walls 1 day Thu 2/6/25 Thu 2/6/25
355 Electrical 139 Pre Rock Inspection 1 day Fri 2/7/25 Fri 2/7/25
356 Electrical 139 Pre Rock Tape 1 day Mon 2/10/25 Mon 2/10/25
357 Electrical 139 Fire Rated Plywood 1 day Tue 2/11/25 Tue 2/11/25
358 Interior Framing 13 days Thu 2/20/25 Mon 3/10/25
359 Interior Framing Inspection 1 day Tue 3/11/25 Tue 3/11/25
360 Interior Door Frames/Storefronts 12 days Tue 3/11/25 Wed 3/26/25
361 Fire Sprinkler Rough 12 days Thu 3/6/25 Fri 3/21/25
362 Plumbing Rough 15 days Thu 3/6/25 Wed 3/26/25
363 Mechanical Rough 15 days Thu 3/13/25 Wed 4/2/25
364 Electrical Rough 15 days Thu 3/6/25 Wed 3/26/25
365 PV Rough 12 days Tue 3/11/25 Wed 3/26/25
366 LV Rough 15 days Thu 3/13/25 Wed 4/2/25
367 Security/Access Control Rough 12 days Tue 3/11/25 Wed 3/26/25
368 Fire Alarm Rough 12 days Tue 3/11/25 Wed 3/26/25
369 Fire Sprinkler Rough Inspection 1 day Mon 3/24/25 Mon 3/24/25
370 Plumbing Rough Inspection 1 day Thu 3/27/25 Thu 3/27/25
371 Mechanical Rough Inspection 1 day Thu 4/3/25 Thu 4/3/25
372 Electrical Rough Inspection 1 day Thu 3/27/25 Thu 3/27/25
373 LV Rough Inspection 1 day Thu 4/3/25 Thu 4/3/25
374 Fire Alarm Rough Inspection 1 day Thu 3/27/25 Thu 3/27/25
375 Insulation 3 days Fri 4/4/25 Tue 4/8/25
376 Insulation Inspection 1 day Wed 4/9/25 Wed 4/9/25
377 Hang Drywall 15 days Tue 4/8/25 Mon 4/28/25
378 Drywall Cover Inspection 1 day Tue 4/29/25 Tue 4/29/25
379 Fire Rated Plywood 3 days Wed 4/30/25 Fri 5/2/25
380 Finish Drywall 15 days Thu 4/24/25 Wed 5/14/25
381 Interior Paint 10 days Mon 5/12/25 Fri 5/23/25
382 Fire Sprinkler Trim 10 days Tue 5/27/25 Mon 6/9/25
383 Plumbing Trim 22 days Tue 5/27/25 Wed 6/25/25
384 Mechanical Trim 17 days Tue 5/27/25 Wed 6/18/25
385 Electrical Trim 20 days Tue 5/27/25 Mon 6/23/25
386 LV Trim 15 days Tue 5/27/25 Mon 6/16/25
387 Security/Access Control Trim 15 days Tue 5/27/25 Mon 6/16/25
388 Fire Alarm Trim 15 days Tue 5/27/25 Mon 6/16/25
5/6 Awnings
4/9 Siding
5/20 Soffits
5/6 Exterior Paint
5/6 Gutters/Downspouts
2/4 Electrical 139 Housekeeping Pad
2/4 Mechanical 127 Housekeeping Pad
2/11 Early Overhead MEPS rough-in
2/20 Start Interior Framing Milestone
2/5 Electrical 139 Framing
2/6 Electrical 139 Pre Rock Interior Walls
2/7 Electrical 139 Pre Rock Inspection
2/10 Electrical 139 Pre Rock Tape
2/11 Electrical 139 Fire Rated Plywood
2/20 Interior Framing
3/11 Interior Framing Inspection
3/11 Interior Door Frames/Storefronts
3/6 Fire Sprinkler Rough
3/6 Plumbing Rough
3/13 Mechanical Rough
3/6 Electrical Rough
3/11 PV Rough
3/13 LV Rough
3/11 Security/Access Control Rough
3/11 Fire Alarm Rough
3/24 Fire Sprinkler Rough Inspection
3/27 Plumbing Rough Inspection
4/3 Mechanical Rough Inspection
3/27 Electrical Rough Inspection
4/3 LV Rough Inspection
3/27 Fire Alarm Rough Inspection
4/4 Insulation
4/9 Insulation Inspection
4/8 Hang Drywall
4/29 Drywall Cover Inspection
4/30 Fire Rated Plywood
4/24 Finish Drywall
5/12 Interior Paint
5/27 Fire Sprinkler Trim
5/27 Plumbing Trim
5/27 Mechanical Trim
5/27 Electrical Trim
5/27 LV Trim
5/27 Security/Access Control Trim
5/27 Fire Alarm Trim
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
389 SAT-1 Grid 10 days Tue 5/27/25 Mon 6/9/25
390 WD-1 10 days Tue 5/27/25 Mon 6/9/25
391 SAT-1 Fire Sprinkler Rough 5 days Tue 6/10/25 Mon 6/16/25
392 SAT-1 Mechanical Trim 10 days Tue 6/10/25 Mon 6/23/25
393 SAT-1 Electrical Trim 13 days Tue 6/10/25 Thu 6/26/25
394 SAT-1 LV Rough 5 days Tue 6/10/25 Mon 6/16/25
395 SAT-1 Security/Access Control Rough 5 days Tue 6/10/25 Mon 6/16/25
396 SAT-1 Fire Alarm Rough 5 days Tue 6/10/25 Mon 6/16/25
397 SAT-1 Fire Sprinkler Rough Inspection 1 day Tue 6/17/25 Tue 6/17/25
398 SAT-1 Mechanical Rough Inspection 1 day Tue 6/24/25 Tue 6/24/25
399 SAT-1 Electrical Rough Inspection 1 day Fri 6/27/25 Fri 6/27/25
400 SAT-1 LV Rough Inspection 1 day Tue 6/17/25 Tue 6/17/25
401 SAT-1 Fire Alarm Rough Inspection 1 day Tue 6/17/25 Tue 6/17/25
402 SAT-1 Inspection 1 day Mon 6/30/25 Mon 6/30/25
403 Drop SAT-1 Tile 10 days Tue 7/1/25 Tue 7/15/25
404 SAT-1/WD-1 Fire Sprinkler Trim 2 days Wed 7/16/25 Thu 7/17/25
405 SAT-1/WD-1 Mechanical Trim 5 days Tue 5/27/25 Mon 6/2/25
406 SAT-1/WD-1 Electrical Trim 5 days Tue 5/27/25 Mon 6/2/25
407 SAT-1/WD-1 LV Trim 5 days Wed 7/16/25 Tue 7/22/25
408 SAT-1/WD-1 Security/Access Control Trim 5 days Wed 7/16/25 Tue 7/22/25
409 SAT-1/WD-1 Fire Alarm Trim 5 days Wed 7/16/25 Tue 7/22/25
410 Polished Concrete 5 days Tue 6/10/25 Mon 6/16/25
411 Sealed Concrete 1 day Wed 2/5/25 Wed 2/5/25
412 Ceramic Tile 10 days Tue 5/27/25 Mon 6/9/25
413 Carpet Tile 12 days Wed 7/16/25 Thu 7/31/25
414 VCT 5 days Tue 5/27/25 Mon 6/2/25
415 LVT 5 days Tue 5/27/25 Mon 6/2/25
416 Casework 9 days Tue 5/27/25 Fri 6/6/25
417 Countertops 5 days Mon 6/23/25 Fri 6/27/25
418 Mirrors 1 day Mon 6/30/25 Mon 6/30/25
419 Rubber Base 5 days Fri 8/1/25 Thu 8/7/25
420 Appliances 3 days Fri 8/8/25 Tue 8/12/25
421 Office Equipment/Furnishes 3 days Fri 8/8/25 Tue 8/12/25
422 Hang Doors 10 days Tue 5/27/25 Mon 6/9/25
423 Door Hardware 15 days Tue 6/10/25 Mon 6/30/25
424 Wall Coverings 5 days Tue 5/27/25 Mon 6/2/25
425 FRP 5 days Tue 5/27/25 Mon 6/2/25
426 Corner Guards 1 day Fri 8/8/25 Fri 8/8/25
427 FEC 2 days Tue 5/27/25 Wed 5/28/25
428 Restroom Partitions 7 days Tue 6/10/25 Wed 6/18/25
429 Restroom Accessories 7 days Tue 6/10/25 Wed 6/18/25
430 Privacy Film 5 days Tue 6/10/25 Mon 6/16/25
431 Signage 2 days Tue 6/10/25 Wed 6/11/25
432 Window Blinds 5 days Tue 6/17/25 Mon 6/23/25
433 Building Systems 59 days Tue 5/27/25 Mon 8/18/25
434 Fire Sprinkler 48 days Tue 5/27/25 Fri 8/1/25
5/27 SAT-1 Grid
5/27 WD-1
6/10 SAT-1 Fire Sprinkler Rough
6/10 SAT-1 Mechanical Trim
6/10 SAT-1 Electrical Trim
6/10 SAT-1 LV Rough
6/10 SAT-1 Security/Access Control Rough
6/10 SAT-1 Fire Alarm Rough
6/17 SAT-1 Fire Sprinkler Rough Inspection
6/24 SAT-1 Mechanical Rough Inspection
6/27 SAT-1 Electrical Rough Inspection
6/17 SAT-1 LV Rough Inspection
6/17 SAT-1 Fire Alarm Rough Inspection
6/30 SAT-1 Inspection
7/1 Drop SAT-1 Tile
7/16 SAT-1/WD-1 Fire Sprinkler Trim
5/27 SAT-1/WD-1 Mechanical Trim
5/27 SAT-1/WD-1 Electrical Trim
7/16 SAT-1/WD-1 LV Trim
7/16 SAT-1/WD-1 Security/Access Control Trim
7/16 SAT-1/WD-1 Fire Alarm Trim
6/10 Polished Concrete
2/5 Sealed Concrete
5/27 Ceramic Tile
7/16 Carpet Tile
5/27 VCT
5/27 LVT
5/27 Casework
6/23 Countertops
6/30 Mirrors
8/1 Rubber Base
8/8 Appliances
8/8 Office Equipment/Furnishes
5/27 Hang Doors
6/10 Door Hardware
5/27 Wall Coverings
5/27 FRP
8/8 Corner Guards
5/27 FEC
6/10 Restroom Partitions
6/10 Restroom Accessories
6/10 Privacy Film
6/10 Signage
6/17 Window Blinds
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025
435 Fire Riser 5 days Tue 5/27/25 Mon 6/2/25
436 FDC 3 days Tue 6/3/25 Thu 6/5/25
437 Fire Sprinkler Start UP/Pretest 5 days Mon 7/28/25 Fri 8/1/25
438 Plumbing 48 days Tue 5/27/25 Fri 8/1/25
439 GWH-1 10 days Tue 5/27/25 Mon 6/9/25
440 Domestic Water Start Up/Pretest 5 days Mon 7/28/25 Fri 8/1/25
441 Mechanical 16 days Mon 7/28/25 Mon 8/18/25
442 Remove/Replace Filters 1 day Mon 7/28/25 Mon 7/28/25
443 Mechanical Start Up 10 days Tue 7/29/25 Mon 8/11/25
444 TAB/Commissioning 5 days Tue 8/12/25 Mon 8/18/25
445 Electrical 24 days Mon 6/23/25 Fri 7/25/25
446 Electrical Room Build Out 10 days Mon 6/23/25 Mon 7/7/25
447 Permanent Power 24 days Mon 6/23/25 Fri 7/25/25
448 AHJ Inspection 1 day Mon 6/23/25 Mon 6/23/25
449 Meter Inspection 1 day Tue 6/24/25 Tue 6/24/25
450 Meter Install 1 day Tue 7/1/25 Tue 7/1/25
451 Schedule PGE 15 days Wed 7/2/25 Wed 7/23/25
452 Set Transformer/Permanent power 2 days Thu 7/24/25 Fri 7/25/25
453 LV 27 days Mon 6/30/25 Wed 8/6/25
454 Access Control Panel 5 days Mon 6/30/25 Mon 7/7/25
455 Intrusion Detection Panel 5 days Tue 7/8/25 Mon 7/14/25
456 4-Post Rack/UPS 5 days Tue 7/15/25 Mon 7/21/25
457 2-Post Rack/UPS 5 days Tue 7/15/25 Mon 7/21/25
458 AV Equipment Rack 5 days Tue 7/22/25 Mon 7/28/25
459 Network Equipment Rack/UPS 5 days Tue 7/29/25 Mon 8/4/25
460 Fire Alarm 8 days Mon 7/28/25 Wed 8/6/25
461 Fire Alarm Panel 5 days Mon 7/28/25 Fri 8/1/25
462 Fire Alarm Start Up/Pretest 3 days Mon 8/4/25 Wed 8/6/25
463 Close Out 67 days Tue 7/8/25 Thu 10/9/25
464 Fire Sprinkler Final Inspection 2 days Mon 8/4/25 Tue 8/5/25
465 Plumbing Final Inspection 2 days Mon 8/4/25 Tue 8/5/25
466 Mechanical Final Inspection 4 days Tue 8/12/25 Fri 8/15/25
467 Electrical Final Inspection 2 days Tue 7/8/25 Wed 7/9/25
468 LV Final Inspection 1 day Tue 8/5/25 Tue 8/5/25
469 Fire Alarm Final Inspection 4 days Thu 8/7/25 Tue 8/12/25
470 Building Final Inspections 4 days Mon 8/18/25 Thu 8/21/25
471 Bulk Clean 3 days Fri 8/22/25 Tue 8/26/25
472 Pre Punch 6 days Wed 8/27/25 Thu 9/4/25
473 Final Clean 4 days Fri 9/5/25 Wed 9/10/25
474 Punch Walk 1 day Thu 9/11/25 Thu 9/11/25
475 Substantial Completion 0 days Wed 9/10/25 Wed 9/10/25
476 Punchlist Corrections 20 days Fri 9/12/25 Thu 10/9/25
477 Final Completion 0 days Thu 10/9/25 Thu 10/9/25
5/27 Fire Riser
6/3 FDC
7/28 Fire Sprinkler Start UP/Pretest
5/27 GWH-1
7/28 Domestic Water Start Up/Pretest
7/28 Remove/Replace Filters
7/29 Mechanical Start Up
8/12 TAB/Commissioning
6/23 Electrical Room Build Out
6/23 AHJ Inspection
6/24 Meter Inspection
7/1 Meter Install
7/2 Schedule PGE
7/24 Set Transformer/Permanent power
6/30 Access Control Panel
7/8 Intrusion Detection Panel
7/15 4-Post Rack/UPS
7/15 2-Post Rack/UPS
7/22 AV Equipment Rack
7/29 Network Equipment Rack/UPS
7/28 Fire Alarm Panel
8/4 Fire Alarm Start Up/Pretest
8/4 Fire Sprinkler Final Inspection
8/4 Plumbing Final Inspection
8/12 Mechanical Final Inspection
7/8 Electrical Final Inspection
8/5 LV Final Inspection
8/7 Fire Alarm Final Inspection
8/18 Building Final Inspections
8/22 Bulk Clean
8/27 Pre Punch
9/5 Final Clean
9/11 Punch Walk
9/10 Substantial Completion
9/12
10/9
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 2025