Cinnamon - Hunter RFP - Addendum #1 - Hunter Bid Schedule.pdf

PDF 136 KB Posted

Attached to
Cinnamon Mountain Road and Hunter Hill Road Drainage and Paving Rehabilitation
Solicitation number
24-07
Issued by
Grand County, Colorado

About this file

This document is an Addendum Order #1 for the Cinnamon Mountain Road & Hunter Hill Drainage & Paving Rehabilitation project, issued by the Town of Mt. Crested Butte, Colorado, and prepared by SGM Inc. The addendum, dated March 18, 2024, modifies the original bid documents for a road and drainage rehabilitation project, with the bid date set for April 01, 2024. Key changes include the deletion of Hunter Hill Road bid item 6-H in its entirety and the increase of Hunter Hill Road bid item 19-H (Subgrade Stabilization) to 750 Square Yards. The project involves drainage and paving improvements for sections of Cinnamon Mountain Road and Hunter Hill Road, with work including stormwater drainage, culvert replacement, drainage pipe installation, and Full Depth Reclamation of roadway surfaces.

The revised bid schedule provides detailed line items for the project, with quantities specified for various elements such as mobilization, curb and gutter removal, sidewalk removal, full depth reclamation, aggregate base course, ditch improvements, culvert cleaning, and hot mix asphalt placement. A fixed amount of $25,000 is allocated for minor contract revisions. The addendum requires contractors to sign and return the form with their bid documents, indicating acknowledgment of the changes. The project has a completion deadline of September 13, 2024, and bid documents are available on the Town's website at https://mtcb.colorado.gov/request-for-proposals.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM ORDER #1

DATE: March 18, 2024

NAME OF PROJECT: Cinnamon Mountain Road & Hunter Hill Drainage & Paving Rehabilitation

PROJECT BID DATE: April 01, 2024

OWNER: Town of Mt. Crested Butte Colorado

ENGINEER: SGM Inc.

The following clarifications and changes and/or clarifications are made to the Contract Documents:

1. Hunter Hill Road bid item 6-H: This bid item has been deleted in its entirety. Hunter Hill Road will only require geogrid as part of bid item 19-H Subgrade Stabilization.

2. Hunter Hill Road bid item 19-H: This bid item has been increased to 750 Square Yards

3. Hunter Hill Road revised bid schedule is attached to this addendum document.

4. This addendum form must be signed and returned with the contractors bid forms.

PREPARED BY:

/s/ G. Burgess____SGM Inc.

ADDENDUM ACKNOWLEDGED BY (contractor):

(contractor signature) Date

Contract Estimated

Item # Quantity Unit Description Unit Price Total Price

1-H 1 LS Mobilization and Demobilization

2-H 227 LF Remove Curb and Gutter

3-H 845 SF Remove Valley Pan

4-H 110 SY Remove Concete Sidewalk and Flatwork

5-H 4,100 SY Full Depth Reclamation

6-H NA Not Used NA NA

7-H 110 TON Aggregate Base Coarse

8-H 605 LF Ditch Improvements

9-H 100 LF Culvert Cleaning

10-H 227 LF New Curb and Gutter

11-H 100 SY Concrete Flat Work

12-H 285 LF New Valley Pan - 36"

13-H 1 EACH Storm Inlet with Valley Pan Inlet/Grate

14-H 1 EACH Storm MH

15-H 170 LF 18" HDPE Pipe/Culvert

16-H 3 EACH Flared End Sections (HDPE Culvert) 18"

17-H 210 LF Electrical Conduit (pipe only - no conductors) 1-1/2" Dia.

18-H 740 TONS Hot Mix Asphalt (prep and place)

19-H 750 SY Subgrade Stabilization

20-H 1 LS Traffic Control

21-H 1 LS Construction Staking/Survey

22-H 1 LS Minor Contract Revisions $25,000.00 $25,000.00

Base Bid Total:

Project Total:

Project Bid Schedule (revised per addenum 1 )

Mt Crested Butte

Hunter Hill Road

MTCB - Cinnamon-Hunter - Addendum 1 - Hunter (Posted 03-19-2024)
MTCB - Cinnamon-Hunter - Addendum 1 - Hunter Bid Schedule (Posted 03-18-2024)

File details come from the government source that posted it. Updated .