Chiller Installation RFP.pdf

PDF 943 KB Posted

Attached to
Chiller Installation
Solicitation number
RFP EHP 180000002222 1
Issued by
Bay County, Elsie Village, Michigan

About this file

Summary

This is a Request for Proposal (RFP) issued by Essexville-Hampton Public Schools (E-HPS) in Michigan for the installation of two owner-purchased air-cooled chillers at Garber High School's Central Chilled Water Plant. The project requires proposals for chiller installation services, with each unit rated at 75 tons (150 tons total capacity) operating at 460/60/3 phase voltage. The chillers will support a chilled water system with a temperature range of 55°F entering/45°F leaving and a flow rate of 360 gallons per minute total. Proposals were due by April 30, 2018, at 1:10 PM EST, with a mandatory walk-through scheduled for April 26, 2018, at 10:30 AM. The contract award was required by July 10, 2018, and proposals could not be withdrawn for ninety days following the submission deadline. All work must comply with the Michigan Mechanical Code (2015) and Michigan Electrical Code (NEC 2014 with Michigan Part 8 amendments), with final inspection and approval by the Authority Having Jurisdiction required before project acceptance.

E-HPS will accept proposals on bidder letterhead with itemized pricing for each unit, applicable discounts, and optional pricing for energy-efficiency features. All quoted prices shall be FOB Essexville, Michigan, with bidders required to accept E-HPS's standard payment terms. The RFP specifies that chillers must be new, genuine manufacturer products delivered in original packaging with full warranty eligibility. Prevailing wage requirements apply to the project, with separate wage schedules provided for road builder and commercial classifications in Bay County, Michigan. All contractors and subcontractors must comply with Michigan's Prevailing Wages on State Projects Act (Public Act 166 of 1965), maintain accurate wage and benefit records, and post prevailing wage rates at the job site. The successful bidder must obtain all necessary permitting through the State of Michigan and coordinate with the controls contractor for integration of the new chillers into the existing Building Logix Control System.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP #4/17/2018 Essexville-Hampton Public Schools- Chiller Purchase April 17, 2018

GLCPC bill@jwjensenpe.com 810-701-8768

Pa ge

Essexville-Hampton Public Schools Garber High School

Central Chilled Water Plant Upgrade

CHILLERS Installation

REQUEST FOR PROPOSAL

RFP #4/17/2018 CHILLERS INSTALLATION

Owner Purchased Chiller Installation

PROP0SALS DUE:

MONDAY, April 30, 2018

1:10 PM EST

OWNER CONTACTS:

Matthew Cortez: cortezm@e-hps.net;

Steve Barlow: barlows@e-hps.net 303 Pine Street Essexville, Michigan 48732 989-984-9700

PROJECT ENGINEER/ CONTACT:

J. William Jensen, P.E.

bjensen@glcpc.com 810-701-8768 mailto:cortezm@e-hps.net mailto:bjensen@glcpc.com

Pa ge

NOTICE!

PROPOSAL: Essexville-Hampton Public Schools (E-HPS) is soliciting bids for the Installation of

Owner purchased chillers for E-HPS Garber Chiller Project. Proposals are due to E-HPS; Attention Matthew Cortez on April 30th, 2018 no later than 1:10 PM. E-mailed Protected Proposals will be accepted using a “Return Receipt, Read Format”. Manditory Walk Through 4/26/18 at 10:30am in Garber High School.

RIGHT TO REJECT: Essexville-Hampton Public Schools (E-HPS) reserves the right to accept or reject any and all proposals, to negotiate terms of proposal(s) with successful vendor(s), to accept a proposal that is not the lowest cost, and to accept the proposal(s) that is in the best interest of E-HPS

WITHDRAWAL OF ANY PROPOSALS is prohibited for a period of ninety (90) days after the proposal due date.

LATE, INCOMPLETE AND NON-CONFORMING PROPOSALS: E-HPS reserves the right to reject without evaluation late, incomplete or otherwise non-conforming proposals.

COMPLETE PROPOSALS: All proposals must contain terms of purchase and delivery in writing. E-HPS will negotiate the actual delivery terms and timetable with the successful manufacturer’s representative, but each proposal must include the anticipated time frame during which E-HPS may reasonably expect materials and equipment to be delivered. E-HPS will not be responsible for any ancillary charges, costs, and/or fees not expressly delineated in the terms of the proposal.

PRESENTATIONS: Prospective bidders are requested to prepare a reference list of owners of the proposed equipment and to provide complete “submittal” documents for approval.

QUESTIONS: Prospective bidders are solely responsible for understanding the requirements of this RFP. Questions regarding any part of this proposal should be submitted in writing to the OWNER via e-mail using “Read Receipt” format.

PROJECT ENGINEER:

J. William Jensen, P.E.

Great Lakes Critical Power and Cooling bill@jwjensenpe.com

810-701-8768

OWNER:

Matthew T. Cortez, Superintendent 303 Pine Street Essexville, Michigan 48732 989-984-9700

Pa ge

INTRODUCTION

This Request for Proposal #4/17/2018 is released by Essexville-Hampton Public Schools (E-HPS) through their Project Engineer for the “Installation of Owner Purchased Chillers” of a chiller arrangement for the Garber Chiller Project.

SECTION 1

GENERAL INFORMATION

Essexville-Hampton Public Schools (E-HPS) intends to solicit bids for the “Owner Purchased Chillers Installation” of 2 AIR COOLED CHILLERS for the Central Chilled Water Plant System Upgrade at Garber High School. The total chilled water plant capacity is 150 tons equally split between 2 chillers (75 tons each). Chiller space is limited to the existing chiller location and rigging new chillers in place is very complex. The installation of the new chillers and demolition of the existing chiller will be a separate contract.

The requirements included in this proposal are complete. The representations made by E-HPS herein are accurate, true and complete to the best of our knowledge. E-HPS, through their Project Engineer prefers to work with only one (1) contact person throughout the proposal process. Please appoint one (1) representative from your firm as your contact for this proposal. This person will be responsible for all communications with the OWNER and Project Engineer that relate to this Request for Proposal. The OWNER will receive all bids and communicate directly with your primary contact for the project.

Your final proposal must be complete and presented in its entirety. All conditions, terms, costs, charges and fees must be included in the proposal. Should E-HPS accept your proposal, any terms, conditions, costs, charges and/or fees excluded from your proposal at the time of submission shall remain excluded and will become the responsibility of the winning bidder.

All proposals must be submitted in writing with all suggested chiller documentation attached.

MULTIPLE CHILLER SELECTIONS and information may be submitted for the OWNERS APPROVAL. Proposals must be signed by a representative who is duly authorized to make such representations to E-HPS on behalf of your firm. Your proposal will form the basis of a purchase contract with E-HPS and should include all equipment and materials that, in your judgment, are necessary to meet the requirements of this proposal.

Pa ge

SECTION 2

TERMS AND CONDITIONS

2.01. Your complete and entire response to this RFP must be received by the OWNER prior to 1:10 pm (EST) April 30th, 2018. Please MAIL or DELIVER your response, with supporting documentation, IN WRITING. Your response should include all requested and required information, as well as any supporting data needed to complete your response. Late responses will not be considered. Bidders are solely responsible for confirming that their responses were received in a timely way. A Verification phone call to the OWNER is acceptable.

2.02. Questions, uncertainties, noted discrepancies and omissions regarding this RFP shall be reported immediately in writing to the OWNER. Should any reported issues require clarification, written instructions or an addendum to the RFP will be distributed to all potential bidders.

E-HPS will not accept any responsibility for any oral interpretation of the requirements. Bidders should rely only on the written responses of the OWNER. E-HPS reserves the right to solicit additional information from bidders to aid our determination of the bid that best meets the needs of E-HPS If our request for additional information on a proposal is not met in a timely way, E-HPS reserves the right to reject the proposal as non-conforming.

2.03. E-HPS reserves the right to reject or accept any bids, in part or whole; select bidders whose proposals best meet the needs of E-HPS without respect to the lowest cost proposal;

and negotiate terms of the proposal to ensure the best interests of E-HPS are met. E-HPS does not assume any contractual obligations or duties as the result of issuing this RFP. No employment relationship will be assumed between E-HPS and the successful bidder.

2.04. Bidders are not entitled to use E-HPS’s name, service mark(s), trademarks or trade names without the express written permission of E-HPS

2.05. E-HPS will evaluate each bid received using the following criteria, listed here in no particular order of importance:

a. The bidder’s ability to satisfy each term and condition fully

b. Compliance with the specifications stated herein

c. Experience with delivering the requirements of the specification

d. Cost (including pricing and price protection)

e. References from previous customers for work of similar scope

f. Interviews as required by E-HPS

g. Other factors not specifically expressed here that are relevant to determining which proposal will succeed.

2.06. Proposals may not be withdrawn for ninety (90) days from the time of issue. After ninety (90) days, proposals may be withdrawn by way of a written request directed to the OWNER.

Successor proposals may not be substituted for a withdrawn proposal. Withdrawal of a proposal

Pa ge constitutes disqualification from the bid process, should E-HPS not render a decision within ninety

(90) days of the response due date.

2.07. Once the successful proposal has been determined and awarded, either party may withdraw from this agreement by giving the other party at least ninety (90) days’ prior written notice of the termination date. Termination or cancellation of this agreement does not affect the collection, enforcement or validity of any accrued obligations between the bidder and E-HPS

2.08. Once the successful proposal has been determined and awarded, modifications deemed necessary to correct errors found to be the sole fault of the bidder and to satisfy performance of the agreement shall be made expediently and at no additional cost to E-HPS This clause will survive the termination and/or expiration of this agreement without respect to the cause or reason for the error.

2.09. No information, report, etc. developed in connection with this RFP may be reproduced without E-HPS’s prior written consent. No portion of this RFP may be reproduced without E-HPS’s prior written consent.

2.10. The successful bidder must perform all work unless E-HPS specifically approves subcontracting in writing prior to the commencement of any work related to this RFP.

2.11. The successful bidder is an independent contractor, licensed and bonded as necessary, and is solely responsible for employment, acts, omissions, insurance, control and direction of its employees. The bidder agrees to indemnify and hold harmless E-HPS, its trustees, officers, employees and agents from any and all damages, injury, loss, claims, demands, or causes of action in the event that the bidder fails or neglects to provide appropriate insurance coverage for its employees while working in performance of this contract at E-HPS, including but not limited to payment of any claims.

2.12. Any personal injury to the bidder, its successors, assigns, employees, agents, subcontractors or third parties or any property damage incurred in the performance of this agreement shall be the responsibility of the bidder. The bidder agrees to restore or make whole any loss of or damage to the property of E-HPS incurred during the performance of this agreement.

2.13. Bidder warrants that all equipment offered for sale to E-HPS are all new materials, genuine products of the chosen manufacturer, delivered in original packaging with all parts and manuals, able to be registered for warranty purposes by E-HPS, eligible for the full manufacturer’s warranty period and warranted as described by the manufacturer.

2.14. Bidder agrees to accept E-HPS’s standard payment terms. Prices quoted in bidder’s response shall be FOB E-HPS, Essexville, Michigan unless otherwise specified. All items on the bidder’s response will be itemized, and all charges and discounts shall be clearly shown.

Pa ge

SECTION 3

CHILLER SYSTEM PERFORMANCE REQUIREMENTS

Capacity And Performance:

Nominal Capacity 2 UNITS @75 tons each A TOTAL OF 150 TONS Chilled Water Temp Range 55 EWT-45 LWT 10 degree DELTA TEMP Chilled Water Flow Rate 180 GPM Each 360 GPM total The chiller plant will be converted to “variable primary system flow” and a flow bypass will be installed.

FEATURES DESIRED:

• Voltage is 460/60/3 phase

• The 75 Tons (each) required is NOMINAL and CAN BE CHANGED per the

OWNER EVALUATION.

• Single Point Power per chiller.

• Energy Management Module for Connection to Owner BAS using BACnet.

OWNER Intends to use their existing BUILDING LOGIX NETWORK for integration.

• Sound Power and Pressure Ratings

• Grooved fitting on evaporator piping connections.

• All External sensors and flow switches are to be included

• Compressor Type is Scroll or Digital Scroll constant or variable speed as identified in your proposal for advanced energy savings.

• Indicate refrigerant type and quantity.

• Premium Spring Steel ISOLATION IS REQUIRED.

JOB SITE CONDITIONS:

• The new chillers will be set on existing steel from the removal of an existing chiller

• Chiller dimensional information WILL BE PROVIDED.

BID FORM

E-HPS will accept proposals on your letterhead which should include all appropriate prices for each size of unit as individual pricing, any discounts and individual option pricing for features that you suggest for added energy and operating efficiency.

All Proposals should clearly indicate the RFP #4/17/2018 and should acknowledge the Terms and Conditions of E-HPS as reflected herein. PLEASE INDICATE RECEIPT OF THIS RFP by RETURN RECEIPT.

Essexville-Hampton Public Schools Chilled Water Plant Renovation April 17, 2018

Essexville-Hampton Public Schools

Garber High School

Chilled Water Plant Renovation Project

GENERAL REQUIREMENTS:

1. Integrated Project Delivery Method:

� The owner, Essexville-Hampton Public Schools (E-HPS) wishes to procure this project using the Integrated Project Delivery Method. The MECHANICAL CONTRACTOR will be the “PRIME” contractor for this project.

� The owner intends to PREPURCHASE the CHILLERS for this project.

� The owner requests that all CONTROL WORK is “BY OTHERS”. The Prime contractor will coordinate with the CONTROLS CONTRACTOR for all integration of the new chillers and VFD’s into the existing Building Logix Control System.

� All CHILLER field mounted devices, such as FLOW SWITCHES, SENSORS and other direct chiller related controls are to be installed by the PRIME CONTRACTOR.

� The owner requests that all ELECTRICAL work is included in the “PRIME BID”.

2. Submittals:

� The Prime Contractor will provide submittals for approval on all valves, fittings and other major items provided by the contractor for this project.

� The Electrical sub-contractor will provide submittals for all disconnects starters and other major electrical components for this project.

� All contractors will be provided all necessary information required to properly receive, install and start the chillers and VFD’s and any other “owner provided” equipment and material.

MECHANCIAL SPECIFICATIONS

3. Demolition Methods and Materials:

General

� The Prime contractor is responsible for removal of all mechanical material as identified on the drawings and herein in a safe and clean manner. A daily cleanup of the work site is mandatory and all material is to be removed either by contractor’s truck or by the placement of a dumpster at the contractor’s expense.

� The existing chiller is to be removed immediately during rigging from the roof.

� Electrical demolition of conduits, disconnects, wiring and other electrical components is the responsibility of the electrical sub-contractor.

� The Prime contractor MUST document the safe and proper removal and disposal of the refrigerant (R-22) in the existing Trane Chiller.

� The DEMOLITION schedule and duration will be coordinated based on the final selection of Prime Contractor, availability of new chillers and the owners operating schedule.

� The owner reserves the right to salvage any and all material from the site by coordinating with the Prime contractor’s crew on the placement of such material.

4. Basic mechanical installation:

General

� The Prime contractor is responsible to provide and install all material not identified as “by others” or “by Owner”. The Chillers have been pre-purchased by the owner for delivery to the site. The Prime contractor will provide all site coordination necessary for offloading and handling of the chillers including crane and rigging. Final setting in place of the chillers is the Prime contractor’s responsibility.

� All mechanical work is to be provided consistent with the State of Michigan Mechanical Code 2015 and is to be inspected by the State recognized Authority Having Jurisdiction (AHJ). The final acceptance of all work by the AHJ must be provided to the “owner” prior to final acceptance by the “owner”. This includes all permitting through the State of Michigan.

� The system is designed as “VARIABLE PRIMARY FLOW” and includes a MINIMUM FLOW BYPASS with CONTROL VALVE and Chiller ISOLATION VALVES.

� The existing chilled water pumps (2) will be reused with a NEW VFD (Yaskawa as base bid) added for the each pump.

Automatic pump alternation will be programmed at the Building Logix Control system.

Draining and Filling

� The Prime contractor is responsible for all labor and material to properly and safely drain all piping systems to be removed and/or modified during this project. All labor required to test and inspect the chilled water plant piping system after draining and refilling is the contractor’s responsibility. The scheduling of this work MUST be approved by the Engineer and the Owner with at least a 24 hour notice.

Piping

� All piping is to be clean and new Schedule 40. Grooved end joints and mechanical connections (Victaulic) are acceptable as well as welded connections where required by the final installation details. All pipe is to be routed “straight, level, plumb and square” and in a consistent path with other existing piping.

� Pipe hangers and supports may utilize existing anchor points from previous piping systems and may utilize existing pipe access openings and penetrations as necessary. The Prime contractor will provide a desired pipe routing plan to the engineer during the FINAL DESIGN process and PRIOR to installation for approval.

� All pipe systems are to be flushed clean and pressure tested prior to final acceptance by the “owner” and mechanical inspector. The engineer is to witness the pressure test and provide an approval for final cleaning and filling of the system.

Fittings and Valves

� Mechanical couplings, elbows and flanges to create a complete system may be Victaulic or approved equal. Both “flexible” and “fixed” type fittings are to be used to create a stable piping system. Fixed anchor points are to be included in the system to prevent significant pipe movement during normal pump starting and stopping.

� Automatic Isolation valves are to be “butterfly” type by BRAY or approved equal.

Insulation and Fire Stopping

� All chilled water pipe is to be insulated with 1½” wall fiberglass preformed pipe insulation with a protective aluminum cover. All elbows and fittings are to be insulated with fiberglass equal to 1 ½” wall with a preformed plastic covering.

� ALL piping above the roof, whether new or existing is to have new insulation with new protective cover.

� Any fire stopping required must be installed per the Hilti Fire Stopping method manual and must be submitted to the “engineer” for approval prior to installation.

Labeling

� All piping is to be labeled using printed labeling methods and directional arrows per SETON and installed per the ANSI/ASME A13.1-2007 Standard.

Chiller Installation:

� The Prime contractor is responsible to receive and set in place the chillers provided by the “owner”. The contractor will be provided all necessary installation, rigging and operation manuals to properly install the chillers and prepare them for operation. Each chiller will have the following minimum features at the inlet and outlet of ALL piping connections:

• Flexible connections

• Butterfly Isolation valves

• A Pressure gauge “manifold” to indicate entering and leaving pressures (Ashcroft 3 ½” dial or greater).

• Thermometers to indicate entering and leaving temperatures (Trerrice 9” flexible mount).

• Spring Vibration Isolation provided by the OWNER.

• Flow switch and sensors provided by the manufacturer.

• Single point power connection

Check, Test and System Startup:

� The entire piping system is to be flushed, cleaned, drained and then pressure tested for integrity prior to final filling.

The pressure test is to be witnessed by the AHJ and the engineer. All pump strainers are to be cleaned as required to remove all debris. Startup strainers are to be left in place during all cleaning and testing. Operating strainers are to be installed after all system leaks and testing is complete.

� The chiller manufacturer will provide factory authorized startup for both chillers. The Prime contractor will provide all necessary labor and material required by the manufacturer for assistance during startup.

� The Prime contractor will provide the assistance of a NEBB Certified Test and Balance Contractor for all work required to properly set all flow rates for both new and existing systems. The Prime contractor and the NEBB Certified test and balance contractor will coordinate all work with the Building Automation System installer to properly operate all systems, verify operating performance and make all necessary adjustments to achieve design operating performance. The final acceptance of this work will not occur until all systems are in full operating condition during the cooling season.

ELECTRICAL SPECIFICATIONS

Demolition Methods and Materials:

General:

� The electrical sub-contractor is responsible for the safe removal of all electrical components, wiring, raceways and materials identified by the Prime contractor during the design process. All circuits to be removed require that all conduit, wire, starters and other related equipment be removed back to the main panels.

� The owner reserves the right to salvage any and all material removed as part of this project for their use.

� In all cases any material that is to be scrapped must be removed from the jobsite by the contractor and the jobsite cleaned prior to installation of new equipment.

BASIC ELECTRICAL INSTALLATION:

General:

� The electrical sub-contractor is responsible to provide and install all material and equipment necessary to power the new chillers using the existing BUSS BAR system. New chiller disconnects are required at each chiller.

� TWO new VFD’s (Yaskawa as base bid) are required at the existing chilled water pump starter locations.

� Conduit, wiring and hardware are required for the CONTROL SYSTEM INTEGRATION. This work to be coordinated with the owners CONTROL CONTRACTOR.

� All electrical work is to be consistent with the State of Michigan Electrical Code (NEC 2014with Michigan Part 8 amendments). All work is to be inspected by the State recognized Authority Having Jurisdiction (AHJ). The final acceptance of all work by the AHJ must be provided to the “owner” prior to final acceptance by the “owner”.

Equipment and circuit isolation

� The electrical sub-contractor is responsible to properly isolate and “Lock Out- Tag Out” all electrical circuits that are removed or modified during this project. The scheduling of all equipment shut downs and circuit renovations must be coordinated with the owner 24 hours prior to the work.

Conduit and Raceways

� All conduits are to be “EMT” type with appropriate fittings and hangers per the NEC. Flexible conduit connections at equipment are appropriate with proper connections. All conduits are to follow basic “straight, level, plumb and square” routing methods and are to be consistent with existing routing methods. All necessary hangers, supports and connectors are to be provided and installed per the NEC guidelines.

Wiring and labeling:

� All insulated wire is to be THWN or THHN copper only. All wire terminations are to be properly identified by tagging and labeling. Labeling may be placed on the conduit as well. All low voltage wiring terminations are to be labeled.

Preliminary ARC-FLASH Hazard Analysis/ Short-Circuit/ Overcurrent Protection Coordination:

� The electrical contractor shall provide a limited NFPA 70E Study to provide proper labeling of all newly installed electrical equipment, control panels and other serviceable devices on this project. The entire facility is not required to be included in this study. All required “labels” for equipment are to be provided and installed by the electrical contractor along with permanent “TAGS” on each device indicating the equipment controlled by that device.

Electrical System Start up and Coordination:

� The electrical contractor is to participate in the startup of all major equipment and modified systems. Rotation, Voltage drop, Phase Imbalances and all other electrical system parameters are to be recorded under operating load for the new chillers. The electrical contractor will assist in the proper adjustments required for the proper operation of the chillers and pumps.

ATTACHMENT “A”

[Familial Disclosure Statement]

AFFIDAVIT OF ______________________________

(insert name of affiant)

STATE OF MICHIGAN )

)ss

COUNTY OF _________________ )

___________________________________ makes this Affidavit under oath and states as follows:

(insert name of affiant)

1. I am a/the:

G President G Vice-President G Chief Executive Officer G Member G Partner G Owner G Other (please specify) ________________________ of [insert name of contractor], a bidder for building entry installation services for Essexville

Hampton Public Schools.

2. I have personal knowledge and/or I have personally verified that the following are all of the familial relationships existing between the owner(s) and the employee(s) of the aforementioned contractor and the school district's superintendent and/or board members:

3. I have authority to bind the aforementioned contractor with the representations contained herein, and I am fully aware that the school district will rely on my representations in evaluating bids for the required services.

4. I declare the above information to be true to the best of my knowledge, information and belief. I could completely and accurately testify regarding the information contained in this affidavit if requested to do so.

(signature of affiant)

Dated: ________________

Subscribed and sworn before me in _________________ County, Michigan, on the ___ day of _________________, 201____ ____________________________________________(signature) _____________________________________________ (printed) Notary public, State of Michigan, County of ________________ My Commission expires on _____________________________ Acting in the County of ________________________________

ATTACHMENT “B”

[Iran Economic Sanctions Act Certification]

I am the _______(title)________ of _____________(bidder)_______________, or I am bidding in my individual capacity ("Bidder"), with authority to submit a binding bid for the installation of Interior Lock Master Rekey/replace to Essexville Hampton Public Schools. I have personal knowledge of the matters described in this Certification, and I am familiar with the Iran Economic Sanctions Act, MCL 129.311, et seq. ("Act"). I am fully aware that the school district will rely on my representations in evaluating bids.

I certify that Bidder is not an Iran-linked business, as that term is defined in the Act. I understand that submission of a false certification may result in contract termination, ineligibility to bid for three (3) years, and a civil penalty of $250,000 or twice the bid amount, whichever is greater, plus related investigation and legal costs.

(signature)

(printed)

(date)

STATE OF MICHIGAN

Wage and Hour Division

P.O. Box 30476 Lansing, Michigan 48909-7976 Toll Free: 1-855-4MI-WAGE (1-855-464-9243) www.michigan.gov/wagehour

Informational Sheet: Prevailing Wages on State Projects

P a g e | 1 of 11

REQUIREMENTS OF

THE PREVAILING WAGES ON STATE PROJECTS ACT, PUBLIC ACT 166 OF 1965

The State of Michigan determines prevailing rates pursuant to the Prevailing Wages on State Projects Act, Public Act 166 of 1965, as amended. The purpose of establishing prevailing rates is to provide minimum rates of pay that must be paid to workers on construction projects for which the state or a school district is the contracting agent and which is financed or financially supported by the state. By law, prevailing rates are compiled from the rates contained in collectively bargained agreements which cover the locations of the state projects. The official prevailing rate schedule provides an hourly rate which includes wage and fringe benefit totals for designated construction mechanic classifications. The overtime rates also include wage and fringe benefit totals. Please pay special attention to the overtime and premium pay requirements. Prevailing wage is satisfied when wages plus fringe benefits paid to a worker are equal to or greater than the required rate.

State of Michigan responsibilities under the law:

• The department establishes the prevailing rate for each classification of construction mechanic requested by a contracting agent prior to contracts being let out for bid on a state project.

Contracting agent responsibilities under the law:

• If a contract is not awarded or construction does not start within 90 days of the date of the issuance of rates, a re-determination of rates must be requested by the contracting agent.

• Rates for classifications needed but not provided on the Prevailing Rate Schedule, must be obtained prior to contracts being let out for bid on a state project.

• The contracting agent, by written notice to the contractor and the sureties of the contractor known to the contracting agent, may terminate the contractor's right to proceed with that part of the contract, for which less than the prevailing rates have been or will be paid, and may proceed to complete the contract by separate agreement with another contractor or otherwise, and the original contractor and his sureties shall be liable to the contracting agent for any excess costs occasioned thereby.

Contractor responsibilities under the law:

• Every contractor and subcontractor shall keep posted on the construction site, in a conspicuous place, a copy of all prevailing rates prescribed in a contract.

• Every contractor and subcontractor shall keep an accurate record showing the name and occupation of and the actual wages and benefits paid to each construction mechanic. This record shall be available for reasonable inspection by the contracting agent or the department.

• Each contractor or subcontractor is separately liable for the payment of the prevailing rate to its employees.

• The prime contractor is responsible for advising all subcontractors of the requirement to pay the prevailing rate prior to commencement of work.

• A construction mechanic shall only be paid the apprentice rate if registered with the United States Department of

Labor, Bureau of Apprenticeship and Training and the rate is included in the contract.

Enforcement:

A person who has information of an alleged prevailing wage violation on a state project may file a complaint with the State of Michigan. The department will investigate and attempt to resolve the complaint informally. During the course of an investigation, if the requested records and posting certification are not made available in compliance with Section 5 of Act 166, the investigation will be concluded and a referral may be made to the local prosecuting attorney.

MICHIGAN PREVAILING WAGE RATE SCHEDULE

For Parking Lot, Road, Highway, Bridge & Airport Construction

P a g e | 2 of 11

General Information Regarding Fringe Benefits Certain fringe benefits may be credited toward the payment of the Prevailing Wage Rate:

o If a fringe benefit is paid directly to a construction mechanic o If a fringe benefit contribution or payment is made on behalf of a construction mechanic o If a fringe benefit, which may be provided to a construction mechanic, is pursuant to a written contract or policy o If a fringe benefit is paid into a fund, for a construction mechanic

When a fringe benefit is not paid by an hourly rate, the hourly credit will be calculated based on the annual value of the fringe benefit divided by 2080 hours per year (52 weeks @ 40 hours per week).

The following is an example of the types of fringe benefits allowed and how an hourly credit is calculated:

Vacation 40 hours X $14.00 per hour = $560/2080 = $.27 Dental insurance $31.07 monthly premium X 12 mos. = $372.84 /2080 = $.18 Vision insurance $5.38 monthly premium X 12 mos. = $64.56/2080 = $.03 Health insurance $230.00 monthly premium X 12 mos. = $2,760.00/2080 = $1.33 Life insurance $27.04 monthly premium X 12 mos. = $324.48/2080 = $.16 Tuition $500.00 annual cost/2080 = $.24 Bonus 4 quarterly bonus/year x $250 = $1000.00/2080 = $.48 401k Employer Contribution $2000.00 total annual contribution/2080 = $.96

Total Hourly Credit $3.65 Other examples of the types of fringe benefits allowed:

Sick pay Holiday pay Accidental Death & Dismemberment insurance premiums

The following are examples of items that will not be credited toward the payment of the Prevailing Wage Rate o Legally required payments, such as:

Unemployment Insurance payments Workers’ Compensation Insurance payments FICA (Social Security contributions, Medicare contributions) o Reimbursable expenses, such as:

Clothing allowance or reimbursement Uniform allowance or reimbursement Gas allowance or reimbursement Travel time or payment Meals or lodging allowance or reimbursement Per diem allowance or payment o Other payments to or on behalf of a construction mechanic that are not wages or fringe benefits, such as:

Industry advancement funds Financial or material loans

P a g e | 3 of 11

OPERATING ENGINEERS CLASSIFICATION DESCRIPTIONS

Class I Asphalt Paver (self-propelled), Asphalt Planer (self-propelled), Asphalt Plant Operator, Auto- Grader, Blade Grader Operator, Batch Plant (concrete-central mix), Backhoe (with over 3/8 yard bucket), Bulldozer Operator, Concrete Pump 3" and over, Conveyor Loader Operator (euclid type), Crane Operator, Dragline Operator, Elevating Grader Operator, End-loader Operator (1 yard capacity or over), Slip Form Paver, Finishing Machine Operator (asphalt), Gradall Operator (and similar type machines), Hoisting Engineer, Hydro demolisher (water blaster), Locomotive Operator, Mechanic, Paver Operator (5 bags or more), Pump Operator (6" discharge or over, gas, diesel powered, or generator of 300 amp or larger), Pile Driving Operator, Roto Mill, Roller Operator (Asphalt), Side Boom Tractor (type D-4, equivalent or larger), Self-Propelled or Tractor Drawn Scraper, Slurry Machine (asphalt), Swinging Boom Truck (over l2 ton capacity), Shouldering or Gravel Distributing Machine Operator (self-propelled), Shovel Operator, Side Boom Tractor (type D-4 or equivalent or larger), Tractor Operator, Trenching Machine Operator (ladder or wheel type), Tube Finisher (slip form paving), Farm type tractor with attached pan

Class II

Sweeper (wayne type & similar equipment), Screening Plant Operator, Washing Plant Operator, Crusher Operator, Vacuum Truck Operator, Backhoe (with 3/8 yard bucket or less), Side Boom Tractor (smaller than D-4 type or equivalent), Batch Plant (concrete-dry mix)

Class II

Grease Truck

Class III Air Compressor Operator (600 cfm or more), Air Compressor (2 or more, less than 600 cfm), Concrete Breaker, Tractor Operator (farm type with attachments), Wagon Drill Operator

Class IV

Boiler Fireman, Oiler, Fireman, Mechanic's Helper, Trencher (service), Flexplane Operator, Cleftplane Operator, Grader Operator Self-propelled Fine-Grade or Form (concrete), Finishing Machine Operator (concrete), End-loader Operator (under 1 yard capacity), Roller Operator (other than asphalt), Curing Equipment Operator (self-propelled), Concrete Saw Operator (Over 40 HP), Power Bin Operator, Plant Drier Operator (asphalt), Vibratory Compaction Equipment (6’ wide or over), Guard Post Driver Operator (power driven), All Mulching Equipment, Stump Remover, Concrete Pump (under 3”), Mesh Installer (self-propelled), Tractor Operator (Farm Type) End Dumps, Boom or Winch Hoist Truck Operator, Skid Steer

P a g e | 4 of 11

LABORERS CLASSIFICATION DESCRIPTIONS

Class 1 Asphalt Shoveler or Loader, Asphalt Raker Tender, Asphalt Plant Misc., Railroad Track and Trestle Laborer, Burlap Man, Carpenter's Tender, Top Man, Yard Man, Guard Rail Builder's Tender, Earth Retention Barrier and Wall and Mechanically Stabilized Earthen Wall Installers Tender, Highway and Median Barrier Installer's Tender (including Sound, Retaining and Crash Barrier), Fence Erector's Tender, Dumper (wagon, truck, etc.) Joint Filling Labor, Misc., Unskilled Labor, Sprinkler Labor, Form Setting Labor, Form Stripper, Pavement Reinforcing, Handling and Placing (e.g. wire mesh, steel mats, dowel bars, etc.) Mason's or Bricklayer's Tender on Manholes, Manhole Builder, Headwalls, etc., Waterproofing (other than buildings), Seal Coating and Slurry Mix, Shoring, Underpinning, Bridge Painting, etc. (spray, roller and brush) Sandblasting, Pressure Grouting, and Bridge Pin and Hanger Removal, Material Recycling Laborer, Horizontal Paver (brick, concrete, clay, stone and asphalt) Ground Stabilization and Modification Laborer, Grouting, Waterblasting, Sign Installer and remote control operated equipment.

Class 2 Mix Operator (less than 5 sacks), Air or Electric Tool Operator (jack hammer, etc.), Spreader, Boxman (asphalt, stone, gravel, etc.), Concrete Paddler, Power Chain Saw Operator, Paving Batch Truck Dumper, Tunnel Mucker (highway work only), Concrete Saw Operator (under 40 H.P.), Dry Pack Machine and Roto-Mill Grounds Person.

Class 3 Tunnel Miner (highway work only), Finishers Tender, Guard Rail Builder, Highway and Median Barrier Installer, Fence Erector, Bottom Man, Powder Man, Wagon Drill and Air Track Operators, Curb and Side Rail Setters' Tender, Diamond & Core Drills, Earth Retention Barriers, Walls and Mechanically Stabilized Earthen Wall Installer (including sound, retaining and crash barrier), grade checker and certified welder.

Class 4 Asphalt Raker

Class 5 Pipe Layers, Oxy-gun

Class 6 Line-Form Setter for Curb or Pavement and asphalt screed checker/screw man on asphalt paving machines.

Class 7 Concrete Specialist, finishing and troweling, of cast in place or precast concrete by any and all methods.

P a g e | 5 of 11

OVERTIME PROVISIONS FOR Road Builder PREVAILING WAGE RATE SCHEDULE

1. Overtime is represented as a nine character code. Each character represents a certain period of time after the first 8 hours Monday thru Friday.

Monday thru Friday Saturday Sunday &

Holidays

Four 10s

First 8 Hours 4

8 9 9th Hour 1 5 10th Hour 2 6 Over 10 hours 3 7

Overtime for Monday thru Friday after 8 hours:

the 1st character is for time worked in the 9th hour (8.1 - 9 hours) the 2nd character is for time worked in the 10th hour (9.1 - 10 hours) the 3rd character is for time worked beyond the 10th hour (10.1 and beyond)

Overtime on Saturday:

the 4th character is for time worked in the first 8 hours on Saturday (0 - 8 hours) the 5th character is for time worked in the 9th hour on Saturday (8.1 - 9 hours) the 6th character is for time worked in the 10th hour (9.1 - 10 hours) the 7th character is for time worked beyond the 10th hour (10.01 and beyond)

Overtime on Sunday & Holidays the 8th character is for time worked on Sunday or on a holiday

4 Ten hour days @ Straight Time The 9th character indicates if an optional 4-day 10-hour per day workweek can be worked between Monday and Friday without paying overtime after 8 hours worked. To utilize a 4 ten workweek, notice is required from the employer to employee prior to the start of work on the project.

2. Overtime Indicators Used in the Overtime Provision: H -means TIME AND ONE-HALF due D -means DOUBLE PAY due X means TIME AND ONE HALF due after 40 hours worked Y means YES an optional 4-day 10-hour per day workweek can be worked without paying overtime after 8 hours worked N -means NO optional 4-day 10-hour per day workweek can be worked without paying overtime after 8 hours worked

3. EXAMPLES:

HHHHHHDDY - This example shows that the 1½ rate must be used for time worked after 8 hours Monday thru Friday (characters 1 - 3)and for all hours worked on Saturday, (characters 4 - 6), except hours worked after 10 hours on Saturday (7th character). Work done after 10 hours must be paid at the double time rate. Work done on Sunday or holidays must be paid double time (character 8). The Y (character 9) indicates that 4 ten-hour days is an acceptable alternative workweek at regular pay.

HHHHHHHHY means that the 1½ rate must be used for time worked after 8 hours worked Monday thru Friday (characters 1-3); and for any hours worked on Saturdays, Sundays or holidays (characters 4-8). The Y (character 9) indicates that 4 ten-hour days is an acceptable alternative workweek at regular pay.

XXHXXXHDY this example allows 4 ten hour days Monday thru Saturday to be worked. Hours worked beyond ten Monday thru Saturday OR hours worked after 40 hours in one week must be paid at time and one half. Sunday or holiday hours must be paid at double.

P a g e | 6 of 11

CARPENTER CRAFT JURISDICTION

Michigan recognizes the Carpenters for any and all work related to weatherization that has historically been the work of the Carpenter. This work shall include, but not be limited to: all work defined under the Federal Weatherization Assistance Program.

The jurisdiction of Carpenters, as to all work that has historically and traditionally been performed consisting of the milling, fashioning, joining, assembling, erecting, fastening or dismantling of all materials of wood, plastic, metal, fiber, cork, or composition and all other substitute materials, as well as the handling, cleaning, erecting, installing and dismantling of all machinery, equipment and all materials used by Carpenters.

The jurisdiction, therefore, extends over the following divisions and subdivisions of the trade: Carpenters and Joiners, Millwrights, Pile Drivers, Bridge, Dock and Wharf Carpenters, Underpinners, Timbermen, and Core-drillers, Shipwrights, Boat Builders, Ship- hand, Stair-Builders, Millmen, Wood and Resilient Floor Decorators, Floor Finishers, Carpet-layers, Shinglers, Siders, Insulators, Acoustic and Drywall Applicators, Sharers and House Movers, Loggers, Lumber and Sawmill Workers, Reed and Rattan Workers, Shingle Weavers, Casket and Coffin Makers, Railroad Carpenters and Car Builders, regardless of material used and all those engaged in the operation of woodworking or other machinery required in fashioning, milling or manufacturing of products used in the trade, and the handling, erecting and installing materials on any of the above divisions or sub-divisions, burning, welding and rigging incidental to the trade. When the term "Carpenter and Joiner" is used, it shall mean all the subdivisions of the trade. The trade autonomy of Carpenters therefore extends over the divisions and subdivisions of the trade, which are set forth as follows:

(a) The framing, erecting and prefabrication of roofs, partitions, floors and other parts of buildings of wood, metal, plastic or other substitutes; application of all metal flashing used for hips, valleys and chimneys; the erection of Stran Steel section or its equal. The building and setting of all forms and centers for brick and masonry. The fabrication and erection of all forms for concrete and decking, the dismantling of same (as per International Agreement) when they are to be re-used on the job or stored for re-use. The cutting and handling of all falsework for fireproofing and slabs. Where power is used in the setting or dismantling of forms, all signaling and handling shall be done by carpenters. The setting of templates for anchor bolts for structural members and for machinery, and the placing, leveling and bracing of these bolts. All framing in connection with the setting or metal columns. The setting of all bulkheads, footing forms and the setting of and fabrication of, screeds and stakes for concrete and mastic floors where the screed is notched or fitted, or made up of more than one member. The making of forms for concrete block, bulkheads, figures, posts, rails, balusters and ornaments, etc.

(b) The handling and erecting of rough material and drywall, the handling, assembly, setting and leveling of all fixtures, display cases, all furniture such as tables, chairs, desks, coat racks, etc., all de-mountable or moveable partitions such as Von wall, E Wall, Steel Case, Herman Miller, Haworth, American Seating, Westinghouse, Lazy Boy, rosewood, etc. All rebuilding, remodeling and setting up of all kinds of partitions, finished lumber, metal and plastic trim to be erected by Carpenters shall be handled from the truck or vehicle delivering same to the job by Carpenters.

P a g e | 7 of 11

(c) The building and moving of all scaffolding runways and staging where carpenters' tools are used, the building from the ground up of all scaffolds over fourteen (14) feet in height including metal and specially designed scaffolding. The building and construction of all hoists and derricks made of wood; the making of mortar boards, boxes, trestles, all shoring, razing and moving of buildings. Lift type trucks are to be considered a tool of the trade. Metal siding and metal roofing fall within the scope of jurisdiction for the carpenters.

(d) The cutting or framing and fireproofing of the openings for pipes, conduits, ducts, etc., where they pass through floors, partitions, walls, roofs or fixtures composed in whole or in part of wood. The laying out of making and installation of all inserts and sleeves for pipes, ducts, etc., where carpenters' tools and knowledge are required. The making and installing of all wooden meter boards, crippling and backing for fixtures. The welding of studs and other fastenings to receive material being applied by carpenters.

(e) The installation of all grounds, furring or stripping, ceilings and sidewalks, application of all types of shingling and siding, etc.

(f) The installation of all interior and exterior trim or finish of wood, aluminum, kalamein, hollow or extruded metal, plastic, doors, transoms, thresholds, mullions and windows. The setting of jambs, bucks, window frames of wood or metal where braces or wedges are used. The installation of all wood, metal or other substitutes of casing, molding, chair rail, wainscoting, china closets, base of mop boards, wardrobes, metal partitions as per National Decisions or specific agreements, etc. The complete laying out, fabrication and erection of stairs. The making and erecting of all fixtures, cabinets, shelving, racks, louvers, etc. The mortising and application of all hardware in connection with our work. The sanding and refinishing of all wood, cork or composition floors to be sanded or scraped, filled, sized and buffed, either by hand or power machines. The assembling and setting of all seats in theaters, halls, churches, schools, auditorium, grandstands and other buildings. All bowling alley work.

(g) The manufacture, fabrication and installation of all screens, storm sash, storm doors and garage doors; the installation of wood, canvas, plastic or metal awnings or eye shades, door shelters, jalousies, etc. The laying of wood, wood block and wood composition in floors.

(h) The installation of all materials used in drywall construction, such as plasterboard, all types of asbestos boards, transite and other composition board. The application of all material which serves as base for acoustic tile, except plaster. All acoustical applications as per National Agreement or specific agreement.

(i) The building and dismantling of all barricades, hand rails, guard rails, partitions and temporary partitions. The erection and dismantling of all temporary housing on construction projects.

(j) The installation of rock wool, cork and other insulation material used for sound or weatherproofing. The removal of caulking and placing of staff bead and brick mold and all Oakum caulking, substitutes, etc., and all caulking in connection with carpentry work.

(k) The installation of all chalk boards/marker boards.

P a g e | 8 of 11

(l) The operation of all hand operated winches used to raise wooden structures.

(m) The erection of porcelain enameled panels and siding.

(n) The unloading and distribution of all furnished, prefabricated and built-up sections such as door bucks, window frames, cupboards, cabinets, store fixtures, counters and show cases or comparably finished or prefabricated materials, to the job sites or points of installation as used in the construction, alteration and remodeling industry.

(o) The handling of doors, metal, wood or composite, partitions and other finished bulk materials used for trim from the point of delivery.

(p) All processing of these materials and handling after processing.

(q) The making up of panels and fitting them into walls, all bracing and securing, all removal of panels from the casting including all braces, whalers, hairpins, etc.

(r) The handling and setting of all metal pans and sections from the stock piles of reasonable distance as required by job needs shall be performed by carpenters. The stripping of such metal pans, panels or sections is to be performed by carpenters.

(s) The sharpening of all carpenter hand or power tools, or those used by carpenters.

(t). The layout, fabrication, assembling of and erection and dismantling of all displays made of wood, metal, plastic, composition board or any substitute material; the covering of same with any type of material, the crating and un-crating, the handling from the point of unloading and back to the point of loading of all displays and other materials or components.

(u) The same shall apply to all other necessary component parts used for display purposes such as turntables, platforms, identification towers and fixtures, regardless of how constructed, assembled or erected or dismantled.

(v) The make-up, handling, cutting and sewing of all materials used in buntings, flags, banners, decorative paper, fabrics and similar materials used in the display decorative industry for draperies and back drops. The decorative framing of trucks, trailers and autos used as floats or moving displays. The slatting of walls to hand fabrics and other decorative materials, drilling of all holes to accommodate such installations. Setting up and removal of booths constructed of steel or aluminum tubing as stanchions, railings, etc., handling and placing of furniture, appliances, etc., which are being used to complete the booth at the request of the exhibitor. Fabricating and application of leather, plastic and other like materials used for covering of booths. The handling of all materials, fabricating of same. The loading and unloading, erecting and assembling at the exhibit of show area, also in or out of storage when used in booth decorations.

P a g e | 9 of 11

(w) A display shall be construed as any exhibit or medium of advertising, open to private or public showing, which is constructed of wood, metal, plastic or any other substitute to accomplish the objectives of advertising or displaying.

(x) Handling,…

This is the start of the file's text. The full file is on GovTribe.