Chilled Water Pipe Insulation Clarification#3-1.pdf
PDF 204 KB Posted
- Attached to
- Interior chilled water pipe insulation
- Solicitation number
- RFP-BATT-190000002475-4
- Issued by
- Calhoun County, Michigan
About this file
This is a clarification document (#3) issued by Elite Companies for a piping insulation project at Ann J Kellogg School within Battle Creek Public Schools, dated June 13th, 2019. The project involves installing insulation on chilled water piping across four designated areas of the facility. The scope requires minimum insulation thickness of ¾" on all chilled water piping less than 3" in diameter and 1" thick insulation on piping 3" or more in diameter, as specified in previous clarification #1.
The construction schedule shows the piping insulation work is to be completed in four-day durations for each area, with contractors required to account for potential weekend and holiday work in their base bids. The schedule indicates the piping insulation work is to be coordinated with other trades including demolition, HVAC cleaning, remedial cleaning, air testing, ceiling work, and content reinstallation. Bidders must include crew sizes and completion timelines for each area (1-4) in their base bid proposals.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Battle Creek Public Schools: Ann J Kellogg Piping Insulation – Clarification #3
June 13th, 2019
Project Schedule:
See attached project schedule reflective of the windows of opportunity for the piping insulation. Please note the weekend work and holiday work potential. Please include in your base bid crew sizes and plan for these dates and completion timelines for your scope by area (1-4).
Scope Clarification;
Base bid insulation needs to based off of previous clarification #1 specifications and needs to be a minimum of ¾” on all chilled water piping less than 3” and 1” thick on piping 3” or more in diameter.
Ann J Kellogg Remediation - Construction Schedule - 2019
Period Highlight: 1 Plan Duration Actual Start % Complete Actual (beyond plan) % Complete (beyond plan)
Trades PERIODS - Starting on 5.1.19 (period 13 = Wednesday, May 1st); Regular/Working Week Days ONLY (I.E. period 16 = Monday, May 6th, etc.)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
M T W R F S S M T W R F S S M T W R F S S M T W R F S S M T W R F S S M T W R F S S M T W R F S
17th 18th 19th 20th 21st 22nd 23rd 24th 25th 26th 27th 28th 29th 30th 1st 2nd 3rd 4th 5th 6th 7th 8th 9th 10th 11th 12th 13th 14th 15th 16th 17th 18th 19th 20th 21st 22nd 23rd 24th 25th 26th 27th 28th 29th 30th 31st 1st 2nd 3rd
Site Mobilization 1 1 As Nec.
Area 1 - Content Removal/Stage (COMPLETE) 0 0 BCPS
VanDam/Krusinga (VK)-Containment 1 2 V/K
VK-Demolition/Remediation (Ceiling Removal) 2 4 V/K
Stanley Steamer (SS) - HVAC Clean 5 2 SS
VK - Remedial Cleaning 7 3 V/K
Wonder Maker (WM) - Air Test/Clear 10 2 WM
VK-Cont. Removal 12 1 V/K
TBD - Piping Insulation 12 4 TBD
BCPS - Reinstall Ceilings 16 2 BCPS
SS - Clean Carpets 18 2 SS
BCPS - Content Install/Clean 19 3 BCPS
Area 2 - Content Removal/Stage A4 1 2 BCPS
VanDam/Krusinga (VK)-Containment 3 2 V/K
VK-Demolition/Remediation (Ceiling Removal) 4 4 V/K
Stanley Steamer (SS) - HVAC Clean 8 4 SS
VK - Remedial Cleaning 11 3 V/K
Wonder Maker (WM) - Air Test/Clear 14 2 WM
VK-Cont. Removal 16 1 V/K
TBD - Piping Insulation 16 4 TBD
BCPS - Reinstall Ceilings 19 2 BCPS
SS - Clean Carpets 21 2 SS
BCPS - Content Install/Clean 22 3 BCPS
Area 3 - Content Removal/Stage A1 22 2 BCPS
VanDam/Krusinga (VK)-Containment 24 2 V/K
VK-Demolition/Remediation (Ceiling Removal) 25 4 V/K
Stanley Steamer (SS) - HVAC Clean 29 4 SS
VK - Remedial Cleaning 32 3 V/K
Wonder Maker (WM) - Air Test/Clear 35 2 WM
VK-Cont. Removal 37 1 V/K
TBD - Piping Insulation 37 4 TBD
BCPS - Reinstall Ceilings 40 2 BCPS
SS - Clean Carpets 42 2 SS
BCPS - Content Install/Clean 43 3 BCPS
Area 4 - Content Removal/Stage A2 24 2 BCPS
VanDam/Krusinga (VK)-Containment 26 2 V/K
VK-Demolition/Remediation (Ceiling Removal) 27 4 V/K
Stanley Steamer (SS) - HVAC Clean 31 4 SS
VK - Remedial Cleaning 34 3 V/K
Wonder Maker (WM) - Air Test/Clear 37 2 WM
VK-Cont. Removal 39 1 V/K
TBD - Piping Insulation 39 4 TBD
BCPS - Reinstall Ceilings 42 2 BCPS
SS - Clean Carpets 44 2 SS
BCPS - Content Install/Clean 45 3 BCPS
Jun-19 Jul-19 Aug-19
ACTIVITY PLAN START
PLAN
DURATION
ELITE COMPANIES, LLC
5630 SOUTH 1ST ST
KALAMAZOO, MI 49009
BATTLE CREEK PUBLIC SCHOOLS
ANN J KELLOGG
BATTLE CREEK, MI 49037
File details come from the government source that posted it. Updated .