Change Order Notice~7.pdf
PDF 1 MB Posted
- Attached to
- Change Order Notice - Milk for Hill CC (MDS)
- Solicitation number
- 25-426DOC-HILLC-B-45218
- Issued by
- Kendall County, Illinois
About this file
This document is a Change Order Notice from the Chief Procurement Office for General Services. It provides details on a price increase for milk delivered to Hill Correctional Center under Contract No. 25-426DOC-HILLC-B-45218. The current price of $16.19 per case of 8 oz. fortified skim milk cartons will be increased by $1.95 to a final price of $18.14 per case. This change order is being requested by the vendor due to increased costs. Per Section 33E-9 of the Criminal Code, the circumstances necessitating this change were not reasonably foreseeable at the time the contract was signed, and the change is germane to the original contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Contract-Amendment Milk Increase November 2024.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Please wait...
If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this type of document.
You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.
For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.
Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.
Change Order Notice Chief Procurement Office for General Services Change Order Notice V.25.1 Page of Notice of renegotiated contracts and change orders that increase the cost of a contract by more than $25,000 or the time of completion by a total of 180 days or more shall be posted on the Bulletin/BidBuy for 14 days.
This Change Order Notice provides detail as to why the change order is needed and, pursuant to Section 33E-9 of the Criminal Code, that the circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed or the change is germane to the original contract as signed. Change orders are defined by Section 1-15.12 of the Procurement Code and Section 1.2067 of the CPO-GS' Administrative Rules.
Detailed explanation for this change order:
11.0.0.20130303.1.892433.887364
| CurrentPage: |
| PageCount: |
| DropDownList1: DOC - Corrections |
| ProcurementTitle: Price Increase Milk |
| BBREFNO.: 25-426DOC-HILLC-B-45218 |
| thedetails: Skim Milk, fortified with vitamins - 8 oz. cartons. Price change requested by vendor for milk delivered to Hill Correctional Center. Current price of $16.19 per case will be increased by $1.95 with a final price per case of $18.14. |
| CheckBox1: 0 |
| CheckBox2: 1 |
File details come from the government source that posted it. Updated .