About this file

This is a Rough Order of Magnitude (ROM) Pricing Template for a Modular Power Generation and Distribution solicitation (CEHNC-031467-OT) issued by the U.S. Army Corps of Engineers, Huntsville Center. The template is designed to collect pricing information from respondents proposing relocatable modular power generation and distribution solutions capable of supplying and stabilizing large transient loads for Department of Defense sites across the 50 United States. The Government requires implementation at 10-12 locations with a critical deadline of 28 February 2028. This template serves as a standardized format for vendors to submit rough order of magnitude estimates and does not contain specific technical requirements, performance metrics, or detailed statement of work information; rather, it functions as a pricing tool to gather cost proposals aligned with the Government's manufacturing, procurement, shipping, delivery, installation, and testing requirements for these modular power systems.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ROM Summary

ROUGH ORDER OF MAGNITUDE (ROM) PRICING TEMPLATE
Modular Power Generation and Distribution | Project No. CEHNC-031467-OT | Request for White Paper
Firm Fixed Price – Prototype Project under 10 U.S.C. § 4022
OFFEROR INFORMATION
Company Name:Date:
CAGE / UEI:POC Name / Email / Phone:
SECTION 1 — POWER GENERATION AND DISTRIBUTION OPTIONS
CLIN / OptionDescriptionScope / QuantityLabor ($)Material / Equipment ($)Other Direct Costs ($)Indirect / Fee ($)Total ROM Price ($)Notes / Assumptions
BASEN Generation + N DistributionBase quantity of generators (N) + base distribution switchgear/feeders sufficient for the proposed load (no redundancy)$0
OPTION 1N+1 Generation (incremental)Additional generation capacity and associated equipment to achieve N+1 redundancy configuration (one additional generator set + paralleling/controls as required)$0
OPTION 2N+2 Generation (incremental)Additional generation capacity and associated equipment to achieve N+2 redundancy configuration (second additional generator set + paralleling/controls as required). Price as incremental over N+1.$0
OPTION 3N+1 DistributionDistribution switchgear, breakers, feeders, and associated equipment sized for N+1 configuration$0
OPTION 4N+2 DistributionDistribution switchgear, breakers, feeders, and associated equipment sized for N+2 configuration . Price as incremental over N+1.$0
SUBTOTAL — Generation & Distribution (Base + All Options)$0$0$0$0$0
SECTION 2 — CONTRACTOR LOGISTICS SUPPORT (CLS) / OPERATIONS & MAINTENANCE OPTIONS
CLIN / OptionDescriptionScope / QuantityLabor ($)Material / Equipment ($)Other Direct Costs ($)Indirect / Fee ($)Total ROM Price ($)Notes / Assumptions
OPTION 5CLS — Year 1Contractor Logistics Support / Operations & Maintenance for the first 12 months following successful commissioning of the complete power solution$0
OPTION 6CLS — Year 2Contractor Logistics Support / Operations & Maintenance for the second 12-month period (months 13–24)$0
OPTION 7CLS — Year 3Contractor Logistics Support / Operations & Maintenance for the third 12-month period (months 25–36)$0
SUBTOTAL — CLS (All Years)$0$0$0$0$0