CDC HVAC SOW.pdf

PDF 303 KB Posted

Attached to
CDC ARSR HVAC Replacement Federal contract opportunity
Solicitation number
697DCK-26-R-00330
Issued by
Department of Transportation Federal Aviation Administration Southwestern Region

About this file

Statement of Work Summary

This is a Statement of Work (SOW) for an HVAC Replacement Project at the Cedar City (CDC) Long Range Radar (ARSR) site near Cedar City, Utah, issued by the Federal Aviation Administration (FAA) under the NAS Defense Program. The anticipated construction period is no longer than 60 days, with a pre-construction conference required before work begins. The project document (FAA-B710-CDC-SOW) references applicable installation drawing M001 and the OAS 2.5 HVAC Controller User Manual.

Scope and Deliverables

The selected contractor must furnish all labor, products, equipment, materials, and supervision for demolition and installation work. Demolition activities include removing and disposing of two existing HVAC units with associated ductwork and radio room wall units, with refrigerant disposal certificates required. Installation requires providing and installing two new 15-ton York Packaged HVAC Units (DSV180C2S5VDA3A00 or FAA-approved equal) with R-454b refrigerant, associated ductwork per SMACNA standards, controls, and components. Additional work includes installing one Government Furnished Equipment (GFE) OAS HVAC controller with conduit and thermostat wiring, new return ducting and grilles, non-motorized counterbalanced back-draft dampers, LED lighting replacing existing fluorescent fixtures, new window AC unit (minimum 2-ton) for radio room, replacement ceiling tiles, electrical work complying with FAA specifications, disconnects with proper labeling, utility locates, and testing and balancing with a minimum 6,000 cfm airflow confirmation. The contractor must provide maintenance equipment including valve manifolds, recovery machines, vacuum pumps, refrigerant scales, recovery tanks, replacement filters, spare fuses, fan belts, and one new R-454b refrigerant tank, plus a minimum 4-hour training session for facility personnel. The facility operates 24/7 as an active operational site; all work must be coordinated with the FAA on a "not to interfere with operations" basis, with temporary HVAC units required and a 24-hour continuous run-in test mandatory before switchover to new units.

View the file

Other files for this federal contract opportunity

Other files attached to CDC ARSR HVAC Replacement, newest first.
File Type Posted
697DCK-26-R-00330 0002.pdf PDF
RFIs - 697DCK-26-R-00330 - CDC ARSR HVAC Replacement.pdf PDF
697DCK-26-R-00330 0001.pdf PDF
Wage Determination - UT20260073 05182026.pdf PDF
697DCK-26-R-00330.pdf PDF
CDC-D-ARSR-M001.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CDC - ARSR HVAC Replacement May 2026

SUMMARY OF WORK PAGE 1

Federal Aviation Administration

NAS DEFENSE PROGRAM

NDP RESOURCE SERVICES TEAM

AJW-B710

INFRASTRUCTURE PROGRAM

HVAC REPLACEMENT PROJECT

FAA-B710-CDC-SOW

Cedar City, UT

CDC ARSR

STATEMENT OF WORK

May 2026

SUMMARY OF WORK PAGE 2

SUMMARY OF WORK

1.0 GENERAL SCOPE

The selected Contractor shall furnish all labor, product, equipment, materials, and supervision for the demolition and installation associated with the HVAC Replacement Project at the Cedar City (CDC) Long Range Radar (ARSR) site located near Cedar City, UT.

“Demolition” includes but is not limited to removing and disposing of the existing 2 HVAC units and associated ductwork from the facility and removing existing radio room wall unit. “Installation” includes but is not limited to providing and installing 2 new 15–ton Packaged HVAC units with associated ductwork, HVAC controls, and all associated components at the site and installing new wall unit for radio room. Prior to “installation,” all of the equipment and material shall be reviewed and accepted by a FAA representative.

The following items are a summary of the project and are provided solely for the purpose of describing the general nature of the work. The Contractor is responsible for accomplishing all items of work identified in the applicable drawings, specifications, and provisions of the contract:

A. General

1. CDC ARSR is an active operational facility that runs 24 hours a day, 7 days a week.

2. All work shall be coordinated with the FAA and be accomplished on a “Not to interfere with FAA operations” basis.

3. Construction material shall be stored only in FAA approved areas.

4. Construction staging shall be allowed only in the FAA approved areas.

5. The Contractor shall provide all temporary services required for construction.

6. The Contractor shall clean up and restore the site grounds to its original condition after the work has been performed.

B. Demolition

1. Remove and properly dispose of existing packaged units (2 units). Provide certificate of disposal for refrigerant.

2. Remove and properly dispose of the associated ducting, controls and other related components.

3. Relocate interferences for the new equipment as needed to allow clearance for new ductwork. All relocations must be done with prior approval from the COR.

4. Patch all wall openings left as a result of the demolition to match surrounding areas.

SUMMARY OF WORK PAGE 3

5. Due to the critical equipment inside this facility, reliable cooling is required throughout the project. Temporary HVAC units will be necessary. Prior to switching over to the new units, a 24-hour continuous run-in test is required.

6. The contractor shall have training and certification in OSHA Lead construction and follow Operations and Maintenance (O&M) Procedures when working around lead containing materials. At a minimum, the contractor shall submit a Standard Operating Procedure (SOP) and/or Site-Specific Work Plan detailing work procedures when working around lead containing materials to accomplish the work detailed in the contract documents.

7. It is not anticipated that the contractor should need to work or disturb asbestos containing materials (ACM) as part of the project work. The contractor shall develop, obtain certifications, and submit a Site-Specific Work Plan detailing a procedure for work around ACM should the need to disturb ACM arise to accomplish the work set forth in the contract documents.

A. Installation

New Air Conditioners- Equipment Room

1. Provide and install 2 each new York 15-Ton Air-Cooled Self-Contained Packaged Air Conditioning Units (DSV180C2S5VDA3A00), or FAA approved equal, and all associated components into the general locations shown on installation drawing M001. Exact locations are to be field determined. The minimum characteristics of the new air conditioning units shall be as follows:

a. Commercial application

b. R-454b Refrigerant

c. 15 tons nominal Capacity

d. Condenser Hail Guards

e. Standard Static Indoor Fan

f. Low Ambient Cooling

g. FreezeStat

h. Hinged Access Doors

i. Return Air Smoke Detector

j. 208V / 60 hertz / 3 phase

k. Associated Factory Curb or Stand

l. GFCI Outlet – Powered

m. Economizer with barometric relief dry bulb temperature controlled

2. Mount unit curbs or stands to concrete using concrete anchor/studs. Secure new units per manufacturer’s instructions.

3. Install 1 each Government Furnished (GFE) OAS HVAC controller. Contractor will be responsible for providing and installing ¾” conduit from the controller and properly sized thermostat wire to each new unit.

SUMMARY OF WORK PAGE 4

a. OAS HVAC controller is limited to a single-stage input for heating. If the HVAC unit has two-stages of heating, Contractor shall install a time delay to ensure both stages of heating do not energize simultaneously.

New Ductwork

1. Provide and install new ducting per SMACNA standards as detailed on associated install drawing M001. Return air discharge is to be installed into existing gooseneck and ice shield. A non-motorized counterbalanced back-draft damper shall be installed in the supply ductwork for each HVAC unit as to prevent back-flow to a non-active unit during normal operation. A 14”x14” access door is required to be installed downstream of each back-draft damper and near security bar locations.

2. Install new return ducting and grilles at the general locations shown on the installation drawing M001.

3. Dimensions shown on drawings are airway (interior) dimensions. Externally insulate interior ductwork.

4. Exterior ducting shall be externally insulated and covered in a protective coating similar to VentureClad 1577CW or FAA approved equal.

5. All new hangers shall be trapeze style. Other hanger styles can be submitted to the FAA for review/approval.

6. All ductwork bonding shall comply with the latest revision of FAA Standard FAA- STD-019, “Lightning Protection, Grounding, Bonding and Shielding Requirements for Facilities”.

Electrical

1. All electrical work shall comply with the latest revision of FAA specification FAA-C- 1217H, “Electrical Work, Interior”.

2. All equipment grounding shall comply with the latest revision of FAA standard FAA- STD-019G, “Lightning Protection, Grounding, Bonding and Shielding Requirements for Facilities”.

3. All bonds shall be exothermic welds or FAA approved pressure connections IAW FAA-STD-019G and current version of the NEC.

4. Contractor shall confirm breaker size prior to construction and replace, if necessary, per unit manufacturer specifications. Breakers may be oversized if the associated disconnect is properly fused for the serviced equipment.

5. Provide and install properly sized Heavy Duty disconnects and connecting wires for each new air conditioner unit. Outdoor disconnects shall be NEMA 3R minimum rating. Each disconnect shall be fused to match manufacturer rating for supported equipment.

6. Provide updated printed Panel schedules to affected Panels.

SUMMARY OF WORK PAGE 5

7. Label each new/reused disconnect with Voltage, Phases, and Source Panel & Breaker info. Labels shall be plastic engraved nameplates with white letters and black background. Letter size must be 1/8" for controls, 3/16" for devices on control panel covers and 3/8" for safety switches, air conditioning equipment and other equipment devices. Nameplates must be secured to equipment, cabinets and to controls with adhesive backing.

8. Utilize Liquid-Tite type flexible conduit when flexible application is required. Flex conduit shall not exceed 6’ individual length.

9. EMT Conduit is only allowed on the interior of FAA facilities. All outdoor conduits shall be rigid steel with threaded connections.

10. Where EMT is used, only compression-type fittings are acceptable.

11. Update arc flash analysis and supply new labels.

Radio Room

1. Remove existing through the wall AC unit and patch any excess space not needed for new unit.

2. Install new window ac unit with at least 2 ton cooling capacity in similar location to existing wall unit.

Ceiling Tiles

1. Replace all existing ceiling tiles with new.

2. Tiles shall be similar in size and style as existing.

3. Existing grid may be reused/modified if possible.

LED Lighting

1. Replace existing florescent lighting with new LED lighting as follows:

a. New LED Lighting shall be a one-for-one replacement with existing fluorescent bulbs & fixtures, providing equal or greater light (lumens) per sq ft.

b. Actual Fixture location shall be altered to accommodate new ductwork.

c. LED light fixtures shall be similar design to existing. Drop ceiling models installed into the same circuits as the existing lights. Lights shall be RAB EZPAN2X4-40N/D10LED Troffer (4000K Color Temperature), or FAA approved equal.

i. LED fixture must be fully sealed to prevent bug entry.

ii. Troffer surface mount kit required for all surface mounted lights.

iii. 90 minute battery back-up accessory required for all lights on routes of egress.

d. In areas requiring hanging light due to ductwork or other interference, utilize

Lithonia SBL4 48L (4000K Color Temperature) or FAA approved equal.

SUMMARY OF WORK PAGE 6

Disconnects

1. Install disconnects for the packaged HVAC units as shown on drawing M001, mounted to the wall. Final location of disconnects is to be field determined and verified by COR.

a. Contractor is responsible to perform all utility locates prior to any digging required on this project.

b. Contractor shall coordinate with the FAA to perform utility locates for all FAA utilities (Communications, electrical, Mechanical, etc. owned by the FAA).

c. Disconnect rack shall be bonded as required by drawing M001 and FAA Standard

019G.

Testing and Balancing

1. Perform an operational check of all newly installed equipment.

2. Confirm the cooling capacity is 15-tons and cfm rate is a minimum of 6000 cfm for new air conditioning units. Confirm proper operation of all dampers.

3. Confirm compressor operation and staging (if applicable) for the controls and air conditioning units and economizers.

4. Balance airflow as shown on M001. Provide Test & Balance Report upon completion of project.

Maintenance Equipment:

1. Provide the following equipment to the FAA for continued maintenance of the new R-454b HVAC Equipment.

a. Valve Manifold with hoses (Fieldpiece SMAN482V or FAA approved equal)

b. Recovery Machine (Fieldpiece MR45 or FAA approved equal)

c. Vacuum Pump (Fieldpiece VPX7 or FAA approved equal)

d. Digital Refrigerant Scale (Fieldpiece SR47 or FAA approved equal)

e. Recovery Tank (Mastercool 62010 or FAA approved equal)

f. 4 sets of replacement filters – Manufacturer Recommended

g. 1 Spare set of disconnect fuses (if applicable)

h. 1 Spare set of evaporator fan belts

i. 1 New tank of R-454b refrigerant

Training:

1. Provide new equipment training to the facility personnel for all newly installed equipment. Training shall consist of at least 4 hours detailing the new units and individual components of the system, including Filter Replacement, Lock Out Procedures, and any special features of installed equipment.

SUMMARY OF WORK PAGE 7

1.2 APPLICABLE DOCUMENTS

A. Applicable Documents - All FAA, Military, Federal, and industrial codes or standards, specifications, and contract drawings referenced in this and the following divisions form a part of this specification and are applicable only to the extent they were used as a basis of this design. All references to codes, standards, specifications, and construction drawings refer to the latest editions (and any supplements) in effect on the date of the contract.

B. Applicable Publications - The publications listed below form a part of this specification to the extent referenced. The publications are referenced to in the text by basic designation only.

1. Code of Federal Regulations (CFR):

a. OSHA General Industry Safety and Health Standards (29 CFR 1910), OSHA

Construction Industry Standards (29 CFR 1926). OSHA 2202 is a condensed version of 29 CFR 1926. Each is for sale by the Superintendent of Documents, U.S. Government Printing Office, Washington DC 20402.

b. National Emission Standards for Hazardous Air Pollutants (40 Cfr, Part 61).

c. 29 CFR 1910.134; Respiratory Protection

d. 29 CFR 1910.1025; Lead

e. 29 CFR 1910.1200; Hazard Communication

f. 29 CFR 1926.55; Gases, Vapors, Fumes, Dusts, and Mists

g. 29 CFR 1926.57; Ventilation

h. 29 CFR 1926.62; Lead Exposure in Construction; Interim Rule (with appendices

A, B, C, and subpart D)

2. SMACNA Handbooks: Sheet Metal and Air Conditioning Contractors’ National

Association

3. Version 2026 National Electrical Code (NEC)

4. Federal Standard (313A): Preparation and the Submission of Material Safety Data

Sheets.

5. FAA Specification 1217H: Electrical Work, Interior.

6. FAA Standard 019G: Lightning and Surge Protection, Grounding, Bonding, and

Shielding Requirements for Facilities and Electronic Equipment.

7. List of Drawings:

These listed drawings are for information only, expressing existing conditions and construction details. The contractor shall verify dimensions, locations, and sizes on the applicable drawings prior to installation.

Project Documentation M001 HVAC Installation OAS 2.5 HVAC Controller User Manual

SUMMARY OF WORK PAGE 8

Existing Project Related Documentation (For reference only)

1.3 DEFINITIONS

A. Federal Aviation Administration (FAA) - The terms "Federal Aviation Administration" (FAA) and "government" as used herein denotes the "owner".

B. Project Engineer (PE) - The term "Project Engineer (PE)” as used herein denotes the "Government’s representative".

C. Contracting Officer (CO) - The term "Contracting Officer" (CO) as used herein denotes the person designated to act for the Government in the performance of this contract.

D. Contracting Officers Representative (COR) - The term "COR” as used herein denotes the representative of the Contracting Officer at the job site. The term is synonymous with the FAA terms "Resident Engineer" (RE).

E. Contractor and Subcontractor - The term "Contractor" as used herein denotes the firm who will perform and complete the work required by the Contract. The term "subcontractor" as used herein denotes the person or firm retained by the Contractor to perform a particular unit of work required by the Contractor. Subcontractors shall be required to meet all specifications required of the Contractor.

1.4 CONSTRUCTION CONDITIONS

A. Pre-construction Conference - The Contractor shall attend a pre-construction conference at the time and location specified by the RE. Requirements for material disposal, security and safety will be discussed. Use of facility restrooms, water, and power will also be discussed. Compliance with these procedures while on site is mandatory.

B. Period of Performance – The FAA anticipates construction activities to last no longer than 60 days.

C. Site Location – The site of construction installation is located in Cedar City, Utah.

Approximate address and coordinates for the project site are:

Site Address

FAA Radar Site, FR 277, Brian Head, UT 84719

SUMMARY OF WORK PAGE 9

Site Coordinates

37° 35' 35.5" N / 112° 51' 49.2" W (Latitude / Longitude)

D. Submittals - Prior to submitting orders, the contractor shall submit specifications for each new component of the installation for approval. Examples of required submittals include the new HVAC units, disconnects, backdraft dampers, diffusers, placards, curbs or stands, duct insulation, etc. Contractor shall provide submittals for samples, certificates, reports, catalog cuts, letters, shop drawings, maintenance and operations manuals, etc. as required throughout the project. All documents shall be submitted to the COR.

E. Conflict Resolution - The Contractor shall meet standards, specifications, and drawings as specified herein. The specifications and drawings shall rule in all cases.

Specifications shall govern over drawings. If any conflict should exist between site drawings (location-specific drawings) and standard drawings (drawings not referring to a particular location), the site drawings shall govern. In the event of dimensional discrepancies or omissions, the Contractor shall field verify and correct the information, and notify the RE. No work shall be done until agreement has been made with the RE

F. Inspection

1. Access for Inspection - The Contractor shall allow the RE complete access to all portions of the work. Portions of the work buried, enclosed, or disguised, shall be inspected by the RE before being obscured by the next operation of the Contractor. In all cases, the RE shall be informed accordingly and given access to the work. Work obscured before inspection and acceptance by the RE, may, at the option of the RE be opened for inspection at no additional cost to Government.

The RE will inspect all work in progress up to completion and final Contractor’s Acceptance Inspection (CAI) including all materials, tools, and equipment. Such inspection may extend to all or a part of the work for the preparation, fabrication or manufacture of the materials to be used. The RE will notify the Contractor of any non-compliance with the contract specifications and/or drawings, and may reject workmanship or materials accordingly.

2. Contractor's Acceptance Inspection (CAI) - After substantial completion of all the Contractor's work, a CAI will be conducted between the Contractor and Government. The RE will review the contract documents and verify that the Contractor has completed all required work. If work remains to be completed, an itemized list will be prepared, and the contractor at no additional cost to the

SUMMARY OF WORK PAGE 10

Government shall complete the remaining tasks correctly. A Joint Acceptance Inspection (JAI) requires FAA personnel to be present. It may be held concurrently with the CAI.

G. Project Coordination - The Contractor shall be required to coordinate his/her construction activities with the FAA through the COR. All work which affects the facility shall be coordinated and approved by FAA personnel through the COR at least forty-eight (48) hours in advance of the scheduled work. Failure to notify and obtain the necessary approval may result in a rescheduling of the work. If weather conditions or aircraft operations preclude a scheduled shutdown of an existing FAA facility, the Contractor shall reschedule the work. The Contractor will be required to coordinate all power shutdowns of existing facilities with the FAA, through the COR, seventy-two

(72) hours in advance. Each shutdown shall be limited and off-peak hours shall be required for testing or power shutdowns, with the facility placed back in service at the end of the workday, or as stipulated by the FAA.

H. Layout of Work - The Contractor shall field verify measurements and work from the established base lines and bench marks indicated on the drawings and shall be responsible for all measurements in connection therewith. The Contractor shall furnish, at his/her own expense, all stakes, templates, platforms, equipment, tools, materials, and labor as may be required in laying out any part of the work from the base lines and bench marks previously established. The Contractor will be held responsible for the execution of the work as detailed in the plans and specifications.

It shall be the responsibility of the Contractor to maintain and preserve all stakes and other marks previously established until authorized to remove them.

I. Permits, Inspection, Licenses, Certificates - The Contractor shall obtain and pay fees for permits, inspections, licenses, or certificates required by Federal, State and City/Town officials as necessary to perform the work, prior to starting construction, and in a timely manner to avoid delays in starting the job. The Contractor shall submit evidence that they have obtained all required permits, inspections, licenses, and/or certificates.

J. Compliance with Local and Other Codes - The Contractor shall comply with local and other codes and standards. Where the requirements of the specifications and drawings exceed those of the local or other codes, the Contractor shall comply with the requirements of the specifications and drawings.

K. Stop Work Orders – The COR may issue a “stop work order” if any part of the work being performed by Contactor or subcontractor fails to comply with the contract. The Contractor shall not be allowed any extension of time or compensation for damages by reason of, or in connection with, such work stoppage. Serious violations shall be

SUMMARY OF WORK PAGE 11

corrected immediately upon notice. Non-serious violations shall be corrected within 24-hours of the non-compliance notice. The Contractor may resume work, at the COR’s discretion, once satisfactory corrective action has been taken to correct the unsafe and unhealthy condition.

L. Protection of Existing Vegetation, Improvements and Structures - The Contractor shall take all precautions necessary to protect the existing facilities, equipment, buildings, foundations, vegetation, etc., during construction. Any areas damaged by the Contractor or any subcontractors, shall be repaired or replaced to their original conditions by the Contractor at no additional cost to the government. Repairs shall be approved by the COR and shall match to original finish. The Contractor shall provide all temporary covers, enclosures, barricades, etc., required to protect the existing facilities.

M. Schedules

1. Schedule - The Contractor shall, within ten (10) calendar days from date of award of contract, submit to the CO for approval a practical project schedule. The schedule shall show the order in which the Contractor proposes to carry out the work, the date on which he/she will start the several salient features (including procurement of materials, plant and equipment) and the contemplated dates for completing the work. The schedule shall be in the form of a progress chart of suitable scale to indicate the approximate percentage of work scheduled for completion at any time. The Contractor shall enter on the chart the actual progress at such intervals as directed by the CO. The project schedule shall include a milestone schedule for payments. The milestones should be stated with requested reimbursement for each milestone (based upon actual costs, overhead and profit).

2. Progress Schedule - The Contractor, if requested by the CO, shall submit a progress schedule at such intervals as directed by the CO. If the Contractor fails to submit a progress schedule within three (3) business days, the CO may withhold approval of progress payment estimates until the Contractor submits the required progress schedule.

3. Hours of Work – Shall be approved by the COR. Most of the work is expected to be performed during normal working hours; however, some work may be required afterhours. Work on weekends and Federal holidays shall be approved in advance by the COR in writing.

N. Site Access - Access to the site will be via a pre-determined route identified and agreed upon at the pre-construction conference.

SUMMARY OF WORK PAGE 12

O. Special Permits - The Contractor shall obtain and submit evidence of all necessary permits for the work. The Contractor shall abide by all requirements dictated by the city, state, federal, airport authority or municipality for such permits without any additional cost to the government.

P. Waste Disposal - The Contractor shall provide on-site containers for the collection of construction waste materials, debris and rubbish and their daily removal from the site.

Any spillage on access and haul routes shall be cleaned up immediately. All spoil, waste and debris removed from the work site and not specified for reuse or identified as salvageable items, or identified as contaminated contents shall be disposed of offsite in areas authorized by the applicable County, State and/or Local agencies and in accordance with current rules and regulations governing the disposal of such waste.

The Contractor, at no additional cost to the government, shall pay disposal fees and miscellaneous charges. Copies of all documentation of the disposal of any fuel or hazardous wastes will be submitted to the COR.

Q. Cleanup - The work site shall be kept clean and orderly during the progress of work.

After final inspection, but before final acceptance of the work, all exterior surfaces of the equipment shall be cleaned of dirt, mud, or oil accumulations. All debris shall be removed from the general site area.

R. O & M - Upon completion of the facility modifications, the Contractor shall provide operation and maintenance instructions for all new equipment. This information will then be retained by the COR (and the FAA) and used to reflect the as-constructed conditions.

S. Warranties - Documentation for the warranties shall be provided to the government upon completion of the project.

T. On-Site Toilet – Contractor shall provide on-site restroom facilities for personnel, (portable “biffie”, “port ‘p let”, “port ‘o potty”) for duration of the project, including cleanout, maintenance, delivery, setup, removal and cleanup. At no additional cost to Government. Cedar City RADAR site restrooms are insufficient for large numbers of personnel.

1.5 SAFETY

OSHA and FAA safety standards will be enforced. In keeping with such standards, the Contractor shall, at a minimum, provide:

A. Safety Plan - The Contractor shall have and submit a Safety Plan with the purpose of maintaining a safe working environment for construction workers employed on site.

SUMMARY OF WORK PAGE 13

The safety plan shall require a statement that the current Occupation Safety and Health Act (OSHA) regulations on safety in the construction industry, OSHA Title 29, Part 1910 and Part 1926, as well as FAA safety regulations are followed. The plan will be used by the COR to insure that the work is accomplished in accordance with accepted safety practices.

B. Trained Personnel - Personnel shall be properly trained in the usage of all equipment for which they will be required to use during the Contract. The COR may request documentation or other evidence of training at any time. Personnel without adequate training will be prohibited from using such equipment.

C. Lock Out / Tag Out – The Contractor shall employ and detail lock-out / tag-out procedures to employees working with and around electrical systems. When accessing an electrical panel, a FAA technician must be present prior to interrupting and energizing the breakers.

D. Safety Data Sheets - The Contractor shall have Safety Data Sheets (SDS) conforming to

Federal Standard 313A, written by the manufacturer, for all materials containing chemicals or other substances which may pose a hazard. One (1) copy of each SDS shall be submitted to the COR and one (1) copy of each SDS shall be kept on file at the job site at all times. The Contractor and subcontractors will be prohibited from handling any material which does not have an applicable SDS on file at the site until such SDS arrives on site.

E. Safety Equipment - The Contractor shall provide safety equipment including, but not limited to, a Red Cross approved First-Aid kit and the appropriate number of annually inspected, charged fire extinguishers with the proper NFPA rating.

F. HAZCOM Program - The Contractor shall have a hazard communications (HAZCOM) program. The Contractor and each subcontractor shall submit a copy of their HAZCOM program as well as a copy of their current OSHA 200 form, if requested.

G. Work Practices - Although OSHA regulations and the Contractor's Safety Plan will usually apply, the COR may consider certain work practices to be unsafe in accordance with Public Law 91-596, Part 5a and 5b. The COR may stop any operation which is in violation of the OSHA standards or fails to comply with the safety plan or other safe work practices.

H. Designated Foreman - When any construction activity is conducted at the site, the presence of a designated, competent contractor’s foreman is required at the job site.

The foreman must be qualified and capable of organizing and coordinating all activities of the Contractor and his subcontractors, and keeping a safe job site.

SUMMARY OF WORK PAGE 14

I. Work Force - The Contractor shall at all times, when construction activities are conducted, have a substantial number of workers for each task to proceed expeditiously and without generating delay, for lack of man-power. Wages of employees shall be subject to Davis-Bacon and related acts.

2.0 CONTRACTOR-FURNISHED MATERIAL AND EQUIPMENT

2.1 MATERIAL DELIVERIES

All material deliveries made under this contract shall be arranged for delivery to the Contractor's material staging area. This area shall be located as determined at the pre-construction conference.

2.2 STORAGE AND PROTECTION

The Contractor, through the COR, shall secure from FAA all necessary clearances for storage areas on site, including any time limitations upon the use of such areas. The storage and protection of Contractor material shall be the sole responsibility of the Contractor. The Contractor shall provide at his/her own expense all fencing, shelters and security personnel as may be necessary for the protection of the material and equipment.

2.3 PERTINENT INFORMATION

Any pertinent information listed about the contractor-furnished material and equipment shall be submitted to the COR.

3.0 EXECUTION

3.1 WORK SEQUENCE

The CDC ARSR is an active operational facility, which runs 24 hours a day, 7 days a week; therefore, all work shall be coordinated and accomplished on a “not to interfere with FAA operations” basis. Some of the work performed may have to be accomplished after hours to accommodate Air Traffic Operations. Many of the steps of this project can be done simultaneously or in a different order.

3.2 CONTRACTOR USE OF PREMISES

A. Use of the Site - Do not disturb portions of the site beyond the areas in which work is required.

B. Driveways and Entrances: Keep driveways and entrances serving the premises clear and available to the Government, the Government’s employees, and emergency

SUMMARY OF WORK PAGE 15

vehicles at all time. Do not use these areas for parking or storage of materials.

Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

C. Use of the Existing Building - Maintain the existing building in a watertight condition throughout the construction period. Repair damage caused by construction operations. Take all precautions necessary to protect the building during the construction period.

END OF SECTION

SUMMARY OF WORK
1.0 GENERAL SCOPE
A. General
5. The Contractor shall provide all temporary services required for construction.
B. Demolition
A. Installation
1.2 APPLICABLE DOCUMENTS
A. Applicable Documents - All FAA, Military, Federal, and industrial codes or standards, specifications, and contract drawings referenced in this and the following divisions form a part of this specification and are applicable only to the extent they ...
B. Applicable Publications - The publications listed below form a part of this specification to the extent referenced. The publications are referenced to in the text by basic designation only.
1.3 DEFINITIONS
1.4 CONSTRUCTION CONDITIONS

File details come from the government source that posted it. Updated .