This document is a Concept Cost Plan prepared by DCW Cost Management for the WCCA Building County Test Fit project, dated August 19, 2021. The cost estimate covers a 41,257 square foot facility with programmatic cost modeling for a multi-floor building involving various functional spaces. The building includes three floors with specific area allocations: Floor 1 (8,822 SF) contains Detox/Sobering/Stabilization and Support areas; Floor 2 (26,750 SF) includes Intake/Assessment, Women's Residential, Detox/Sobering, Kitchen, Storage, and Men's Residential spaces; and Floor 3 (5,685 SF) features additional Men's Residential areas. Sitework components include a Staff Patio and Gardens.

The total recommended budget for the project is $12,103,081, which breaks down to $293.36 per square foot. The cost estimate includes building elemental direct costs of $8,029,508, with additional line items for contingency (20%, $1,605,902), general contractor/general conditions (13.50%, $1,300,780), overhead and profit (5%, $546,809), and bonds and insurance (2%, $229,660). The estimate accounts for escalation to the start date of May 2022 at 3.33% ($390,422) and explicitly notes that sales tax and furniture, fixtures, and equipment (FF&E) are not included. The estimate assumes regular working hours and prevailing wages, based on design documents provided by Lrs Architects.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Concept Cost Plan August 19, 2021

Programatic Cost Modeling

WCCA Building - County Test Fit

DCW Cost Management 2Concept Cost Plan August 19, 2021

Programatic Cost Modeling

Prepared for: Alex Karel

Lrs Architects Inc

720 NW Davis St. #300

Portland OR 97209

720 NW Davis St. #300

Prepared by: Andrew Jonsson

DCW Cost Management

815 1st Avenue Suite 176

Seattle WA 98104

DCW Cost Management 3Concept Cost Plan August 19, 2021

Programatic Cost Modeling

Overall Summary

SF $/SF TOTAL

BUILDING

WCCA Building - County Test Fit 41,257 281.58 11,616,969

SITEWORK

Site Development 486,112

RECOMMENDED BUDGET 12,103,081

DCW Cost Management 4Concept Cost Plan August 19, 2021

Programatic Cost Modeling

Basis of Estimate

Assumptions and Clarifications

This estimate is based on the following assumptions and clarifications:

1 Costs are based upon the design package provided by Lrs Architects.

2 Sales Tax is not included

3 FF&E furnishings is not included

4 Escalation is included for a 3 year period ending Q2 2021.

5 Regular working hours and assumed using prevailing wages

DCW Cost Management 5Concept Cost Plan August 19, 2021

Programatic Cost Modeling

WCCA Building - County Test Fit Summary

% $/SF TOTAL

Gross Area: 41,257 SF

A Substructure 2% 5.47 225,750

B Shell 10% 29.41 1,213,500

C Interiors 17% 51.27 2,115,360

D Services 29% 84.79 3,498,165

E Equipment & Furnishings 5% 13.81 569,805

F Special Construction & Demolition 3% 7.50 309,428

G Sitework 1% 2.36 97,500

BUILDING ELEMENTAL - DIRECT COST 66% 194.62 8,029,508

Z10 Contingency 20.00% 13% 38.92 1,605,902

BUILDING ELEMENTAL COST INCLUDING CONTINGENCIES 80% 233.55 9,635,409

Z21 GR/GCs 13.50% 11% 31.53 1,300,780

Z22 Office Overhead & Profit 5.00% 5% 13.25 546,809

Z23 Bonds and Insurance 2.00% 2% 5.57 229,660

Z24 Permit 0.00% 0% 0.00 By Owner

BUILDING CONSTRUCTION COST BEFORE ESCALATION 97% 283.90 11,712,659

Z30 Escalation to Start Date (May 2022) 3.33% 3% 9.46 390,422

RECOMMENDED BUDGET 100% 293.36 12,103,081

181.37 6,451,920

1,290,384

7,742,304

36.28

851,653 387,115 154,846

9,135,918 274,077

9,409,995

REVISE AND

CONFIRM PER

DCW Cost Management 6Concept Cost Plan August 19, 2021

Programatic Cost Modeling

WCCA Building - County Test Fit Quantity Unit Rate Total

Program Areas

Floor 1 8,822 SF

Detox/Sobering/Stabilization 5,635 SF 157.50 887,513

Support 3,187 SF 122.50 390,408

Floor 2 26,750 SF

Intake/Assessment 4,115 SF 142.50 586,388

Women's Residential 6,830 SF 142.50 973,275

Detox/Sobering 5,975 SF 157.50 941,063

Kitchen 1,500 SF 257.50 386,250

Storage 1,880 SF 92.50 173,900

Men's Residential (New Construction) 6,450 SF 312.50 2,015,625

Floor 3 5,685 SF

Men's Residential (New Construction) 5,685 SF 277.50 1,577,588

Sitework

Staff Patio 600 SF 35.00 21,000

Gardens 4,500 SF 17.00 76,500

Tower - existing to remain NIC

Total 41,257 SF 194.62 8,029,508

6,451,92035,572 SF 181.37