CATT_-_Community_Services_Cost_Estimate.pdf

PDF 314 KB Posted

Attached to
Architect Services for the Center for Addictions Triage and Treatment (CATT) Project
Solicitation number
2022.116-RFP
Issued by
Washington County, Oregon

About this file

This document is a feasibility study cost plan prepared by DCW Cost Management for Washington County, Oregon, focusing on the Community Services Building Options at the 5250 Elam Young Parkway location. The study examines the conversion of an existing building into a Community Service Building (CSB), with a comprehensive analysis of renovation costs for a 40,940 square foot facility. The project scope involves a high-level conceptual design that includes heavy renovation of 23,157 square feet and light renovation of 17,783 square feet, with spaces designated for outpatient services, medical and dental areas, conference rooms, and various county services.

The total recommended budget for the project is $9,399,304, which breaks down to approximately $229.59 per square foot. The cost estimate includes detailed line items for foundations, superstructure, interior construction, mechanical systems, electrical systems, fire protection, and site improvements. The project is anticipated to start in Q1 2023 and will be delivered through traditional low-bid procurement with a minimum of four qualified general contractors. The estimate accounts for contingencies, escalation, and includes provisions for hazardous materials abatement, with the majority of work to be performed during typical daytime hours and the project location to be made unoccupied during construction.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DCW Cost Management 1Feasibility Study Cost Plan December 13, 2021

Washington County Oregon

Community Services Building Options

Prepared for: Alex Karel

Lrs Architects Inc

720 NW Davis St

Suite 300

Portland, OR 97209

Prepared by: Project Manager: Katya Gamarnik

Project Leader: Andrew Jonsson

DCW Cost Management

815 1st Ave

Suite 176

Seattle, WA 98104

205 259-2992

DCW Cost Management 2Feasibility Study Cost Plan December 13, 2021

Community Services Building Options

Contents

Overall Summary 3

Scope of Work 4

Basis of Estimate 5

Option 1 - 5250 Elam Young Pkwy Building 6

DCW Cost Management 3Feasibility Study Cost Plan December 13, 2021

Community Services Building Options

Overall Summary

SF $/SF TOTAL

Option 1 - 5250 Elam Young Pkwy Building Summary 40,940 229.59 9,399,304

TOTAL RECOMMENED BUDGET 9,399,304

DCW Cost Management 4Feasibility Study Cost Plan December 13, 2021

Community Services Building Options

Scope of Work

Project Scope Description

Project Design Documents

Procurement

The intended design package consists of cost planning for the Community Service Building (CSB) at a high conceptual level. The package consists of the conversion of one of the two potential buildings into the CSB. The goal of this study is to assess two options of developing the Community Service Building:

- Option 1 considers conversion of Elam Young building with possible seismic strengthening.

The cost report is based on the following documents, along with additional supplemental information:

- 220357 CATT - 5250 Elam Young Pkwy - Conceptual Test Fit, dated 11/12/08.

It is anticipated that the project will be delivered by traditional low bid procurement with a minimum of 4 qualified general contractors for competitive market pricing. The start date is anticipated for: Q1 2023.

DCW Cost Management 5Feasibility Study Cost Plan December 13, 2021

Community Services Building Options

Basis of Estimate

Assumptions and Clarifications

This estimate is based on the following assumptions and clarifications:

1 Hazardous materials abatement is included.

2 The majority of work will be performed during typical daytime hours.

3 Projects locations will be made unoccupied during construction.

4 Excludes jurisdiction fees and Owner's contingency.

5 Sales Tax is NOT shown and is assumed to be included in Owner's Project Cost Estimate.

DCW Cost Management 6Feasibility Study Cost Plan December 13, 2021

Community Services Building Options

Option 1 - 5250 Elam Young Pkwy Building Summary

% $/SF TOTAL

Gross Area: 40,940 SF

A10 Foundations 0% 0.59 24,052

A Substructure 0% 0.59 24,052

B10 Superstructure 2% 4.71 192,900

B20 Exterior Enclosure 0% 0.19 7,750

B30 Roofing 2% 3.85 157,541

B Shell 4% 8.75 358,191

C10 Interior Construction 7% 16.33 668,622

C20 Stairways 0% 0.00 0

C30 Interior Finishes 8% 19.51 798,792

C Interiors 16% 35.84 1,467,413

D10 Conveying Systems 0% 0.00 0

D20 Plumbing Systems 3% 7.10 290,561

D30 Heating, Ventilation & Air Conditioning 21% 48.58 1,988,737

D40 Fire Protection 3% 6.53 267,482

D50 Electrical Lighting, Power & Communications 14% 32.64 1,336,357

D Services 41% 94.85 3,883,137

E10 Equipment 1% 1.19 48,550

E20 Furnishings 1% 3.02 123,625

E Equipment & Furnishings 2% 4.21 172,175

F10 Special Construction 0% 0.00 0

F20 Selective Demolition 4% 10.24 419,252

F Special Construction & Demolition 4% 10.24 419,252

G20 G20 Site Improvements 0% 0.85 34,750

G Building Sitework 0% 0.85 34,750

BUILDING ELEMENTAL COST BEFORE CONTINGENCIES 68% 155.32 6,358,970

Contingency 15.00% 10% 23.30 953,846

BUILDING ELEMENTAL COST INCLUDING CONTINGENCIES 78% 178.62 7,312,816

General Conditions 8.00% 6% 14.29 585,025

General Requirements 7.50% 6% 14.47 592,338

Office Overhead & Profit 4.50% 4% 9.33 382,058

Bonds and Insurance 1.50% 1% 3.25 133,084

Permit By Owner

BUILDING CONSTRUCTION COST BEFORE ESCALATION 96% 219.96 9,005,321

Escalation to Start Date (Q1 2023) 4.38% 4% 9.62 393,983

RECOMMENDED BUDGET 100% 229.59 9,399,304

DCW Cost Management 7Feasibility Study Cost Plan December 13, 2021

Community Services Building Options

Option 1 - 5250 Elam Young Pkwy Building Quantity Unit Rate Total

Control Quantities

Building footprint 40,940 SF

Building - perimeter 1,115 LF

Building - height 15 LF

Program - area 40,940 SF

Heavy renovation 23,157 SF

Outpatient services 5,562 SF

Café 1,320 SF

Medical & dental 2,165 SF

Peer 2,180 SF

Hawthorn 10,135 SF

Lobby 1,550 SF

Restrooms/showers 180 SF

Lactation 65 SF

Light renovation 17,783 SF

SHS 910 SF

Conference rooms 3,037 SF

MDF 510 SF

County 9,655 SF

Hawthorn - break room 325 SF

Restrooms 910 SF

Other 185 SF

Circulation 2,251 SF

A10 Foundations 40,940 SF 0.59 24,052

A1010 Standard Foundations

No work anticipated NIC

A1030 Slab On Grade

Slab on grade - existing, patch and repair (25%) 10,235 SF 2.35 24,052

B10 Superstructure 40,940 SF 4.71 192,900

B1010 Floor Construction

Brace frames incl. plates and connections 3 EA 35,000.00 105,000

Porch, complete 265 SF 55.00 14,575

DCW Cost Management 8Feasibility Study Cost Plan December 13, 2021

Community Services Building Options

Option 1 - 5250 Elam Young Pkwy Building Quantity Unit Rate Total

B1020 Roof Construction

Blocking and strapping, allow 40,940 SF 1.50 61,325

Strengthening at re-entrant corners 4 LOC 3,000.00 12,000

B20 Exterior Enclosure 40,940 SF 0.19 7,750

B2010 Exterior Walls

No work anticipated NIC

B2020 Exterior Windows

No work anticipated NIC

B2030 Exterior Doors

HM glazed - double 1 EA 4,650.00 4,650

HM glazed - single 1 EA 3,100.00 3,100

B30 Roofing 40,940 SF 3.85 157,541

B3010 Roof Coverings

Patch and repair, as required 1 LS 3,500.00 3,500

Temporary roof 565 SF 5.25 2,966

Canopies 880 SF 85.00 74,800

B3020 Roof Openings

Skylights 565 SF 135.00 76,275

C10 Interior Construction 40,940 SF 16.33 668,622

C1010 Partitions

Solid and glazed walls

Metal stud framing - 2x6, complete 25,596 SF 15.00 383,940

Glazing - 3' cont. band 192 SF 85.00 16,320

Glazing - interior, allow 640 SF 85.00 54,392

C1020 Interior Doors

Doors and frames

Wood - single, flush 33 EA 2,750.00 90,750

Wood - single, relite 20 EA 2,950.00 59,000

HM - single, flush 2 EA 2,500.00 5,000

HM - double, flush 2 EA 4,375.00 8,750

DCW Cost Management 9Feasibility Study Cost Plan December 13, 2021

Community Services Building Options

Option 1 - 5250 Elam Young Pkwy Building Quantity Unit Rate Total

C1030 Fittings

Mirrors - restrooms 1 LS 5,000.00 5,000

Wayfinding and signage 40,940 SF 0.50 20,470

Whiteboards and tack boards 1 LS 20,000.00 20,000

Corner guards and kick plates 1 LS 5,000.00 5,000

C20 Stairways 40,940 SF

C2010 Stair Construction

No work anticipated NIC

C30 Interior Finishes 40,940 SF 19.51 798,792

C3010 Wall Finishes

Paint, new partitions 47,353 SF 1.85 87,602

Paint, existing partitions 3,345 SF 1.85 6,188

Tile restroom walls to 7' ht. 676 SF 15.50 10,481

Allow for miscellaneous graphics and special finishes 1 LS 10,000.00 10,000

Acoustic wall panel - allow 2,500 SF 30.00 75,000

C3020 Floor Finishes

Walk-off mat 200 SF 15.00 3,000

Sealed concrete 510 SF 2.25 1,148

Carpet tile 28,132 SF 6.50 182,858

Resilient flooring 11,047 SF 8.50 93,900

Tile floor - locker and restrooms 1,251 SF 16.00 20,016

C3030 Ceiling Finishes

Open to structure, paint 510 SF 1.85 944

Gypsum board ceilings, painted 1,251 SF 6.00 7,506

ACT - suspended acoustical ceiling tile 36,309 SF 5.50 199,700

Wood slat ceiling - decorative 2,870 SF 35.00 100,450

D10 Conveying Systems 40,940 SF

No work anticipated NIC

DCW Cost Management 10Feasibility Study Cost Plan December 13, 2021

Community Services Building Options

Option 1 - 5250 Elam Young Pkwy Building Quantity Unit Rate Total

D20 Plumbing Systems 40,940 SF 7.10 290,561

D20 Plumbing Fixtures and Domestic Water Distribution

Trade demolition - plumbing, heavy 23,157 SF 2.25 52,103

Sanitary fixtures

Water closets 5 EA 1,550.00 7,750

Lavatories 5 EA 1,200.00 6,000

Shower 3 EA 2,750.00 8,250

Sink, counter set 9 EA 1,080.00 9,720

Drinking fountains 2 EA 4,500.00 9,000

Janitor sink 1 EA 1,300.00 1,300

Hose bibs 4 EA 750.00 3,000

Floor drains 7 EA 850.00 5,950

Connections 1 LS 5,000.00 5,000

Piping and drainage

Domestic cold water - 2" dia., PEX 1,508 LF 25.00 37,700

Sanitary piping and vent 2,160 LF 45.00 97,200

Pipe insulation 1,508 LF 11.00 16,588

Valves and specialties 1 LS 10,500.00 10,500

Hot water heaters 2 EA 5,000.00 10,000

Expansion tanks 2 EA 3,750.00 7,500

Backflow preventors 1 EA 3,000.00 3,000

D2040 Rain Water Drainage

No work anticipated NIC

D30 Heating, Ventilation & Air Conditioning 40,940 SF 48.58 1,988,737

D3020 Heat Generating Systems

Trade demolition - mechanical 40,940 SF 4.50 184,230

VAV units 27 EA 1,760.00 48,036

Air cooled chiller 30 TN 2,000.00 60,000

Air source heat pump 250 TN 1,096.00 274,000

Exhaust fans and connections 40,940 SF 3.00 122,820

DOAS, complete 40,940 SF 8.50 347,990

Unit heaters 5 EA 1,750.00 8,750

Diffusers and grills 103 EA 180.00 18,540

Ductwork 38,893 LB 12.50 486,163

Seismic bracing 40,940 SF 1.70 69,598

Ancillaries 1 LS 75,000.00 75,000

DCW Cost Management 11Feasibility Study Cost Plan December 13, 2021

Community Services Building Options

Option 1 - 5250 Elam Young Pkwy Building Quantity Unit Rate Total

DDC controls 40,940 SF 6.50 266,110

Testing and balancing 120 HR 125.00 15,000

Commissioning 100 HR 125.00 12,500

D40 Fire Protection 40,940 SF 6.53 267,482

D4010 Sprinklers

Wet system - modifications to existing 40,940 SF 3.55 145,337

Dry pipe system, complete 880 SF 8.50 7,480

D4030 Fire Protection Specialties

Fire extinguisher boxes 8 EA 260.00 2,080

CO2 alarm system, allow 40,940 SF 2.75 112,585

D50 Electrical Lighting, Power & Communications 40,940 SF 32.64 1,336,357

D5010 Electrical Service & Distribution

Trade demolition - electrical, heavy 23,157 SF 3.25 75,260

Trade demolition - electrical, light 17,783 SF 1.25 22,229

Main distribution board - existing to remain

Distribution panels - modifications as required 1 LS 32,500.00 32,500

Secondary conduit and feeder 23,157 SF 4.00 92,628

Ancillaries and equipment 1 LS 15,000.00 15,000

D5020 Lighting & Branch Wiring

Lighting controls 23,157 SF 4.50 104,207

Lighting fixtures, LED 40,940 SF 10.15 415,541

Branch wiring including switches 23,157 SF 5.00 115,785

Exterior lighting 1 LS 5,000.00 5,000

User convenience power 23,157 SF 4.50 104,207

D5030 Communications & Security

Phone and data including wiring and conduit 23,157 SF 2.50 57,893

Fire alarm system 23,157 SF 2.50 57,893

Paging system rough in 23,157 SF 1.50 34,736

Wireless access points 5 EA 1,650.00 8,250

A/V and sound system - FF&E

CCTV 40,940 SF 2.50 102,350

Access control 2 LOC 5,500.00 11,000

DCW Cost Management 12Feasibility Study Cost Plan December 13, 2021

Community Services Building Options

Option 1 - 5250 Elam Young Pkwy Building Quantity Unit Rate Total

D5040 Electrical Specialty

Electrical to mechanical systems 40,940 SF 2.00 81,880

E10 Equipment 40,940 SF 1.19 48,550

E1010 Commercial Equipment

Kitchenette equipment - allow 1 LS 25,000.00 25,000

Washer 2 EA 650.00 1,300

Dryer 2 EA 650.00 1,300

Refrigerator 1 EA 2,200.00 2,200

Water machine 1 EA 1,500.00 1,500

Ice machine 1 EA 3,500.00 3,500

Vending machine - by other NIC

E1020 Institutional Equipment

By Owner NIC

E1090 Other Equipment

Lockers 1 LS 7,500.00 7,500

Restroom fitout 5 EA 1,250.00 6,250

E20 Furnishings 40,940 SF 3.02 123,625

E2010 Fixed Furnishings

Casework - café 30 LF 650.00 19,500

Casework - coffee bar 15 LF 575.00 8,625

Casework - treatment 120 LF 375.00 45,000

Casework - exam 55 LF 375.00 20,625

Casework - lactation 5 LF 375.00 1,875

Reception desk 20 LF 650.00 13,000

Casework - other, allow 1 LS 10,000.00 10,000

Bench - allow 1 LS 5,000.00 5,000

FF&E - by Owner NIC

F10 Special Construction 40,940 SF

F1040 Special Facilities

No work anticipated NIC

DCW Cost Management 13Feasibility Study Cost Plan December 13, 2021

Community Services Building Options

Option 1 - 5250 Elam Young Pkwy Building Quantity Unit Rate Total

F20 Selective Demolition 40,940 SF 10.24 419,252

F2010 Building Elements Demolition

Temporary protection, structural elements to remain 40,940 SF 1.25 51,175

Structural

Demo - cut roof for new skylights 565 SF 9.50 5,368

Architectural

Demo - all interior systems and finishes, heavy renovation 23,157 SF 8.25 191,045

Demo - finishes, light renovation 17,783 SF 3.85 68,465

Demo - cut for new exterior doors 2 LOC 425 850

F2020 Hazardous Components Abatement

Abatement, allow 40,940 SF 2.50 102,350

G Building Sitework 40,940 SF 0.85 34,750

G20 Site Improvements

Green wall - vegetated, incl. earthwork and prep 400 SF 52.50 21,000

Landscape restoration - allow 5,000 SF 1.25 6,250

Site furnishings - allow 1 LS 5,000.00 5,000

Site utilities - adjustments as required 1 LS 2,500.00 2,500

File details come from the government source that posted it. Updated .