Carpenter_Shop,_Gas_Storage,_Water_Dept_Asbestos_Survey_Report.pdf

PDF 6 MB Posted

Attached to
Demolition, Asbestos Abatement, Lead Paint & Hazardous Materials Removal
Solicitation number
2026-063
Issued by
Alachua County, Graceville City, Florida

About this file

This is an Asbestos Survey Report prepared for Collin County, Texas, documenting asbestos-containing materials (ACM) identified across multiple county facilities including the Carpenter Shop, Gas Storage facility, and Water Department administrative and storage buildings. The survey provides the technical foundation for the associated demolition and asbestos abatement project (IFB #2026-063) at the Collin County Adult Detention Facility (CCADF) Lower B. The project scope encompasses full asbestos abatement of all identified ACM, lead-based paint waste handling and disposal, removal of hazardous building components, and complete demolition to slab or subgrade with backfill and site stabilization. Two mandatory pre-bid meetings and site walks are scheduled for December 2, 2025, at 1:30 p.m. and December 4, 2025, at 10:00 a.m., both at the Collin County Central Plant in McKinney, Texas. Attendance at one meeting is required to obtain electrical and mechanical drawings, which are available only upon signing a Non-Disclosure Agreement. The sealed bid submission deadline is December 18, 2025, at 2:00 p.m., with bid opening occurring the same day. The successful contractor must be awarded within 90 calendar days of bid opening.

The estimated probable construction cost is $1,100,000.00, with bidders required to provide 5% bid security and comply with prevailing wage requirements, federal E-Verify and immigration verification, debarment certification, and conflict of interest disclosure. The contractor must furnish performance, payment, and two-year maintenance bonds within ten calendar days of contract award. Liquidated damages of $500 per calendar day apply for failure to meet the completion schedule. The contract includes a one-year warranty for mechanical systems and two to five years for electrical equipment and generators from the date of substantial completion. Comprehensive insurance coverage is required, including workers' compensation, commercial general liability, automobile liability, and umbrella liability. No specific set-aside designations for disadvantaged enterprises are mentioned in the procurement documents. Full regulatory compliance with EPA, OSHA, DEP, and Florida Department of Health requirements is mandated, with the successful bidder responsible for providing all labor, materials, equipment, permitting, disposal, and documentation necessary for project completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Carpenter Shop and Gas Storage

Water Department Admin/Water Department Storage

File details come from the government source that posted it. Updated .