Carbon_Coal_Road_McKinley_County_Industrial_Park_Waterline_Project_.pdf
PDF 31 MB Posted
- Attached to
- Carbon Coal Road, McKinley County Industrial Park Waterline - US Department of Commerce (EDA) 08-79-05634
- Solicitation number
- ITB-2609
- Issued by
- Quay County, New Mexico
About this file
This file contains project specifications and procurement documents for the City of Gallup, New Mexico's Carbon Coal Road, McKinley County Industrial Park Waterline Project, funded by the US Department of Commerce Economic Development Administration (EDA) under grant 08-79-05634. The project involves the installation of new waterline infrastructure consisting of approximately 2,395 linear feet of 12-inch CL350 ductile iron pipe on Carbon Coal Road and 535 linear feet of 8-inch CL350 ductile iron pipe on Industrial Park Road. Deliverables include gate valves, air release valves, fire hydrant assemblies, waterline tie-ins, fittings, trenching, rock excavation, backfilling, and traffic control measures. Sealed bids must be submitted electronically via the City's OpenGov procurement portal by 2:00 pm local time on January 5, 2026, with a deadline for submitting questions by December 16, 2025 at 5:00 pm. The contractor is expected to commence work within the timeframe specified in the Notice to Proceed and complete the entire project within 90 calendar days, including anticipated weather delays. The contract includes a one-year performance and materials warranty period following substantial completion.
The Engineer's Estimate establishes a total project cost of $834,458.63, including New Mexico Gross Receipts Tax at 8.0625%. Bidders must submit a bid bond equal to five percent of the bid sum and, upon contract award, provide performance and payment bonds each in 100 percent of the contract amount. The procurement offers preferences to New Mexico resident contractors and New Mexico resident veteran contractors certified by the State Department of Taxation and Revenue. All contractors and subcontractors must be registered with the New Mexico Labor and Industrial Division for public works projects exceeding $60,000 and must comply with prevailing wage requirements per the Public Works Minimum Wage Act. Subcontractors exceeding $5,000 must be listed with the bid, and those exceeding $125,000 must furnish separate performance bonds. Liquidated damages are assessed at $500 per calendar day for failure to meet the 90-day completion deadline. The contractor is responsible for all costs related to traffic control, storm water pollution prevention, construction staking detail, independent testing, insurance coverage, and waste disposal.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .