2-Addendum.01.pdf

PDF 34 KB Posted

Attached to
Gunkle Mill Roof Replacement
Solicitation number
US.193081
Issued by
Chester County, Mcconnellsburg Borough, Pennsylvania

View the file

Other files

File Type Posted
1-BID SPEC 202511304.05.pdf PDF
3-Addendum.02.pdf PDF
6-Bid Tabulation 11340.05.pdf PDF
5-Pricing Section BT-07BE 1754329080.2866802.xlsx XLSX spreadsheet
4-ADDENDUM.03.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

011340.05 A1-1 ARRO

EAST WHITELAND TOWNSHIP – GUNKLE ROOF 07/11/2025

ARRO Consulting, Inc. July 14, 2025 108 West Airport Road Lititz, PA 17543

ADDENDUM NO. 1

EAST WHITELAND TOWNSHIP

GUNKLE MILL ROOF REPLACEMENT

In accordance with the requirements of the “Instructions to Bidders,” this Addendum shall be attached to and become a part of the Contract Documents for the above referenced project.

Concerning the Project Manual

(A)Section 07313 – DELETE and REPLACE in its entirety, attached to this addendum

Miscellaneous (Public, Q & A, Clarifications, Pre-Bid Meeting Minutes etc.)

(A)American Rod Company asked “There is an existing lightning protection system that is in disrepair. Will there be a reinstall and bring up to standards scope added to the project?

(B) Answer 1: All questions prior to the mandatory pre-bid meeting will be compiled and answered after the Pre-Bid Meeting on Wednesday July 16th, 2025 via posting on PennBid.

(1) – If you observed an issue with the lightning protection system, please feel free to share your observations and bring a proposed solution to the issue to the mandatory Pre-Bid Meeting for discussion.

BIDDERS MUST ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE SPECIFIED

PLACE ON THE BID FORM. THE ABSENCE OF THIS ACKNOWLEDGMENT WILL BE

CAUSE FOR REJECTION OF THE BID.

11340.05 07313-1 ARRO

EAST WHITELAND TOWNSHIP – GUNKLE ROOF (PennBid)

SECTION 07313

WOOD SHINGLES AND SHAKES

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. Wood Shingles

B. Underlayment

1.02 RELATED SECTIONS

A. Rough Carpentry: Section 06100.

B. Flashing and Sheet Metal: Section 07600

C. Roof Specialties: Section 07710

D. Joint Sealers: Section 07900

1.03 REFERENCES

A. CSSB-97 Grading Rules

B. ASTM D226 - Asphalt-Saturated Organic Roofing Felt for Use in Membrane

Waterproofing and Built-up Roofing.

C. SMACNA Architectural Sheet Metal Manual

1.04 ACTION SUBMITTALS

A. Product Data: Submit manufacturer’s descriptive product data and current specification indicating compliance with quality standards previously specified. Pattern and color selected with submittal approval.

11340.05 07313-2 ARRO

B. Samples for Initial Selection: For each type of cedar wood shingle ridge cap shingles and ridge vent indicated.

1. Include similar Samples of trim and accessories involving color selection

C. Samples for Verification: For the following products, of sizes indicated, to verify color selected:

1. Wood Shingle: Three (3) Full size. Illustrating the finish selection of shake.

2. 8-inch square samples of painted sheet metal flashing.

3. Ice & Water Shield

4. Cedar Breather Ventilation System

5. 30 lb. Asphalt saturated felt paper

6. 1/3/4: ring shank stainless steel nails

7. Ridge Cap Shingles: Full size.

8. Self-Adhering Underlayment: 12 inches square.

D. Research and Evaluation Reports: Evidence of shingle and shake manufacturers and grading agency’s compliance with building code in effect for Project, from a model code organization acceptable to authorities having jurisdiction.

E. Warranties: Special warranties specified in the Section.

1.06 INFORMATIONAL SUBMITTALS

A. Qualification Data: Installer shall have at least 5 years’ experience in cedar shake roofing..

11340.05 07313-3 ARRO

B. Product Test Reports: Based on evaluation of comprehensive tests performed by manufacturers and witnessed by a qualified testing agency, for cedar wood shingles.

C. Research/ Evaluation Reports: For each type of cedar wood shingle required, from the ICC.

D. Warranties: Sample of special warranties

1.07 CLOSEOUT SUBMITTALS

A. Maintenance Data: For each type of cedar wood shingle to include in maintenance manuals.

1.08 MAINTENANCE MATERIAL SUBMITTALS

A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

1. Cedar Shingle Wood: 50 sq. ft. of each type, in unbroken bundles

1.09 QUALITY ASSURANCE

A. Grading Agency Qualifications: An independent testing and inspecting agency recognized by authorities having jurisdiction as qualified to label shingles or shakes for compliance with referenced wood shingle and shake grading rules.

B. Source Limitations: Obtain shingles or shakes throughout one source from a shingle manufacturer.

C. Mockups: Before installing, construction mockups for each form of construction and finish required to verify selections made under Sample submittals and to demonstrate aesthetic effects and qualities of materials and execution. Build mockups to comply with the following requirements, using materials indicated for completed

Work.

11340.05 07313-4 ARRO

1. The first 5’ x 5’ area of roof shingles to be inspected and approved by the

East Whiteland Township Building Inspector before proceeding

2. Notify the Building Inspector 3-days in advance of the dates and times when mockups will be constructed.

3. Demonstrate the proposed range of aesthetic effects and workmanship

4. Obtain Building Inspector’s approval of mockups before proceeding with construction.

5. Maintain mockups during construction in an undisturbed condition as a standard for judging the completed Work.

1.10 DELIVERY, STORAGE, AND HANDLING

A. Deliver materials with manufacturer’s labels intact and legible to Project Site in unopened bundles or containers.

B. Store roofing shingles and associated materials protected from contamination from wet, damp or dirty surfaces. Do not cover stored shingles and associated materials with plastic coverings; use tarpaulins or other weatherproof non-plastic coverings. Comply with manufacturer’s written instructions for Project Site storage, handling, and protection.

D. Store rolled goods on end.

1.11 PROJECT CONDITIONS

A. Do not install underlayment or shingles on wet surfaces.

B. Weather Limitations: Proceed with work only when existing and forecast weather conditions permit work to be installed according to the manufacturer’s written instructions and warranty requirements, and when substrate is completely dry.

11340.05 07313-5 ARRO

C. Do not apply shingles when the air temperature is below 40 degrees or above 90 degrees F.

1.12 PROJECT DEBRIS

A. Disposal of all removed roof materials shall be the responsibility of the contractor.

B. The areas around the outside of the structure and inside the attic shall be cleaned of all debris.

1.13 DAMAGES

A. At all times during construction, the inside and outside of the structure, the existing vegetation and any other features shall be protected.

1.14 GUARANTEES

A. General Warranty: The special warranties specified in this article shall not deprive the Owner of other rights the Owner may have under other provisions on the Contract

Documents and shall be in addition to, and run concurrent with, other warranties made by the contractor under requirements of the Contract Documents.

B. Special Product-Defect Warranty: Submit a written warranty, signed by shingle manufacturer ensuing that shingles, when installed according to manufacturer’s written instructions, will remain free of water infiltration and agreeing to furnish replacement shingles or refund a pro-rata portion of the amount originally paid for the defective shingles due to originals product defects, for the specified warranty period.

C. The roofing applicator shall provide the Owner with a guarantee for shingles and installation. The guarantee shall pay the cost of repairing or replacing defective shingles as may be required to prevent leaks, but such liability shall not exceed the original cost of the shingles or their application.

1. Warranty Period: 25 years from date of Substantial Completion.

11340.05 07313-6 ARRO

D. Provide a written warranty from the contractor that the installed system and components will remain free of water infiltration.

1. Warranty Period: 1 year from date of Substantial Completion

E. Provide a written warranty against damage due to wind uplift and blow-off when subjected to wind velocities not in excess of 60 mph, or higher as appropriate for the area.

1. Warranty Period: 1 year from date of Substantial Completion.

F. The guarantee shall not apply if the roof is altered in any way after application of the shingles. Additionally, the shingle manufacturer must be notified promptly of failures.

PART 2 - PRODUCTS

2.01 MATERIALS, GENERAL

A. Grading Standards: Conform to the Cedar Shake & Shingle Bureau’s ‘Grading

Rules for Cedar Shakes and Shingles (CSSB-97),’ as recognized by ICC for use with

Certi-label® Western Red Cedar products.

B. Identification: Attach a label to each bundle of shingles: identify manufacturer, references to model code approval, type of product, grade, dimensions, and approved agency.

2.02 ROOFING

A. Cedar Shingles

Taper-sawn, smooth-sawn Western Red Cedar shingles conforming to CSSB-97 grading standards.

1. Grade: Premium Grade; taper-sawn; 100% edge grain; 100% clear wood;

free from knots, sapwood, and other visual defects.

2. Size: Nominal 18 inches long x 7/8 inch thick at the butt.

11340.05 07313-7 ARRO

3. Hip and Ridge Units: Factory-assembled, No. 1 Blue Label, 18 inches long x 7/8 inch thick, with maximum 10-inch exposure.

4. Exposure: Install with 7-1/2 inch weather exposure for the main field of the roof.

5. Starter Course: Install double layer started course along fascia.

6. Overhang: Provide 1.5” overhang at the fascia and 1” overhang along rakes.

2.04 UNDERLAYMENT

A. Felt Underlayment: Asphalt-saturated organic felt, un-perforated, complying with

ASTM D 226, Type II, No. 30.

1. Underlayment shall be installed between each row of shingles.

B. Perimeter Underlayment: Polyethylene-sheet-backed, self-adhering, polymer-modified, bituminous sheet underlayment; complying with ASTM D 1970; minimum

40 mils thick. Provide primer when recommended by underlayment manufacturer.

1. Must be high temperature rated for use under roofing.

2. Required: On outer three feet of entire roof perimeter

3. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, the following:

A WinterGuard; CertainTeed Corporation.

B. Bituthene Ice and Water Shield; W.R. Grace & Co.

C Nordshield Ice and WaterGard: Nord Bitumi U.S., Inc.

D. F210; Northern Elastomeric, Inc.

E. Polyguard Deck Guard; Polyguard Products, Inc.

F. Polyken 640 Underlayment Membrane; Polyken Technologies.

G. QSC-707; Quaker Construction Products.

H. Moisture Guard; Tamko Asphalt Products, Inc.

I. Weather Watch; GAF Building Materials Corp.

J. Jiffy Seal Ice and Water Guard; Protecto Wrap Co.

K. Ice Guard Membrane No 108-AG; Royston Laboratories, Inc.

11340.05 07313-8 ARRO

2.05 FASTENERS

A. Nails: 316 ring shank stainless-steel nails of sufficient length to penetrate through or at least ¾ inch into sheathing. Copper, bright steel, or blue-steeled nails are unacceptable.

1. Shingle Nails: Provide Box-type nails at wood shingles as per NRCA

Roofing & Waterproofing Manual – Fourth Edition.

B. When the fastener fails to penetrate decking, remove fastener and secure it in a new location. Fill void with roofing manufacturer’s recommended sealant.

2.06 SHEET METAL FLASHING

A. Base Bid: Provide new lead coated copper materials as detailed in Specifications section 07600 for all new flashing used:

B. Reuse existing Sheet metal flashing and replace as required.

C. Other Sheet Metal Flashing: Of types and thicknesses indicated, but in thicknesses not less than that specific or required by referenced standards.

2.07 ROOFING ACCESSORIES

A. Roof Ventilation:

1. Continuous ridge vent with cedar cap – pre-manufactured or field-fabricated, to match shingle finish and material. Ridge vent must provide a minimum of 18 sq. in. of net free ventilation per linear foot and be securely fastened per manufacturer recommendations.

B. Underlayment: Organic felt saturated with refined asphalt and manufactured to meet requirements of ASTM Designation D226 (unperforated); No. 15 Asphalt Felt.

C. Ice and Water Shield Underlayment: Self-adhesive, cold-applied composite sheet similar to CertainTeed Winterguard, Royston Ice Guard 108AGN, or approved equal.

D. Metal Drip Edge: None required

11340.05 07313-9 ARRO

PART 3 - EXECUTION

3.01 EXAMINATION

A. Examine Substrates for compliance with requirements for substrates, installation tolerances, and other conditions affecting performance of Word specified in the

Section. Do not proceed with installation until satisfactory conditions have been corrected and accepted by the Building Inspector

3.02 PREPARATION

A. Clean substrates of projection and substances detrimental to application. Cover knotholes or other minor voids in substrate with sheet metal flashing secured with noncorrosive roofing nails.

B. Coordinate installation with flashing and other adjoining work to ensure proper sequencing.

1. Do not install roofing material under all vent stacks and other penetrations through roof sheathing have been installed and are securely fastened against movement.

3.03 INSPECTION

A. Verify that the work of other Trades, and other Sections affecting this work, is complete to the extent that the work of this Section may be performed in accordance with the shingle manufacturer’s printed installation instructions.

B. Repair or corrective work required to plywood roof deck performed as work of

Section 06100.

C. Repair or corrective work required to skip sheathing, soffit and facia support work prior to covering performed as work of Section 06300.

3.04 INSTALLATION, GENERAL

A. Comply with the manufacturer’s written installation instructions and the following:

1. CSSB’s “Design and Application Manual for New Roof Construction.”

11340.05 07313-10 ARRO

2. NRCA’s “The NRCA Roofing and Waterproofing Manual”: Section “The

NRCA Steep Roofing Manual,” Chapter “Wood Shingle and Wood Shake Roofing.”

3.05 WOOD SHINGLE ROOFING INSTALLATION

A. Class B. Rated Roof: Install Class B fire-retardant treated shingles on new vertical strips over existing solid sheathing in a straight-line course application.

B. Felt Underlayment: Apply felt underlayment horizontally over the entire surface to receive wood shingles, lapping ends and succeeding courses a minimum of 2 inches. Fasten felt with a sufficient number of galvanized roofing nails or non-corrosive staples to hold underlayment in place until shingles are applied.

1. Omit Felt underlayment at areas of perimeter underlayment. Lap felt underlayment over perimeter underlayment as recommended by manufacturer, but not less than 2 inches.

C. Perimeter Underlayment: Apply minimum 36-inch-wide layer of perimeter underlayment along entire perimeter of surface to receive wood shingles, including at eaves, ridges, hips, valleys, skylights, dormers, and edges, and around projections through roof. Extend perimeter underlayment a minimum of 24 inches inside exterior wall line at edges.

D. Install wood shingles, beginning at lower end, with double layer starter course, projecting shingles 1-1/2 inches beyond fascia, but only 1 inch apart at gutters. Space adjoining shingles 1/4 to 3/8 inch apart, attach each shingle with 2 fasteners spaced 3/4 to 1 inch from edge of shingle and 1-1/2 inches above butt line of subsequent course.

Stagger edge joints a minimum of 1-1/2 inches in succeeding courses. Prevent alignment of vertical joints in every third course. Drive fasteners tight to top surface of shingles without crushing wood.

1. Weather Exposure: 7.5 inches for 18-inch-long shingles

2. Edges: Cut and fit singles at edges to provide maximum weather protection.

3. Ridges: Install continuous ridge vent centered along ridge, beneath cedar ridge cap shingles. Ensure proper ventilation and secure fastening per vent and shingle manufacturer instructions.

11340.05 07313-11 ARRO

E. Flashing: Install metal flashing as indicated and according to details and recommendations of NRCA’s “The NRCA Roofing and Waterproofing Manual”:

Section “The NRCA Steep Roofing Manual,” Chapter “Wood Shingle and Wood

Shake Roofing.”

1. Chimney flashing shall extend up the roof slope to a point equal in height to the flashing on the chimney but never less than 1 ½ times the shingle exposure.

2. Apron counter flashing shall extend to within 1 inch of the surface of the finished roof.

3. Step flashing shall be used where vertical surfaces occur in connection with slopes. They shall be formed of separate pieces. Flashing shall extend horizontally not less than 3 inches and up the vertical wall so that they shall be lapped by the counter flashing not less than 4 inches.

3.06 ADJUSTING

A. Replace damaged materials specified in this Section with new materials that meet requirements.

B. Install shingles in accordance with manufacturer’s directions printed on each shingle package, and as augmented herein.

C. Install the recommended nail quantity per shingle. Locate nails to provide recommended shingle exposure, 1 inch from each end of the shingles and 1½ inches to either side of the cutouts.

D. Drive nails straight, heads flush with shingle surface. Exposed nail heads not permitted.

E. Prior to shingle installation install underlayment in a single layer with 2-inch edge overlap horizontally and 4-inch overlap on ends.