C5613684-D_Notice_to_Contractors.pdf

PDF 1 MB Posted

Attached to
C5613684-D CHCF Potable Water Treatment System
Solicitation number
0000040952
Issued by
San Joaquin County, Stockton City, California

About this file

This Notice to Contractors and Instructions to Bidders document pertains to a construction contract issued by the California Department of Corrections and Rehabilitation (CDCR) for the California Health Care Facility (CHCF) located in Stockton, California. The project involves construction of a new Potable Water Treatment System (PWTS), including a chlorination boosting system to supplement water disinfection from the City of Stockton, an above-ground chemical storage tank, chemical injection system with electrical and mechanical components, a 900-square-foot pre-engineered metal building to house equipment, site work, utilities, and integration with an existing Supervisory Control and Data Acquisition (SCADA) system. The mandatory pre-bid conference and site walk is scheduled for 10:00 AM on December 2, 2026, with bid submission due at 11:00 AM on January 7, 2027, and public bid opening at 2:00 PM on January 8, 2027. The anticipated Notice to Proceed is April 6, 2027, with project completion 578 days from issuance of that notice. Drawings and specifications are available as of November 16, 2026, and the deadline for letters of inquiry is 5:00 PM on December 10, 2026.

The State's estimate for the project is approximately $3,380,000.00, with bidder's security required at 10 percent of the bid amount. The contract mandates a minimum 3 percent Disabled Veteran Business Enterprise (DVBE) participation goal, with failure to meet this requirement resulting in bid rejection. A 5 percent small business preference (not to exceed $50,000) is available to certified small businesses submitting bids by the deadline. Prime contractors must possess a valid California Contractors State License Board "A - General Engineering Contractor" license at time of bid and throughout the project duration. Prevailing wage requirements apply pursuant to California Labor Code Section 1773. Performance and payment bonds, each equal to 100 percent of the contract amount, must be provided by the successful bidder. The contract is subject to audit rights retained by CDCR for three years following final payment.

View the file

Other files

File Type Posted
Attachment_I_-_Geotechnical_Engineering_Report.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

California Department of Corrections and Rehabilitation

NOTICE TO

CONTRACTORS

Division of Administrative Services Office of Business Services Contracts Management Branch

Updated: June 2025

California Health Care Facility Potable Water Treatment System Bid Number C5613684-D

NOTICE TO CONTRACTORS

STATE OF CALIFORNIA

DEPARTMENT OF CORRECTIONS AND REHABILITATION

CALIFORNIA HEALTH CARE FACILITY

POTABLE WATER TREATMENT SYSTEM

The California Department of Corrections and Rehabilitation (CDCR) intends to receive bids and award a contract for the construction of a new Potable Water Treatment System (PWTS) for the California Health Care Facility (CHCF) located in Stockton, California.

PROJECTED TIMETABLE

The following dates are set forth for informational and planning purposes only and are subject to change.

Drawings and Specifications available to Prospective Bidders November 16, 2026

Mandatory Pre-Bid Conference/Site Walk 10:00 AM on December 2, 2026

Bid Proposal Available After Pre-Bid Conference

Letters of Inquiry 5:00 PM on December 10, 2026

Questions and Answers Addendum Posted December 30, 2026

Submission of Bid 11:00 AM on January 7, 2027

Public Bid Opening 2:00 PM on January 8, 2027

Anticipated Date for Notice to Proceed April 6, 2027

Project Completion 578 Days from Issuance of Notice to Proceed

GENERAL PROJECT AND BID INFORMATION

Sealed proposals for construction of the project will be received at the California Department of Corrections and Rehabilitation (CDCR), Office of Business Services, Contracts Management Branch, CDCR-CMB-Non-IT-Service-Bids@cdcr.ca.gov as specified in the Projected Timetable above, at which time they will be publicly opened and read aloud. The proposals relate to the performance of the following work:

Work Covered by Contract: In general, the CHCF PWTS project will construct a new chlorination boosting system to supplement the disinfection of potable water delivered by the City of Stockton.

The project will construct a PWTS consisting of an above ground chemical storage tank, chemical injection system with required electrical, mechanical, metering and control equipment. An approximately 900 square foot pre-engineered metal building, with site work and utilities, will also be constructed to house the chemicals and associated equipment. Integration of the new

Supervisory Control and Data Acquisition (SCADA) system with the existing SCADA system is also required. Upon completion, the project must ensure compliance with the Environmental Protection Agency (EPA) and State Water Resources Control Board (SWRCB) drinking water quality standards related to chlorine residual at CHCF.

A mandatory pre-bid conference and site inspection is scheduled at CHCF located at 7707 Austin Rd, Stockton, CA 95215 on the date and time specified in the Projected Timetable.

LICENSING REQUIREMENTS

The Prime Contractor shall possess a valid “A - General Engineering Contractor” license issued by the California Contractors State License Board (CSLB) at the time of bid and for the duration of the project. The A - General Engineering Prime Contractor may either hold the specialty licenses and self-perform the work, or they can subcontract to the appropriate specialty classes required for the specific trades.

A “C-57 - Well Drilling Contractor” will be required to complete all dewatering well abandonment work.

A “C-10 - Electrical Contractor” will be required to complete the electrical work.

The air balancing may be completed by a “C-61/D-62 - Air and Water Balancing Contractor”, or by a “C-20 - Warm-Air Heating, Ventilating and Air-Conditioning Contractor”.

Contractors and their subcontractors shall have all necessary licenses to perform work. If awarded the contract, Contractor and subcontractors licenses shall be current and active throughout the project. If any license is suspended, revoked, canceled, or expires and/or becomes inactive during the project, the Contractor shall immediately notify the Department.

PLEASE NOTE:

All participants attending the mandatory pre-bid conference and site inspection must enter the grounds of CHCF: 7707 Austin Rd, Stockton, CA 95215 visitor entrance. Participants are required to show valid photo identification (ID) (i.e. Driver License) to attend the walk-through. For security reasons attendees should arrive no earlier than 30 minutes ahead to allow time to sign in at the Administration Building prior to the conference. Attendees should park at the Visitor parking lot. Late arrivals will not be allowed to attend the mandatory pre-bid conference or walk-through.

The mandatory walk-through will be conducted after the mandatory pre-bid conference; there will be no break for lunch. Prospective bidders should plan for a one-hour tour after the mandatory pre-bid conference. Participants will be escorted to and from the project site by custody staff.

IT IS MANDATORY FOR PROSPECTIVE BIDDERS TO ATTEND THE PRE-BID CONFERENCE

AND SITE INSPECTION. BIDS WILL NOT BE CONSIDERED FROM BIDDERS WHO FAIL TO

MEET THESE REQUIREMENTS. SUBCONTRACTORS WHO COULD BE POTENTIALLY

IMPACTED BY EXISTING SITE AND BUILDING CONDITIONS WILL BE ALLOWED TO

PARTICIPATE.

Prospective bidders are encouraged to invite their potential subcontractors and suppliers to the mandatory pre-bid conference and walk-through. All personnel entering onto State Prison property for the mandatory pre-bid conference and walk-through shall not wear blue outer clothing (especially blue denim jeans) which could be mistaken for inmate authorized clothing. Refer to the bid documents, Section 01 35 53 – Security Procedures, for additional security requirements when entering onto State Prison property, including a list of items which cannot be brought onto State Prison property under any circumstances (including but not limited to weapons, knives, and alcohol).

Prospective prime contractor bidders and potential subcontractors attending the mandatory pre-bid conference and site walk must contact the institution staff to confirm attendance. Please submit your participation request to Marco Zeer via e-mail at Marco.Zeer@cdcr.ca.gov, or by phone at

(209) 467-3154 before the pre-bid conference/site walk date indicated on the Projected Timetable.

Please lock all vehicles. Please leave all cell phones locked in your vehicle and do not bring them into the meeting. Personal cameras will be allowed; however, pictures should only be taken under the supervision of CDCR personnel.

Additionally, a PICTURE I.D. (Drivers License) is mandatory to attend the pre-bid conference and to gain access on prison property. For security reasons attendees should arrive approximately ½ hour early (9:30 am) to allow time to sign in at the Administration Building prior to the conference. Late arrivals will only be allowed to attend the pre-bid conference at the discretion of the Project Director.

SPECIAL REQUIREMENTS FOR PARTICIPATING IN THE ON-SITE INSPECTION

All prime contractors shall participate in the on-site inspection (immediately following the pre-bid conference). In addition, subcontractors who could be potentially impacted by existing site and building conditions will be allowed to participate. Subcontractors will be screened to this effect following the pre-bid conference and prior to the on-site inspection.

ATTENTION:

THIS BID PROPOSAL MUST MEET THE DISABLED VETERAN BUSINESS

ENTERPRISE (DVBE) 3% PARTICIPATION GOAL. ONLY THOSE PROPOSALS THAT

INCLUDE THE MINIMUM 3% DVBE PARTICIPATION WILL BE CONSIDERED.

Contact the CDCR Contracts Management Branch DVBE Representative, Julia Diener at

(279) 210-3722 or via e-mail at SBDVBEadvocate@cdcr.ca.gov for DVBE assistance.

A bidder preference will be granted to bidders who are certified as “Small Business” by the close of business on the day of the bid opening date, and in accordance with Section 1896 et seq, Title 2, California Code of Regulations. A form for requesting such preference is included with the Bid Documents. Applications for status as a "Small Business" must be submitted to the Department of General Services, Office of Small Business and DVBE Certification (OSDS), 707 3rd Street, 1st Floor, Room 1-400, West Sacramento, California 95605.

Request for Drawings and Specifications:

Drawings and Specifications for this project can be obtained by contacting American Reprographics Company (ARC) at (916) 443-1322. The bid documents can also be viewed and ordered by selecting the project from the online PlanWell at the ARC Northern California Public Planroom by going to https://www.e-arc.com. "Public Planroom" button, then search the bid number and click on the project number to view online, or order digital or printed copies for a fee. Please note when using Internet Explorer compatibility view must be turned on to see the project list (Tools -> Compatibility View Settings -> add www.e-arc.com). Questions regarding the website can be directed to the PlanWell team at ARC Sacramento by calling (916) 443-1322 or by e-mailing sac.planwell@e-arc.com. Bid documents may be purchased either in hard copy of electronic media format.

Request for Bid Proposals:

After the Mandatory Pre-Bid Conference/Site Walk, a Bid Proposal for this project can be obtained ONLY by qualified Prime Contractors by contacting Helen Wong, CDCR Facility Planning, Construction and Management Branch, via email request to Helen.Wong@cdcr.ca.gov. Bidders must include the project name, contractor name, mailing address or email address, and their phone number.

No bid will be considered unless it is made on the State’s Bid Proposal Form which is non-transferable.

Letters of Inquiry:

The purpose of these letters is to provide bidders with the opportunity to ask questions regarding the bid documents and walk-through and will be answered via addendum. Additionally, any modifications to the Notice to Contractors (NTC), Specifications or Drawings, and responses to inquiries will be documented via addendum and posted on the CaleProcure website at http://www.caleprocure.ca.gov.

Any letters of inquiry must be submitted by email to allow CDCR time to research and prepare a response. Submit your letter of inquiry by the date specified in the Projected Timetable Section of this NTC directly to Helen Wong, Facility Planning, Construction and Management Branch, by e-mail: Helen.Wong@cdcr.ca.gov.

Inquiries received after this date will only be addressed at CDCR’s discretion.

The successful Bidder shall furnish bonds, insurance, and other documents as specified in the Instruction to Bidders.

Pursuant to Section 1773 of the California Labor Code, the general prevailing rate of wages in the county in which the work is to be done, as determined by the Director of the Department of Industrial Relations, must be paid to all workers on Public Works projects such as this one. Usage rates may be obtained through the Department of Industrial Relations website at www.dir.ca.gov.

The CDCR reserves the right to reject any or all bids, to waive any irregularity in any bid, and to award a contract for any part or whole of the project.

Bidder's security in the amount of ten percent (10%) of the bid, and appropriate licensing are required of all bidders.

The State’s Estimate for the project is approximately $3,380,000.00.

INSTRUCTIONS TO BIDDERS

1. ABBREVIATIONS

Whenever the following abbreviations are used the meaning shall be indicated as:

BOE California Board of Equalization BPC Business and Professions Code CCC Contractor Certification Clauses CCR California Code of Regulations CDCR California Department of Corrections and Rehabilitation CMB Contracts Management Branch CSLB Contractors State License Board CUF Commercially Useful Function DGS California Department of General Services DVBE Disabled Veteran Business Enterprise FPCM CDCR Facility Planning, Construction and Management GC California Government Code MVC Military and Veteran Code MB Micro Business Enterprise NSBS Non-Small Business Subcontractor NVSA Nonprofit Veteran Service Agency OBS Office of Business Services OSDS Office of Small Business and DVBE Certification Services PCC California Public Contract Code PD Procurement Division SB Small Business Enterprise SBA U.S. Small Business Administration SCA State Contracting Act UNSPSC United Nations Standard Products and Services Codes

2. COMPETENCE OF BIDDERS

Bidder may bid only on work for which they are properly licensed by the CSLB. Joint venture bidders must possess a joint venture license. The bidder must be licensed at the time of bid, and the license must remain current for the duration of the project.

3. AVAILABILITY OF BIDDING DOCUMENTS

Bid proposal forms will be provided by CDCR to only those bidders that meet the eligibility requirements for this project.

Drawings and specifications are available as specified in the Notice to Contractors.

Drawings and specifications are NOT to be returned to the CDCR upon bid completion. However, as these drawings and specifications are the PROPERTY OF THE STATE, they cannot legally be used in construction other than this project.

4. EXAMINATION OF BID DOCUMENTS AND WORKSITE

Bidder should carefully examine the bid documents and any addenda thereto, work site, and all related data and materials referenced in the bid documents or otherwise available and be fully informed of the nature and location of the work, the quantities of the work and the conditions to be encountered in performing the work.

Conditions to be examined shall include, but not be limited to, the character, quality and quantity of surface and sub-surface materials and obstacles; the availability of labor, water, electricity and road; the location of utilities; the uncertainties of weather, river stages and similar natural phenomena; and conditions bearing upon the transportation, handling, storage and disposal of materials.

5. SUBSTITUTIONS OF PRODUCTS/EQUIPMENT

Proposed substitutions of products and equipment designated in this contract must be submitted in the following manner and timeframe. Substitutions shall be in accordance with Specifications Section 00 72 06 of Division 01, General Conditions and Specifications Section 01 25 00, Substitution Procedures. Only substitution requests conforming to these specifications and received within the timeframe specified therein will be considered. Late or incomplete substitution requests will not be considered for approval.

6. DISCREPANCIES OF ERROR AND ADDENDA

If omissions, discrepancies or an apparent error are found in the drawings and specifications prior to the date of bid opening, the bidder shall request clarification from the CDCR. Clarification will be given only in the form of addenda to all bidders if time permits. Otherwise, in figuring the work, bidders shall consider that discrepancies or conflict between drawings and specifications shall be governed by Specifications Section 00 72 02, Section 2.4, Governing Order.

7. BID DOCUMENTS

A. Bid Proposal - The CDCR will furnish to each eligible bidder a standard bid proposal which, when filled out and executed, shall be submitted as a bid.

1. Bid proposal not presented on said proposal forms shall be disregarded.

2. Bid proposal is nontransferable to another bidder.

3. Proposal shall be submitted in same name style and manner as is used on bidder's license.

4. Proposal shall give the prices proposed in the manner required and shall be signed by bidder through a duly authorized representative.

5. If the proposal is made by an individual, the name and address shall be shown; if made by a firm or partnership, the name and address of the firm or partnership and the signature of one or more partners shall be shown; if made by a corporation, the name of the corporation, the state of incorporation, the title of the person who signs on behalf of the corporation and address of the corporation shall be shown. Corporation seal shall be used.

6. Bidder shall acknowledge the receipt of drawings, specifications and all addenda on the bid proposal.

Failure by the bidder to acknowledge any bid document could result in rejection of the bid.

B. Payee Data Record - Contractors shall comply with State and Federal Reportable Payment Identification and Classification Requirements by fully completing a Payee Data Record (STD 204) form.

C. Required Listing of Proposed Subcontractors - All bidders shall comply with the Subletting and

Subcontracting Fair Practices Act, PCC Section §4100 et seq. Pursuant to Section §4104, each bidder shall, in his or her bid or offer, set forth:

(a) the name and the location of the place of business of each subcontractor who will perform work or labor or render service to the prime contractor in or about the construction of the work or improvement, or a subcontractor licensed by the State of California who, under subcontract to the prime contractor, specially fabricates and installs a portion of the work or improvement according to detailed drawings contained in the drawings and specifications, in an amount in excess of one-half of one percent of the prime contractor's total bid or, in the case of bids or offers for the construction of streets or highways, including bridges, in excess of one-half of one percent of the prime contractor's total bid or ten thousand dollars ($10,000), whichever is greater; and

(b) the portion of the work which will be done by each subcontractor under this act.

PURSUANT TO PUBLIC CONTRACT CODE SECTION 10108.7, PRIME CONTRACTORS SHALL

INCLUDE WITH THEIR BID PROPOSAL, REGARDLESS OF THE DOLLAR AMOUNT, ALL CERTIFIED

DVBE SUBCONTRACTORS WHO WILL PERFORM WORK OR LABOR OR RENDER SERVICE TO

THE PRIME CONTRACTOR IN CONNECTION WITH THE PERFORMANCE OF THE CONTRACT AND

WHO WILL BE USED BY THE PRIME CONTRACTOR TO FULFILL DVBE PARTICIPATION GOALS.

The prime contractor shall list only one subcontractor for each portion as is defined by the prime contractor in his or her bid. This section does not apply to 2nd or 3rd-tier subcontractors.

In accordance with PCC Section §4108, if a prime contractor requires a bond or bonds of his/her subcontractors, whether the expense of the bond or bonds be borne by the prime or the subcontractor, these requirements shall be specified in the prime contractor's written or published request for sub-bids.

Failure to adhere to these requirements shall preclude the prime contractor from imposing bond requirements under this section.

D. Bidder's Security - Proposals shall have enclosed a bidder's bond, a cashier’s check or a certified check made payable to the "Agency Secretary of the California Department of Corrections and Rehabilitation" in an amount equal to 10 percent (10%) of the bid. If a bidder's bond is utilized, it must be executed as surety by a corporation authorized to issue surety bonds in the State of California and it must be submitted on the form attached to the bid proposal.

Bidder's security shall be returned in accordance with PCC Section §10184.

E. Non-Collusion Affidavit - Bidder shall complete a Non-Collusion Affidavit as required in accordance with

PCC Section §7106. The Non-Collusion Affidavit must be on the form included with this bid proposal and notarized.

F. Business License - Copy of valid California city or county business license, if applicable, or if a corporation is located within the State of California, incorporation documents or a letter from the Secretary of State or, if not a California business, an affidavit that the business is in good standing with the state, province, or country in which the business is headquartered.

G. Small Business Preference - CDCR is committed to supporting SB and MB participation in state contracting and seeks to use California certified SB and MB businesses whenever possible. See Item 8, Small Business Certification for detailed SB information.

H. Disabled Veteran Business Enterprise - CDCR is committed to supporting DVBE participation in state contracting. All contractors shall comply with the mandatory DVBE requirements, which is no less than 3 percent (3%) of the total bid amount. Failure to do so will result in rejection of bid. See Item 9, Disabled Veteran Business Enterprise for detailed information.

8. DISABLED VETERAN BUSINESS ENTERPRISE PROGRAM

NOTE: Bidders need to begin the required DVBE participation process as soon as possible to allow adequate response time for DVBE participants.

a. DVBE participation of no less than three percent (3%) is mandatory for all bids exceeding $15,000.

These requirements apply whether conducting business as a for-profit or nonprofit individual, partnership or corporation. To be deemed responsive and eligible for award of the Agreement, the bidder shall attain the prescribed goals.

For more information, bidders have been provided with a DVBE Program Requirements resource packet. Additionally, to document DVBE participation, bidders shall complete and return the Bidder Declaration form (GSPD-05-105) and the DVBE Declarations form (STD 843) attached to this IFB.

Failure to complete and submit all required forms with the bid, that fully document and meet the DVBE requirement, will cause the bid to be rejected.

b. The DVBE participation requirements must be based on the total amount of the bid proposal.

c. Failure to submit the completed worksheets with the bid proposal will result in automatic rejection of your bid. Your bid will also be rejected if the DVBE requirement is not met.

d. Proof of DGS DVBE certification for your firm and/or subcontractors must be submitted with your DVBE Participation Worksheets.

9. DISABLED VETERAN BUSINESS ENTERPRISE INCENTIVE

CDCR is committed to meet and exceed the three percent (3%) requirement for DVBE participation in State contracting activities, set forth in MVC 999. The DVBE Incentive Program applies to all contracting activities for services including public works, construction, services, leasing, materials testing, and other related contracts. The DVBE incentive is applied during the evaluation process and is only applied to responsive bids from responsible bidders proposing DVBE participation. This incentive is for bid computation only.

To be eligible for the DVBE incentive, the business shall:

1. Complete DVBE Incentive Request and Subcontractor Acknowledgement form (OBS 554) and submit with bid proposal.

2. Have a completed DVBE application on file with DGS, OSDS by 5:00 p.m. on the date bids are due.

For certification and preference approval process information, contact the OSDS by telephone at (916) 375-4940 or access the OSDS Internet website at Apply For or Re-apply as Small Business, Disabled Veteran Business Enterprise.

Award Based on Low Price The incentive shall be equal to a bidder’s DVBE participation level (rounded to the nearest two decimal places).

DVBE PARTICIPATION LEVEL INCENTIVE APPLIED

1.0 - 1.99% 1%

2.0 UP TO 2.99% 2%

3.0 UP TO 3.99% 3%

4.0 UP TO 4.99% 4%

5.0 UP TO 5.99% 5%

1) The incentive is subject to a minimum of one percent (1%) and a maximum of five percent (5%) and will not exceed $500,000. Bids with DVBE participation of more than five percent (5%) will be calculated with a five percent (5%) incentive.

2) Bidders with DVBE participation of less than the required percentage listed in the solicitation will be deemed non-responsive and eliminated from any further participation.

3) The Small Business Preference (five percent (5%) up to $50,000) may be combined with the DVBE incentive but will not exceed a combined total of $500,000.

4) The DVBE incentive is computed from the lowest responsive and responsible bid price.

A. Counting DVBE Participation

DVBEs must be certified by DGS OSDS prior to bid opening.

Sub-bids from DVBEs must be accepted by the prime bidder prior to bid opening.

Prime Contractors that are also DVBE certified will have their participation count in proportion to the work they perform on the project. The DVBE prime contractor shall fulfill all Program requirements.

A prime bidder may count toward the participation goal the total dollar value of contracts from its subcontractors, suppliers and/or truckers, provided that the DVBEs assume the actual and contractual responsibility for the total dollar value of the work and/or supplies to be provided.

DVBEs used toward the participation goal must perform a commercially useful function. In order to perform a CUF, a firm shall be:

(1) responsible for execution of a distinct element of the work on the contract;

(2) carry out its obligation by actually performing, managing, or supervising the work involved; and

(3) perform work that is normal for its business services and functions. DVBEs who subcontract a greater portion of the work that would be considered normal industry practice, will be presumed not to be performing a CUF.

B. Monitoring DVBE Participation

Throughout the life of the contract, the prime contractor shall submit quarterly reports on increases and/or decreases in DVBE participation including work on change orders.

Upon completion of the contract, the prime contractor shall submit a final report identifying all DVBEs used. The report must be submitted within thirty (30) days of contract closeout to Construction Management.

Failure to provide reports may result in CDCR withholding final payment from the prime contractor.

All reports must be submitted to Construction Management.

C. Contractor DVBE Certification Requirement

The Contractor shall within 60 days of receiving final payment of the awarded agreement (or within such other time period as may be specified elsewhere in this agreement) certify in a report to the awarding department:

1. the total amount the prime contractor received under the contract;

2. the name and address of the DVBE(s) that participated in the performance of the contract;

(1) the amount each DVBE received from the prime contractor;

(2) that all payments under the contract have been made to the DVBE(s); and

(3) the actual percentage of DVBE participation that was achieved.

A person or entity that knowingly provides false information shall be subject to a civil penalty for each violation in the minimum amount of $2,500 and the maximum amount of $25,000 (M&VC § 999.5(d)).

D. Contractor DVBE Replacement Request

Contractor understands and agrees that award of this contract is based in part on their commitment to use the DVBE subcontractor(s) identified in their bid or offer, according to M&VC §999.5(e). A DVBE subcontractor may only be replaced by another DVBE subcontractor and must be approved by the CDCR prior to replacement. Changes to the scope of work that impact the DVBE subcontractor(s) identified in the bid or offer and approved DVBE substitutions will be documented by contract amendment. Requests to replace a DVBE subcontractor must be amply documented to show that the replacement meets the criteria as specified in the Title 2 CCR, Section §1896.64(c) or the PCC §4107 (for public works). Failure of Contractor to seek substitution and adhere to the DVBE participation level identified in the bid or offer may be cause for contract termination, recovery of damages under rights and remedies due to the State, and penalties as outlined in M&VC § 999.9; PCC § 10115.10, or PCC § 4110 (for public works contracts).

If a prime contractor substitutes a DVBE, written notice must be made to CDCR FPCM. The notice should be emailed to m_FPCM-Contract-Mail@cdcr.ca.gov and must include the name of the DVBE firm to be substituted and the type of work they were to perform.

In addition to the notification above, the prime contractors shall obtain CDCR approval for substitution pursuant to PCC §10108.7 and as specified in PCC §4107 (Subletting and Subcontracting Fair Practices Act). Direct request to:

MAIL DELIVERY CDCR

HAND DELIVERY or Facility Planning, Construction and Management OVERNIGHT MAIL: 9838 Old Placerville Road, Suite B Sacramento, CA 95827

10. SMALL BUSINESS PREFERENCE PROGRAM

Current law requires state departments to support the success of small businesses, including microbusinesses, in participation in contracting opportunities. CDCR is committed to supporting SB/MB participation in state contracting and seeks to contract with certified SB/MB whenever possible.

A SB enterprise is defined as a business certified by the DGS OSDS in which:

1. The principal office is located in California;

2. The officers are domiciled in California;

3. The business is independently owned and operated;

4. The business, with any affiliates, is not dominant in its field of operation; and

a. For SB, either:

(1) The business, together with any affiliates, has one hundred (100) or fewer employees and averaged annual gross receipts of $16,000,000 or less over the previous three years, or

(2) The business is a manufacturer with one hundred (100) or fewer employees;

b. For MB, either:

(1) The business, together with any affiliates, has twenty-five (25) or fewer employees and averaged annual gross receipts of $5,000,000 or less over the previous three years, or

(2) The business is a manufacturer with twenty-five (25) or fewer employees.

Section 14835, et seq., of the California GC requires that a five percent (5%) preference be given to bidders who certify as a SB/MB enterprise. The rules and regulations of this law are contained in Title 2, CCR, Section 1896, et seq. A copy of the regulation is available upon request.

To claim the SB/MB preference, which may not exceed $50,000 for any bid, your firm must:

1. Have a completed application (including proof of annual receipts) on file with the DGS OSDS, by

5:00 p.m. on the date bids are due, and

2. Receipt of documents verified by such office.

Therefore, if you are a SB/MB, but are not certified, it is to your advantage to become certified. For certification and preference approval process information, contact the OSDS by telephone at (916) 375-4940 or access the OSDS Internet website at Apply For or Re-apply as Small Business, Disabled Veteran Business Enterprise.

11. NON-SMALL BUSINESS PREFERENCE REQUEST

Pursuant to Title 2, CCR Section 1896, et seq., and GC Section 14838, et seq., a bid preference of five percent (5%) is available to a responsive non-small business claiming no less than twenty-five percent (25%), SB/MB subcontractor participation with one or more SB/MB enterprises. This preference is considered only if the tentative low bidder is not a certified SB/MB.

In granting the Non-SB Preference, no bid price will be reduced by more than $50,000. This preference cost adjustment is for bid evaluation purposes only and does not alter the actual cost offered by the bidder.

A non-SB is defined as a responsive/responsible bidder that is not certified by the DGS OSDS as a SB/MB enterprise.

To be eligible for the non-SB preference, the business prime vendor must complete and submit the Non-SB Preference Request and Subcontractor Acknowledgement form (OBS 555) with their bid proposal.

12. NONPROFIT VETERAN SERVICE AGENCY SMALL BUSINESS PREFERENCE

Pursuant to M&VC Section 999.50 et seq., NVSAs claiming SB/MB preference and verified as such in the relevant category or business type, will be granted a preference of five percent (5%) of the lowest responsive bid, if the lowest responsive bid is submitted by a bidder not certified as a SB/MB.

In granting SB/MB preference to NVSAs, no bid will be reduced by more than $50,000. The preference cost adjustment is for computation purposes only and does not alter the actual cost offered by the bidder.

To be eligible for the NVSA SB/MB Preference, the business concern must:

1. request preference at the time of bid submission, and

2. must possess a valid certification prior to bid submission.

An SB/NVSA is not subject to the same standards as other certified SB/MB. SB/NVSA standards are identified in MVC Section 999.51(a) (3).

13. IDENTIFICATION OF CONTRACTORS, SUBCONTRACTORS, CONSULTANTS: SB/MB AND DVBES

CDCR must identify all contractors, subcontractors, and consultants who will provide labor or render services in the performance of this Agreement and further identify whether any of the listed subcontractors and consultants are a certified SB/MB, or a certified DVBE. Therefore, the bidder must complete a Bidder Declaration (GSPD-05-105). If any changes occur in the submitted original GSPD-05-105, the Contractor shall notify FPCM in writing within ten (10) working days of those changes, including any changes to SB/MB or DVBE status.

CDCR asks that you encourage any subcontractor(s) and/or consultant(s) not currently certified as a SB/MB or DVBE that may meet the certification requirements specified herein to become certified through the DGS, OSDS. Please provide those subcontractor(s)/consultant(s) with the OSDS contact and certification information provided above.

If you are a certified SB/MB enterprise and fail to complete the Prime Contractor information of the CDCR Bidder Acknowledgement/Certification form (OBS 300), your business shall be classified as a large business, which will preclude your bid from receiving the five percent (5%) SB/MB preference and can cause incorrect reporting of SB/MB and large business participation by CDCR.

If you are a certified DVBE and fail to specify that information on the CDCR Bidder Acknowledgement/Certification form, (OBS 300) your business shall be classified as a large business, which will preclude your bid from receiving any range of the DVBE incentive and cause incorrect reporting of DVBE participation by CDCR.

14. SUBMISSION OF BID PROPOSALS

It is the sole responsibility of the bidder to ensure that their bid proposal is received by the time and manner prescribed in the Notice to Contractors. Any bid proposal received after the scheduled closing time for receipt of bid will be returned to the bidder unopened.

The bid proposal shall be submitted under sealed cover and plainly identified as a proposal for the work being bid upon. Failure to comply with this procedure may result in a premature opening of, or failure to open, such proposal.

Bidders planning to attend the public bid opening must notify the CDCR contract analyst listed three (3) working days prior to the bid opening date specified. If you or your representative requires reasonable accommodation to participate, you shall contact the contract analyst and identify what reasonable accommodation(s) is required for you to participate.

15. WITHDRAWAL OF BID PROPOSALS

The bid proposal may be withdrawn at any time prior to the time fixed for opening of bids provided that a request in writing, executed by bidder through a duly authorized representative for withdrawal of such bid, is filed with the Agency Secretary of the CDCR through FPCM. Verbal, telegraphic or telephonic requests to withdraw a bid proposal are not acceptable. Withdrawal of a proposal should not prejudice the right of a bidder to file a new proposal. This does not authorize withdrawal of any proposal after the time fixed in the public notice for opening of bids.

16. PUBLIC OPENING OF BID PROPOSALS

At the time of the public bid proposal opening, the dollar amount of each bid proposal will be read aloud at the time and place indicated in the Notice to Contractors. Bidders or their authorized agents/representatives are invited to be present.

All bid proposals are subject to a complete review of the entire proposal for compliance and adherence to the bid requirements, verification of all calculations and claimed preferences, and compliance with mandatory DVBE participation requirements prior to release of intended awardee.

17. IDENTICAL BIDS

In the event two contractors submit identical bids, a coin toss will be held to determine the apparent low bidder. The CDCR reserves the right to require a rebid.

18. REJECTION OF IRREGULAR PROPOSALS

Proposals may be rejected if they show any alterations of form, additions not called for, conditional bids, incomplete bids, erasures or irregularities of any kind. If bid amount is changed after the amount is originally inserted, the change shall be initialed by the bidder through a duly authorized representative.

When proposals are signed by an agent, other than the officer or officers of a corporation authorized to sign contracts in its behalf, or are signed by any agent other than a partner of a partnership, or by an agent for an individual, a power of attorney shall be on file with the CDCR prior to opening bids or shall be submitted with the proposal.

19. COMPETITIVE BIDDING

If more than one proposal is submitted by any individual, firm, partnership, corporation, association or any combination thereof, under the same or different names, all such proposals may be rejected. This is not intended to disqualify a party who has quoted prices on materials or work to one bidder from quoting prices to other bidders, or from submitting a bid directly to the CDCR for materials or work.

Any collusive agreement fixing the prices to bid to control or affect awarding of this contract is in violation of competitive bidding requirements of the SCA and may render void any contract let under such circumstances.

20. AWARD OF CONTRACT

Bidders will be notified via email of the bid results after all preferences are applied and calculations are complete to determine the lowest responsive and responsible bidder. The bid results may be obtained by submitting a Public Records request per the California Public Records Act GC Section 6250 et seq.).

CDCR reserves the right to reject all bid proposals. Award of the contract, if it is awarded, will be to the lowest responsive and responsible bidder whose bid proposal complies with all bidding requirements. Such award, if made, will be made within 60 days after opening of the bid proposals. If lowest responsive and responsible bidder refuses or fails to execute the contract, its bidder's security will be forfeited, and the Agency Secretary of the CDCR may award the contract to the second lowest responsive and responsible bidder. Such award, if made, will be made within 75 days after opening of the proposals. If second lowest responsive and responsible bidder refuses or fails to execute the contract, the CDCR may award the contract to the third lowest responsive and responsible bidder. Such award, if made, will be made within 90 days after opening of the proposals. The above time periods within which award of contract may be made are subject to extension of such further periods as may be agreed upon in writing between the CDCR and the bidder.

21. NONDISCRIMINATION PROGRAM

Contractors shall comply with all requirements of Regulations Applicable to Construction Contracts as outlined in the CCR, Title 2, Chapter 5 Sections §8101 through §8504.

22. EXECUTION OF CONTRACT

Contract shall be signed by successful bidder and returned within seven (7) days of notice of contract award, together with contract bonds and Certificate of Insurance. Successful bidder shall also return a signed set of drawings and specifications for filing with the contract. Contract shall not be binding upon the State until it has been executed by the State and approved by the Attorney General.

a. Contract Bonds - The successful bidder shall furnish in duplicate counterparts the two surety bonds required by the SCA, each in the amount as required by said Act. Pursuant to that Act, a Performance Bond is required guaranteeing faithful performance of the work in the amount of 100 percent (100%) of the contract amount and a Payment Bond is required securing payment of laborers, mechanics or suppliers employed on the work under contract in the amount of 100 percent (100%) of the contract amount. These bonds must be executed by an admitted surety insurer that is licensed to transact surety business in the State of California, appears in the California Department of Insurance’s listing as a surety bond provider and carries a minimum Best’s Key Rating of A-VI.

b. Certificate of Insurance - The successful bidder shall furnish to the CDCR within seven (7) days of notice of contract award, a Certificate of Insurance covering Contractor Maintained Insurance as more particularly described in Section 00 72 01 of the General Conditions of the Contract. The certificate must be executed by an admitted surety insurer that is licensed to transact insurance business in the State of California, appears in the California Department of Insurance’s listing as an insurance provider and carries a minimum Best’s Key Rating of A-VI.

23. FAILURE TO EXECUTE CONTRACT

Failure of successful bidder to execute the contract, including providing acceptable bonds and insurance as provided herein within the time specified above shall be deemed a failure or refusal to execute the contract and shall be cause for forfeiture of bidder's security.

24. SALES TAX JOBSITE SUB-PERMITS

Effective January 1, 1995, contractors may elect to allocate the local sales and use tax derived from construction contracts of $5,000,000 or more directly to the local jurisdiction where the jobsite is located.

The process for accomplishing this is explained in the Notice from the State BOE included in the specifications. Questions regarding this program should be directed to the local BOE office.

25. CONTRACT AUDIT

In accepting the contract award, the prime contractor agrees that CDCR, or its delegate, will have the right to review, obtain, and copy all records pertaining to performance of the contract. The Contractor agrees to provide CDCR, or its delegate, any relevant information requested. The Contractor shall permit CDCR, or its delegate, access to its premises, upon reasonable notice, during normal business hours for the purpose of interviewing employees, and inspecting and copying such books, records, accounts, and other material that may be relevant to a matter under investigation for the purpose of determining compliance with

PCC Section 10115. The Contractor further agrees to maintain such records for a period of three (3) years after final payment under the contract.

26. LOSS LEADER

It is unlawful for any person engaged in business within this state to sell or use any article or product as a “loss leader” as defined in BPC Section §17030. A “loss leader” is any article or product sold at less than cost: (a) where the purpose is to induce, promote or encourage the purchase of other merchandise; or (b) where the effect is a tendency or capacity to mislead or deceive purchasers or prospective purchasers; or

(c) where the effect is to divert trade from or otherwise injure competitors.

END OF DOCUMENT