These are architectural and engineering design drawings for the "Improve Security York Campus" project at the Alvin C. York VA Medical Center in Murfreesboro, Tennessee. The bid documents detail a comprehensive security enhancement project for the medical facility, focusing on the pharmacy area and involving demolition and new construction. Key elements include installing ballistic-level security walls with 9-gauge diamond security mesh, new card access systems with dual authentication, a stainless steel pass-through chamber, window film, and modifications to existing walls and infrastructure. The project is divided into two phases to maintain operational continuity, with specific requirements for infection control, electrical system modifications, and careful coordination with VA staff. The design drawings cover civil, architectural, and electrical plans, with detailed specifications for wall construction, door schedules, and electrical access control systems.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Murfreesboro Asbestos Survey Report.pdf | ||
| 36C24925B0007 0001.docx | DOCX document | |
| Contractor EMR Certification Form.pdf | ||
| IMPORTANT SUBMISSION INFORMATION.pdf | ||
| Fire Protection Requirements.docx | DOCX document | |
| WD Rutherford County Building TN20250187 06062025.docx | DOCX document | |
| Site visit sign in sheet 07102025.pdf | ||
| P07_Wage Determination.docx | DOCX document | |
| C28_ York Specs Bid.pdf | ||
| 36C24925B0007_1.docx | DOCX document | |
| RFI Form.docx | DOCX document | |
| CALCULATION OF SELF PERFORMED WORK.docx | DOCX document | |
| UEI _ TAX ID.docx | DOCX document |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VETERANS CIRCLE
S O
U
TH
V
IE
W D
R
IV
E
VETERANS CIRCLE
S A
M
JA
R E
D R
O A
D
VETERANS CIRCLE
VETERANS CIRCLE
EAST MAIN STREET
E A
S T
V
IE
W D
R
IV
E
N O
R
TH
V
IE
W D
R
IV
E
JOHN F COADY DRIVE
JOHN F COADY DRIVE
LAKE ROAD
'-2
'-3
'-3
'-5
ES
CR
ES
CR
ES
CR
ES C
R
Engineers Architects
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
PROJECT SITE MAP PROJECT LOCATION MAP
PROJECT IMAGE
/4
/2
:0
:1
P M
C U s e rs
\c k u rk u l\ D o c u m e n ts
\A
-1
Y
-Q
-V
A Y o rk
S e c I m p ro v -T
N c k u rk u lG
V Y
H
.r v t
G-001
COVER
1 4NPM
IMPROVE SECURITY YORK
CAMPUS
ALVIN C. YORK VA MEDICAL CENTER
3400 LEBANON RD.
MURFREESBORO, TN 37129 MARCH 8, 2024
BID DOCUMENTS
626A4-20-10322-199Y
IMPROVE SECURITY YORK CAMPUS
ALVIN C. YORK VA MEDICAL CENTER
3400 LEBANON RD.
MURFREESBORO, TN 37129
VA PROJECT #: 626A4-20-103
WVS
DRAWING LIST
GENERAL
G-001 COVER 1 4
G-002 SITE PLAN 2 4
G-003 ICRA INFORMATION AND DETAILS 3 4
G-004 GROUND FLOOR LOGISTICS PLAN 4 4
CIVIL
CS100 CIVIL SITE PLAN 1 1
ARCHITECTURAL
A-001 ARCHITECTURAL GENERAL NOTES 1 4
AD-100 GROUND FLOOR DEMOLITION AND ICRA PLAN 2 4
A-100 GROUND FLOOR PLAN 3 4
A-601 DOOR SCHEDULE AND DETAILS 4 4
ELECTRICAL
E-001 ELECTRICAL GENERAL NOTES, SYMBOL LEGENDS, AND ABBREVIATIONS 1 4
ED101 FIRST FLOOR ELECTRICAL DEMOLITION PLAN 2 4
E-101 FIRST FLOOR ELECTRICAL PLAN 3 4
E-501 ELECTRICAL DETAILS 4 4
PHARMACY SITE - BLDG 3 PROJECT LOCATION
DocuSign Envelope ID: CCA35CFA-10D5-46CA-B65B-41D1EAF752D3
3/5/2024
A-100
A-401CS100
V E
T E
R A
N S
B L V
D
VE
TE
R A N S C
IR
C
LE
VETERANS CIRCLE
LA
K E R
D
NORTHVIEW DRIVE
LAKE RD
H
IL
L S T
P A
R K
R D
B O
IL
E
R P
L A
N T
R D
V E
T E
R A
N S
C
IR
C L E
EASTVIEW DR
LEBANON PIKE - HIGHWAY 231 - MEMORIAL BLVD.
12 13
BUILDING NOT IN SCOPE
PROJECT LOCATION
SITE PLAN LEGEND
Engineers Architects
# KEY NOTES:
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
SHEET NOTES:
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/4
/2
:0
:1
P M
C U s e rs
\c k u rk u l\ D o c u m e n ts
\A
-1
Y
-Q
-V
A Y o rk
S e c I m p ro v -T
N c k u rk u lG
V Y
H
.r v t
G-002
SITE PLAN
2 4NPM
IMPROVE SECURITY YORK
CAMPUS
ALVIN C. YORK VA MEDICAL CENTER
3400 LEBANON RD.
MURFREESBORO, TN 37129 MARCH 8, 2024
BID DOCUMENTS
626A4-20-10322-199Y
WVS
Scale: 1" = 80'-0"
SITE PLAN
N O
R T
H
0 4 8 16
A. GENERAL CONTRACTOR TO COORDINATE WITH
VA COR ON LOCATION AND NUMBER OF SPACES
AVAILABLE TO CONSTRUCTION CREW.
1 STAGING AREA. CONTRACTOR TO PROVIDE A
TEMPORARY GALVANIZED 6' HIGH CHAIN LINK
CONSTRUCTION FENCE, WEIGHTED PANEL TYPE
WITH PRIVACY SCREEN AND ONE 8' DOUBLE GATE.
ANY GROUND DAMAGED AT THE STAGING AREA
TO BE REPAIRED TO ITS ORIGINAL CONDITION.
2 CONSTRUCTION MATERIALS ENTRANCE
COORDINATE TIMES WITH COR.
INFECTION CONTROL RISK MITIGATION RECOMMENDATIONS MATRIX OF PRECAUTIONS
FOR CONSTRUCTION AND RENOVATION
PLASTIC WINDOW
SWIVEL CASTERS
WITH TWO
LOCKING BRAKES
MOBILE CART
A D
J U
S T
A B
L E
H E
IG
H
T
HEPA NEGATIVE
AIR UNIT
EXISTING WALL
EXISTING CEILING
FLEX DUCT
3 5/8" METAL STUDS @ 16" O.C.
5/8" TYPE 'X' GYPSUM BOARD -
BOTH SIDES
EXISTING CEILING SYSTEM
BASE - TO MATCH
EXISTING AREA
EXISTING FLOOR
UNDERSIDE OF EXISTING
DECK
A P
P R
O X
V
IF
4 7/8"
A
FIRE RESISTANT SEALANT,
BOTH SIDES
1-HR RATED AND UL U419
A P
P R
O X
V
IF
ISLM TEMPORARY BARRIER TAG
PROJECT:
PRIME CONTRACTOR:
SUB CONTRACTOR:
EMERGENCY CONTACT NO.:
BARRIER INSTALLATION DATE:
BARRIER EXPIRATION DATE:
ILSM SIGNAGE
INTERIM LIFE SAFETY MEASURES IN EFFECT
FOR IMPROVE SECURITY MURFREESBORO CAMPUS
THIS EXIT IS CLOSED AND LEADS TO A
CONSTRUCTION AREA.
PLEASE USE ALL ALTERNATE EXITS AS MARKED.
1' - 5"
1/2"1/2"
/2
/2
/2
/2
/2
/2
EQ.EQ.
DUST CONTROL PLAN NOTES
1. THE VAMC INFECTION CONTROL GROUP HAS CONFIRMED THE
DESIGNATION FOR THIS PROJECT IS LEVEL III/IV FOR THE CLASS OF
PRECAUTIONS OR LEVEL OF INFECTION CONTROL ACTIVITIES. HARD
SURFACE BARRIERS SHALL BE USED EXCEPT IN THE AREA INDICATED
ON THE PHASING PLAN WITH PLASTIC BARRIERS (MINIMUM 4MIL) TO
SEAL AREA FROM NON-WORK AREA AS LONG AS THE SPRINKLER
SYSTEM IS INTACT AND ACTIVE.
1A. THIS PROJECT NEEDS AN ENTRY VESTIBULE FOR CLOTHING CHANGES
(PROVIDE AND LOCATE A STAGING AREA FOR HAZMAT SUITS NEAR THE
PLASTIC BARRIER ENTRANCE SPACES - CONSTRUCTION ANTEROOM.
THEY SHALL BE USED WHEN GOING INTO CONSTRUCTION AREA AND
LEAVING THE CONSTRUCTION AREA) AND TOOL STORAGE AND TIGHT
SEALS SHALL BE MAINTAINED AT THE FULL PERIMETER OF WALLS AND
WALL PENETRATIONS. ANY DUST SHALL BE IMMEDIATELY CLEANED IF
TRACKED OUTSIDE OF THE CONSTRUCTION BARRIER. UPON
COMPLETION OF THE CONSTRUCTION PHASE, DUST BARRIERS SHALL
BE REMOVED CAREFULLY TO MINIMIZE SPREADING OF DUST AND THE
CONTRACTOR SHALL HAVE TEMPORARY DUST PROTECTION IN PLACE
BEFORE REMOVAL OF A PERMANENT BARRIER.
AFTER EACH PHASE, PERFORM TASKS STATED IN NOTE 6A.
2. PROVIDE STICKY MATS AND BLANKET AT THE PLASTIC BARRIER
ENTRANCE SPACES (CONSTRUCTION ANTEROOM) AND CHANGE DAILY
OR MORE OFTEN AS NEEDED TO PREVENT THE SPREAD OF DUST AND
DEBRIS INTO ADJACENT CLEAN SPACE.
INTERNAL DEMOLITION AND CONSTRUCTION ACTIVITIES DUST AND DEBRIS
CONTROL
3. USE CORRIDORS AS PRIMARY CONSTRUCTION ACCESS.
3A. TRAFFIC CONTROL: DESIGNATED ENTRY AND EXIT PROCEDURES
SHALL BE DEFINED. EGRESS PATHS SHALL BE FREE OF DEBRIS;
DESIGNATED ELEVATORS SHALL BE USED DURING SCHEDULED
TIMES; AND ONLY AUTHORIZED PERSONNEL SHALL BE ALLOWED TO
ENTER THE CONSTRUCTION ZONE. SIGNAGE SHALL DIRECT
PEDESTRIAN TRAFFIC AWAY FROM THE CONSTRUCTION AREA AND
MATERIALS.
4. CONTRACTOR SHALL USE TWO CARTS TO TRANSFER CONSTRUCTION
MATERIAL IN AND OUT OF THE PROJECT - A CLEAN CART SHALL BE
USED; THE NOT-SO-CLEAN CART SHALL BE USED BETWEEN THE MAIN
ENTRY AND THE CONSTRUCTION STAGING/PREP AREA.
4A. DEMOLITION DEBRIS: DEBRIS SHALL BE REMOVED IN CARTS WITH
TIGHTLY FITTED COVERS, USING DESIGNATED TRAFFIC ROUTES.
EFFORTS SHALL BE MADE TO MINIMIZE USE OF ELEVATORS WITH AN
EMPHASIS ON TRANSPORT DURING THE LOWEST PERIOD OF ACTIVITY.
DEBRIS SHALL BE REMOVED DAILY AND AT TIMES SPECIFIED BY THE
VAMC. IF CHUTES ARE USED TO DIRECT DEBRIS OUTSIDE, HIGH
EFFICIENCY PARTICULATE AIR (HEPA) FILTERED NEGATIVE AIR
MACHINES SHALL BE USED, AND THE CHUTE OPENING SHALL BE
SEALED WHEN NOT IN USE. FILTERS SHALL BE BAGGED AND SEALED
BEFORE BEING TRANSPORTED OUT OF THE CONSTRUCTION AREA.
THE CONTRACTOR SHALL NOT HAUL DEBRIS THROUGH PATIENT-CARE
AREAS WITHOUT PRIOR APPROVAL OF THE COR.
4B. EXTERIOR WINDOWS: WINDOWS SHALL BE SEALED TO MINIMIZE
INFILTRATION FROM ANY ADJACENT EXCAVATION DEBRIS.
4C. ALL EQUIPMENT REMAIN IN THE ORs AND ASSOCIATED ROOMS SHALL
BE COVERED AND PROTECTED PRIOR STARTING EACH CONSTRUCTION
PHASE.
VENTILATION AND ENVIRONMENTAL CONTROLS
5. AIR SYSTEM FLOW: THE COR VERIFY AND ACKNOWLEDGE
CONTRACTOR WHETHER THE CONSTRUCTION AREA USES
FRESH/OUTSIDE OR RE-CIRCULATED AIR; FILTERS SHALL BE ADDED OR
RETURN VENTS COVERED AS NEEDED WITH FILTER MATERIAL OR
PLASTIC. AIR MUST FLOW FROM CLEAN TO DIRTY AREAS.
5A. NEGATIVE AIR PRESSURE: THE AIR WITHIN THE CONSTRUCTION AREA
SHALL BE NEGATIVE WITH RESPECT TO SURROUNDING AREAS AND
WITH NO DISRUPTION OF AIR SYSTEMS OF ADJACENT AREAS. USE OF
THE NEGATIVE AIR PRESSURE SYSTEM WITHIN THE ENCLOSURE TO
REMOVE DUST SHALL PASS AIR THROUGH AN INDUSTRIAL GRADE,
PORTABLE HEPA FILTER CAPABLE OF FILTRATION RATES OF 300-800
CUBIC FEET PER MINUTE (FT3/MIN), OR EXHAUST AIR DIRECTLY TO THE
OUTSIDE IF APPROVED BY VAMC. IF EXHAUST SHALL BE TIED INTO A
RE-CIRCULATED AIR SYSTEM, A PRE-FILTER AND HEPA FILTER SHALL
BE USED BEFORE EXHAUST TO PREVENT CONTAMINATION OF THE
DUCTS.
5B. ADJACENT AREAS: THE STATUS OF SEALED PENETRATIONS AND
INTACT CEILING SHALL BE VERIFIED DAILY.
5C. AIR EXCHANGE RATES AND PRESSURE RELATIONSHIPS: VAMC AND
CONTRACTOR SHALL VERIFY AND MAINTAIN PROPER RATES IN
CRITICAL AREAS NEAR CONSTRUCTION ACTIVITY AND ENSURE AIR IS
NOT BEING RE-CIRCULATED WITHOUT FILTRATION FROM THE
CONSTRUCTION AREA ELSEWHERE. PROVIDE AIR PRESSURE TESTING
THROUGHOUT THE PROJECT IN THE FREQUENCY AS IDENTIFIED BY
THE COR.
CONTAMINATION OF PATIENT ROOMS, SUPPLIES, EQUIPMENT AND RELATED
AREAS
6. WORKSITE CLOTHING: CONTRACTOR PERSONNEL CLOTHING SHALL BE
FREE OF LOOSE SOIL AND DEBRIS BEFORE LEAVING THE
CONSTRUCTION AREA. IF PROTECTIVE APPAREL IS NOT WORN (E.G.,
COVERALLS, FOOTGEAR AND HEADGEAR) A HEPA-FILTERED VACUUM
SHALL BE USED TO REMOVE DUST FROM CLOTHING BEFORE LEAVING
THE BARRICADE. IF PROTECTIVE APPAREL IS UTILIZED, THE
CONTRACTOR SHALL CONSTRUCT A SPACE OR ANTEROOM FOR
CHANGING CLOTHING AND STORING EQUIPMENT (DESIGNATED AREA.
ALL EQUIPMENT, TOOLS, TOOL CARTS, AND MATERIALS TRANSPORTED
THROUGH OCCUPIED AREAS SHALL BE MADE FREE FROM DUST AND
MOISTURE BY VACUUMING AND WET WIPING BEFORE THEIR REMOVAL
FROM THE CONSTRUCTION ZONE OR WORK AREA.
6A. POST CONSTRUCTION: DO NOT REMOVE BARRIERS AND KEEP ALL
HVAC ISOLATION UNTIL CONTRACTOR HAS CLEANED CONSTRUCTION
SITE, VA EMS STAFF HAS DONE A TERMINAL CLEANING, AND VA
INFECTIOUS DISEASE CONTROL HAS INSPECTED AND APPROVED THE
CLEANING.
ICRA NOTES
III/IVLOW Risk Group 1
Class III
Note: Infection Control approval will be required when the Construction Activity and Risk Level indicate that
It is the Contractor's Responsibility to provide the following Infection Control Precautions depending upon the Area Class Designation
II
I
III
MEDIUM Risk Group 2
HIGH Risk Group 3
HIGHEST Risk Group 4 IV
IV
IV
III/IV
III/IV
III
III/IV
I
III
Patient Risk Group Table
Infection Control Matrix - Class of Precautions: Construction Project by Patient Risk
TYPE A
Construction Project Type
Major demolition and construction projects
Includes, but is not limited to:
- activities which require consecutive work shifts
- requires heavy demolition or removal of a complete ceiling system
- new construction
Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies
Includes, but is not limited to:
- sanding of walls for painting or wall covering
- removal of floor coverings, ceiling tiles and casework
- new wall construction
- minor duct work or electrical work above ceilings
- major cabling activities
- any activity which cannot be completed within a single work shift
Small scale, short duration activities which create minimal dust
Includes, but is not limited to:
- installation of telephone and computer cabling
- access to chase spaces
- cutting of walls or ceiling where dust migration can be controlled
Inspection and Non-Invasive Activities
Includes, but is not limited to:
- removal of ceiling tiles for visual inspection limited to 1 tile to 50 square feet
- painting (but not sanding), wall covering
- electrical trim work, minor plumbing, and activities which do not generate dust or require cutting of walls or access to ceilings other than for visual inspection
Type of Construction / Project Activity Table
Group 2 Medium Risk
Group 1 Low Risk
- Office areas (non-clinical)
- Hallways
- FES/EMS areas
I
Patient Risk Group
TYPE D
TYPE C
TYPE B
TYPE A
Group 4 Highest Risk
Group 3 High Risk
- Pharmacy
- Radiology/ CT Scanner
- Urgent Care
- Laboratories
- CLCs
- SPD; AMCU;
- Respiratory Isolation Rooms
- Surgery
III
TYPE DTYPE CTYPE B
Class IVor control procedures are necessary.
C
LA
S S
IV
C
LA
S
S
II
During Construction Project
C L-
I C
LA
S
S
II
I
1. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.
2. Contain construction waste before transport in tightly covered containers.
3. Cover transport receptacles or carts. Tape covering
4. Vacuum work area with HEPA filtered vacuums.
5. Wet mop area with disinfectant after barriers are removed.
6. Remove or isolate HVAC system in areas where work was being performed.
1. Remove barrier materials carefully to minimize spreading of dirt and debris associated with construction.
2. Contain construction waste before transport in tightly covered containers.
3. Cover transport receptacles or carts. Tape covering.
4. Vacuum work with HEPA-filtered vacuums.
5. Wet mop with disinfectant.
6. Remove isolation of HVAC system in areas where work is being performed.
1. Wipe surfaces to remove dust.
Upon Completion of Project
1. Wipe work surfaces with disinfectant.
2. Contain construction waste before transport in tightly covered containers.
3. Wet mop and/or vacuum work area with HEPA filtered vacuum before leaving work areas.
4. Remove isolation of HVAC system in areas where work is being performed.
1. Includes all activities required by Class II
2. Obtain Infection Control Permit from Hospital Safety Officer or Facilities
Management Maintenance and Engineering department before construction begins.
3. Remove or isolate HVAC system in area where work is being done to prevent contamination of duct system.
4. Complete all critical barriers before construction begins or implement control cube method.
5. Maintain negative air pressure within work site utilizing HEPA-equipped air filtration units.
6. Contain construction waste before transport in tightly covered containers.
7. Cover transport receptacles or carts. Tape covers.
8. Wet mop and/or vacuum with HEPA filtered vacuum before leaving work areas.
9. Remove isolation of HVAC system in areas where work is being performed.
1. Execute work by methods to minimize raising dust from construction operations.
2. Immediately replace a ceiling tile displaced for visual inspection.
1. Includes all activities required by Class I
2. Provide active means to prevent airborne dust from dispersing into atmosphere.
3. Water mist work surfaces to control dust while cutting.
4. Seal unused doors with duct tape.
5. Block off and seal air vents.
6. Replace adhesive walk-off mats at entrance and exit of work area. Replace used mats in accordance with manufacturer's recommendations.
7. Remove or isolate HVAC system in area where work is being done to prevent contamination of duct system.
1. Includes all activities required by Class III
2. Obtain Infection Control Permit from Hospital Safety Officer or Facilities
Management Maintenance and Engineering department before construction begins.
3. Isolate HVAC system in areas where work is being done to prevent contamination of duct system.
4. Complete all critical barriers or implement control cube method before construction begins.
5. Maintain negative air pressure within work site utilizing HEPA equipped air filtration units.
6. Seal holes, pipes, conduits, and punctures appropriately.
7. Construct anteroom and require all personnel to pass through this room so they can be vacuumed sing a HEPA vacuum cleaner before leaving work site or they can wear cloth or paper coveralls that re removed each time they leave the work site.
8. All personnel entering work site are required to wear shoe covers. Shoe covers must be changed each time the worker exits the work area.
9. Place adhesive walk-off mats at entrance to work area within anteroom.
10. Replace per manufacturer's recommendations. Do not remove barriers from work area until completed project is inspected each by the Hospital Safety Officer, Facilities Management Maintenance and Engineering Department and thoroughly cleaned by the Hospital Environmental Services Department or their contracted Environmental Service Company Contain construction waste before transport in tightly covered containers.
11. Cover transport receptacles or carts. Tape covering
12. Vacuum work area with HEPA filtered vacuums.
13. Wet mop with disinfectant after barriers are removed.
14. Remove isolation of HVAC system in areas where work is being performed.
- Physical Therapy
- Radiology departments
- All patient waiting rooms
- All outpatient clinics
- Research Areas
- Respiratory Therapy
Engineers Architects
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/4
/2
:0
:1
P M
C U s e rs
\c k u rk u l\ D o c u m e n ts
\A
-1
Y
-Q
-V
A Y o rk
S e c I m p ro v -T
N c k u rk u lG
V Y
H
.r v t
G-003
ICRA INFORMATION AND DETAILS
3 4NPM
IMPROVE SECURITY YORK
CAMPUS
ALVIN C. YORK VA MEDICAL CENTER
3400 LEBANON RD.
MURFREESBORO, TN 37129 MARCH 8, 2024
BID DOCUMENTS
626A4-20-10322-199Y
WVS
Scale: 1/2" = 1'-0"
ICRA MOBILE CONTAINMENT CART
Scale: 3/4" = 1'-0"
ICRA BARRIER WALL TYPE
Scale: 3" = 1'-0"
ILSM CONSTRUCTION EGRESS SIGNAGE
107 18 17 16
PAT ED
BOOTHS
G12M
IV
BUFFER
G12CC
HD
BUFFER
G12HH HD
ANTEROOM
G12GG
HD
STAGING
G12X
DELIVERY/
RECYCLING
/WASTE
PICKUP
G12U
RECEIVING
TEARDOWN
G12V
OPEN
STORAGE
G12Z
CORRIDOR
G12W
OFFICE
G12AA
IV
ANTEROOM
OFFICE
G12H
ANTE
G12J
CHEMO
IV
BUFFER
DISPENSING
G12B
VAULT
G12P
WAITING
G12
VAULT,
G12D
TECH
G12H
RECEIVING
G12G
PICK
G12M
PRO
TECH
G12J
SUPER
G12F
PHARM
PROCESS
G12G
OFFICE 4
G08C
OFFICE 3
G08D
OFFICE 2
G08E
TECH
G12E
PHARMACY
BULK
G12D COMPOUNDING
G12O
CORRIDOR
G12Q
MULTI-PURPOSE
G08
HAC
G12A
CORR.
G30A
STAIR
G10
VESTIBULE
FILLING/ASSEMBLY
G12C
CART
STOR.
G12N
G12G
G30A
G12FAN
ROOM
G12A
G12B
CORRIDOR
G29
OFFICE 1
G80A
ADMIN
G08B
EXISTING SIDEWALK
A-601
CONSTRUCTION MATERIALS
ROUTE
PROPOSED CONTRACTOR
STAGING AREA
LEGEND
Engineers Architects
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
SHEET NOTES:
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/4
/2
:0
:1
P M
C U s e rs
\c k u rk u l\ D o c u m e n ts
\A
-1
Y
-Q
-V
A Y o rk
S e c I m p ro v -T
N c k u rk u lG
V Y
H
.r v t
G-004
GROUND FLOOR LOGISTICS PLAN
4 4NPM
IMPROVE SECURITY YORK
CAMPUS
ALVIN C. YORK VA MEDICAL CENTER
3400 LEBANON RD.
MURFREESBORO, TN 37129 MARCH 8, 2024
BID DOCUMENTS
626A4-20-10322-199Y
WVS
Scale: 1/8" = 1'-0"
GROUND FLOOR LOGISTICS PLAN
N
KEY PLAN
SCALE: NO SCALE
AREA OF WORK
N O
R T
H
0 4 8 16
A. SEE SPECIFICATIONS FOR BADGING
REQUIREMENTS.
B. NO MAJOR EQUIPMENT ACCESS THROUGH THE
BUILDING BETWEEN 7AM TO 5PM. CONTRACTOR
TO COORDINATE WITH VA COR.
C. STICKY MAT AT CONSTRUCTION ACCESS TO BE
CHANGED WHEN DIRTY AT VA REQUEST.
CB
M W
W
G
G
G
G W
W W
W W
W W
W W
W W
W W
UG
/E
UG
/E
UG
/E
UG/E
UG/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG
/E
UG/E
PA
R
K R
O A
D
G
BUILDING 121
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
Date Checked Drawn
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs© COPYRIGHT Apogee Consulting Group, P.A.
Engineers Architects
MARCH 8, 2024
BID DOCUMENTS
626A4-20-10322-199Y
A
B C
D E
21 4 5 6 7
321 4 5 6 7
NC License #: C-1848
Revisions: Date#
# N/A
ALVIN C. YORK VA MEDICAL CENTER
3400 LEBANON RD.
MURFREESBORO, TN 37129
IMPROVE SECURITY
YORK CAMPUS
CS100
CAHDLS
CIVIL SITE PLAN
1 1
KEY PLAN
1" = 10'
SCALE IN FEET
10 5 10 20 before you dig belowKnow what's
Call
R
1) CONTRACTOR SHALL NOTIFY COR OF ANY DISCREPANCIES
BETWEEN THE EXISTING CONDITIONS IN THE FIELD AND THE SURVEY
SHOWN ON THE PLANS BEFORE PROCEEDING WITH ANY NEW
CONSTRUCTION.
2) CONTRACTOR IS RESPONSIBLE FOR CORRECT HORIZONTAL AND
VERTICAL ALIGNMENT OF ALL TIES BETWEEN PROPOSED AND
EXISTING PAVEMENTS, CURB AND GUTTER, SIDEWALKS, WALLS, AND
UTILITIES.
3) ALL BUFFERS, TREE SAVE AREAS, AND UNDISTURBED AREAS
SHALL BE CLEARLY IDENTIFIED BY FLAGGING AND/OR FENCING PRIOR
TO COMMENCEMENT OF ANY LAND DISTURBANCE.
4) NO OUTSIDE STORAGE IS PERMITTED. THIS INCLUDES SUPPLIES,
VEHICLE, EQUIPMENT, PRODUCTS, ETC.
5) ALL EROSION, SEDIMENT CONTROL AND TREE PROTECTION
MEASURES SHALL BE INSTALLED PRIOR TO ANY GRADING.
6) MAXIMUM CUT OR FILL SLOPE=3H:1V
7) 24 HOUR CONTACT: VA COR
8) IN ALL AREAS OF FILL OR OTHERWISE DISTURBANCE OF EXISTING
CONDITIONS, UNLESS OTHERWISE NOTED, THE CONTRACTOR SHALL
FULLY AND COMPLETELY REMOVE AND LEGALLY DISPOSE OFF-SITE,
ALL PLANT MATERIALS INCLUDING BUT NOT LIMITED TO ROOT
SYSTEMS, CONCRETE, REINFORCED CONCRETE, ASPHALT DEBRIS,
UNDERBRUSH, TOPSOIL, AND OTHER DELETERIOUS MATERIAL. THE
SUBGRADE TO REMAIN SHALL BE COMPACTED TO 98% STANDARD
PROCTOR MAXIMUM DRY DENSITY FOLLOWING FULL REMOVAL OF
THESE MATERIALS. REFER TO SPEC 31 20 00 FOR FURTHER DETAILS.
9) CONTRACTOR SHALL BE RESPONSIBLE FOR CONSTRUCTION AND
MAINTENANCE OF EROSION AND SEDIMENTATION CONTROLS DURING
CONSTRUCTION FOR PROTECTION OF ADJACENT ROADWAYS.
SHEET NOTES:
KEY NOTES:
1. EXISTING METAL CANOPY (TO REMAIN)
2. EXISTING CONCRETE ISLAND (TO REMAIN)
3. TYPE "A" 5" CONCRETE BOLLARDS TO BE INSTALLED 10" ON
CENTER FROM FACE OF CONCRETE ISLAND, 3" ON CENTER
FROM CORNER OF GAS PUMPS, MAX BOLLARD SPACING 5'
CENTER TO CENTER (TYP.)
4. EXISTING CONCRETE PAVING (TO REMAIN)
5. EXISTING FUEL PUMP (TO REMAIN)
6. EXISTING CONCRETE CURB (TO REMAIN)
7. EXISTING CANOPY SUPPORT COLUMN (TO REMAIN)
8. EXISTING STORM GRATE (TO REMAIN)
9. EXISTING IN-GROUND FUEL TANK CONNECTION POINT (TO
REMAIN)
NOTES:
1. POST BARRICADES SHALL BE PAINTED WITH ONE PRIME COAT OF RED OXIDE (PAINT NO.1).
ONE FINISH COAT OF DULL BLACK ENAMEL PER VA SPECIFICATIONS AND STRIPES CONSISTING OF 4" [102mm] BANDS OF YELLOW REFLECTORIZED TAPE SHALL BE USED UNLESS OTHERWISE
SPECIFIED ON THE PLANS.
2. FINISH COLOR COMBINATIONS, OTHER THAN THAT SPECIFIED ABOVE, SHALL BE SUBMITTED TO
THE AGENCY FOR APPROVAL.
5"Øx7'-0" [127Øx2134mm]
STANDARD PIPE POST
BARRICADE CONCRETE
FILLED
UTILITY CONCRETE
PER VA
SPECIFICATIONS
5' O.C.[1.5m]
3"Øx5'-0" [76Øx1524mm]
STANDARD PIPE POST
BARRICADE CONCRETE
FILLED.
[1 m m
4" [1 m m
4"
[1
2m m
4'-
6" 2'-
6" [7 m m
[7 6m
3" m
4" m m
4"
[1
7m m
3'-
6" 1'-
6" [7 m m
[7 6m
3"
TYPE "A" TYPE "B"
[305mm] 12"
[229mm] 9"
CONCRETE POST BARRICADES
NOT TO SCALE
CS100
UG/E UG/E EXISTING UNDERGROUND ELECTRICAL
W W EXISTING UNDERGROUND WATER LINE
LEGEND
ENTER
EXIT
03/08/2024
AFF ABOVE FINISHED FLOOR
ACP/APC ACOUSTIC CEILING PANEL/
ACOUSTIC PANEL CEILING
ACT ACOUSTIC(AL) TILE
ADJ ADJUSTABLE
ADT'L ADDITIONAL
AGG AGGREGATE
ALT ALTERNATE
AL ALUMINUM
APPROX APPROXIMATE(LY)
ASPH ASPHALT
AUTO AUTOMATIC
B/O BOTTOM OF
BD BOARD
BLDG BUILDING
BLKG BLOCKING
BOT BOTTOM
BRG BEARING
CENTERLINE
C/C CENTER TO CENTER
CJ CONTROL JOINT
CLL CONTRACT LIMIT LINE
CEM CEMENT(ITIOUS)
CMU CONCRETE MASONRY UNIT
CLG CEILING
CLR CLEAR
COL COLUMN
CONC CONCRETE
CONST CONSTRUCTION
CONT CONTINUOUS
CPT CARPET
CT CERAMIC TILE
CTR CENTER(ED)
DF DRINKING FOUNTAIN
DS DOWNSPOUT
DBL DOUBLE
DEG DEGREE
DEMO DEMOLITION
DET/DTL DETAIL
DIA DIAMETER
DIM DIMENSION
DN DOWN
DWG(S) DRAWING(S)
E EAST
EC ELECTRICAL CONTRACTOR
EHO ELECTRICAL HOLD OPEN
EJ EXPANSION JOINT
EW EACH WAY
EA EACH
EIFS EXTERIOR INSULATION
FINISH SYSTEM
EL ELEVATION
ELEC ELECTRIC(AL)
ELEV ELEVATOR
EMER EMERGENCY
EQ EQUAL
EQUIP EQUIPMENT
EXIST EXISTING
EXT EXTERIOR
EWC ELECTRIC WATER COOLER
FD FLOOR DRAIN
FE FIRE EXTINGUISHER
FFE FINISH FLOOR ELEVATION
FV FIELD VERIFY
FEC FIRE EXTINGUISHER CABINET
FDN FOUNDATION
FIN FINISH
FLSHG FLASHING
FLR FLOOR
FRMG FRAMING
FT FOOT/FEET
FTG FOOTING
GC GENERAL CONTRACTOR
GA GAUGE
GALV GALVANIZED
GEN GENERAL
GYP GYPSUM
HM HOLLOW METAL
HDWR HARDWARE
HOL HOLLOW
HOR HORIZONTAL
HT HEIGHT
HVAC HEATING/VENTILATION/AIR
CONDITIONING
ID INSIDE DIAMETER
IN INCH
INCL INCLUDING
INSUL INSULATION
INT INTERIOR
JAN JANITOR
JT JOINT
LAV LAVATORY
LB(S) POUND(S)
L/S LANDSCAPE
LT LIGHT
MO MASONRY OPENING
MAS MASONRY
MAT'L MATERIAL
MAX MAXIMUM
MECH MECHANICAL
MFR MANUFACTURER
MIN MINIMUM
MISC MISCELLANEOUS
MTD MOUNTED
MTL METAL
N NORTH
NIC NOT IN CONTRACT
NTS NOT TO SCALE
NOM NOMINAL
OC ON CENTER
OD OUTSIDE DIAMETER
O TO O OUT TO OUT
OPNG OPENING
OPP OPPOSITE
OVHD OVERHEAD
PEB PRE-ENGINEERED BUILDING
PJF PREFORMED JOINT FILLER
PT PRESSURE TREATED
PERIM PERIMETER
PL PLATE
PLAM PLASTIC LAMINATE
PLBG PLUMBING
PLYWD PLYWOOD
PNT PAINT
PR PAIR
PTD PAINTED
PWR POWER
RB RUBBER BASE
RD ROOF DRAIN
RO ROUGH OPENING
RAD RADIUS
REC RECESSED
REINF REINFORCED
REQ'D REQUIRED
REV REVISED (REVISION)
RM ROOM
S SOUTH
SB SPLASH BLOCK
SF SQUARE FEET
SS STAINLESS STEEL
SIM SIMILAR
SPEC SPECIFICATIONS
SQ SQUARE
STD STANDARD
STL STEEL
STOR STORAGE
STRUCT STRUCTURAL
SUSP SUSPENDED
T&G TONGUE AND GROOVE
T/O TOP OF
TELE TELEPHONE
TRTD TREATED
TS TUBE STEEL
TYP TYPICAL
UNFIN UNFINISHED
UNO UNLESS NOTED OTHERWISE
VCT VINYL COMPOSITION TILE
VIF VERIFY IN FIELD
VERT VERTICAL
W WEST
W/ WITH
W/O WITHOUT
WC WATER CLOSET
WWF WELDED WIRE FABRIC
WD WOOD
WH WATER HEATER
WT WEIGHT
CL
DEMOLITION KEYNOTE WINDOW TYPE
DOOR TAG
TYPICAL KEYNOTE CEILING/ SOFFIT
HEIGHT
MATL
1'-0"
1. INDICATIONS OF PROJECT LIMITS OR LINES OF DEMARCATION ARE SHOWN FOR GENERAL SCOPE DEFINITION AND REFLECT THE UNDERSTANDING OF THE DESIGNER AS TO THE LIMITATIONS OF THE WORK AREA IN AN OCCUPIED AREA. ACTUAL CONTRACT LIMITS ARE TO BE DETERMINED BY AGREEMENT BETWEEN THE COR AND
CONTRACTOR BEFORE THE START OF THE WORK.
2. DRAWINGS ARE PREPARED USING PRODUCT DIMENSIONS AND DETAILS FROM BASIS OF DESIGN PRODUCT.
PRODUCTS MAY CHANGE IN DIMENSION AND DETAIL BEFORE THEY ARE INCORPORATED INTO
WORK. PRODUCTS FROM OTHER MANUFACTURER’S ARE ALSO ACCEPTABLE. DIMENSIONS AND DETAILS FOR ALTERNATE PRODUCTS MAY VARY FROM BASIS OF DESIGN. CONTRACTOR SHALL VERIFY INSTALLATION REQUIREMENTS FOR ALL PRODUCTS TO BE INCORPORATED INTO WORK (INCLUDING THICKNESS FOR RECESSED OR SEMI-RECESSED PRODUCTS) AND IS REPONSIBLE FOR ACCOMODATING AND COORDINATING CHANGES TO OTHER MATERIALS OR PRODUCTS THAT ARE NECESSARY BECAUSE OF THESE DIFFERENCES.
3. THE DRAWINGS AND SPECIFICATIONS ARE SEPARATED INTO DISCIPLINES FOR CONVENIENCE. THE SEPARATIONS ARE USED ONLY FOR THE PURPOSES OF CONVENIENCE AND REFERENCE AND IN NO WAY DO THEY DEFINE OR LIMIT THE SCOPE OR INTENT OF ANY PART OF THE DRAWINGS AND SPECIFICATIONS AS A WHOLE. THE FACT THAT THE DRAWINGS ARE SEPARATED IN NO WAY SUGGESTS THAT THE WORK IS NOT TO
BE CONSTRUCTED AS A COMPLETE, INTEGRATED AND UNIFIED WHOLE.
4. THE DRAWINGS AND SPECIFICATIONS, INCLUDING DRAWINGS PREPARED BY SPECIFIC ENGINEERING DISCIPLINES ARE COMPLEMENTARY; ITEMS SHOWN IN ANY ONE LOCATION IN THE DRAWINGS SHALL BE CONSIDERED TO BE REQUIREMENTS OF THE CONTRACT FOR CONSTRUCTION. IN THE EVENT OF AN INCONSISTENCY BETWEEN THE DRAWINGS AND SPECIFICATIONS, OR WITHIN EITHER DOCUMENT, THE CONTRACTOR SHALL SEEK CLARIFICATION OR INTERPRETATION FROM THE COR PRIOR TO BIDDING. WHERE INCONSISTENCIES ARE NOT CLARIFIED PRIOR TO BIDDING, AND WHERE THE ACTUAL SOLUTION OR INTENT CANNOT BE REASONABLY INFERRED, THE CONTRACTOR SHALL PROVIDE THE BETTER QUALITY OR GREATER
QUANTITY OF WORK.
5. THE CONTRACTOR SHALL NOTIFY THE COR IMMEDIATELY SHOULD DISCREPANCIES BE FOUND IN THE
DRAWINGS AND SPECIFICATIONS.
6. THE CONTRACTOR IS RESPONSIBLE FOR CHECKING ALL FIELD CONDITIONS AND DIMENSIONS AS THEY RELATE TO THIS PROJECT, FOR EACH PHASE. SHOULD DISCREPANCIES EXIST BETWEEN THE WORK INDICATED AND
ACTUAL FIELD CONDITIONS, NOTIFY THE COR PRIOR TO PROCEEDING WITH THE WORK.
7. DO NOT SCALE THE DRAWINGS. DRAWING SCALES AS INDICATED ARE FOR REFERENCE ONLY AND ARE NOT INTENDED TO ACCURATELY DEPICT ACTUAL OR DESIGNATED CONDITIONS. WRITTEN DIMENSIONS SHALL
GOVERN.
8. PROVIDE SEALANT AT ALL INTERSECTIONS BETWEEN DIFFERENT MATERIALS.
9. COORDINATE WORK OF ALL TRADES PRIOR TO STARTING CONSTRUCTION.
10. REFER TO ALL OTHER TRADE DRAWINGS AND SPECIFICATIONS FOR ADDITIONAL INFORMATION ON THIS
PROJECT.
11. PROVIDE BLOCKING AT PARTITIONS AS REQUIRED FOR MOUNTING OF WALL-MOUNTED ITEMS: PROVIDE SUPPLEMENTAL FRAMING AT WALL OPENINGS INCLUDING KING STUDS, JACK STUDS, AND CRIPPLE STUDS, AS
REQUIRED FOR COMPLETION OF THE WORK.
12. DIMENSIONS SHOWN ARE TO FACE OF STUD FRAMING, FACE OF CONCRETE/MASONRY WALLS, OR FINISHED
FACE OF EXISTING WALL SURFACE.
13. ALL WOOD IN CONTACT WITH CONCRETE SHALL BE PRESSURE TREATED.
1. KEY NOTES AND DRAWINGS ARE INTENDED TO GRAPHICALLY REPRESENT GENERAL WORK AND DO NOT
PORTRAY FULL SCOPE OF THE PROJECT. SEE SPECIFICATIONS FOR DETAILED REQUIREMENTS.
2. REMOVE EXISTING CONSTRUCTION AS DESIGNATED HEREIN AND CLEAR AREA OF DEBRIS PRIOR TO
PROCEEDING WITH NEW CONSTRUCTION.
3. EXISTING EQUIPMENT REMOVED SHALL BE PROPERLY DISPOSED OF, OFF PROJECT GROUNDS. COORDINATE
WITH COR.
4. AT AREAS INDICATED TO BE PATCHED AND REPAIRED, FOR ADDITION AND RENOVATION PROJECTS: THE CONSTRUCTION AND ASSEMBLY OF THE PATCH OR REPAIR SHALL MATCH THE ASSEMBLY AND INTEGRITY OF THE ADJACENT EXISTING CONSTRUCTION, FOR FIRE RATING, MATERIALS, FINISH, THICKNESS, AND QUALITY.
5. COORDINATE WORKING HOURS ALLOWED FOR DEMOLITION AND WASTE REMOVAL WITH COR.
6. NOTIFY COR OF ANY DEMOLITION REQUIRED AND NOT INDICATED FOR INSTALLATION OF ELECTRICAL OR DATA ITEMS. AFTER SUCH DEMOLITION AND INSTALLATION, PATCH OR REPLACE MATERIALS AND FINISHES TO MATCH
EXISTING.
7. CONTRACTOR SHALL PROTECT AREA ADJACENT TO THE DEMOLITION AND NEW CONSTRUCTION WORK TO PREVENT DAMAGES, (IF DAMAGED REPAIR, RE-PATCH, SAND SMOOTH AND REFINISH WITH SAME QUALITY OR BETTER.) REPAIR OR REPLACE ITEMS DAMAGED DURING CONSTRUCTION ACTIVITIES AT NO ADDITIONAL COST.
8. THE INFORMATION CONTAINED IN THESE DEMOLITION DOCUMENTS DEFINES GENERAL SCOPE ONLY AND DOES NOT RELIEVE THE CONTRACTOR OF THE RESPONSIBILITY OF PROVIDING ALL DEMOLITION REQUIRED FOR THE
COMPLETION OF THE PROJECT.
9. DO NOT ENCROACH ON ADJACENT OCCUPIED AREAS NOT IDENTIFIED WITHIN THE SCOPE OF WORK.
10. REFER TO THE ELECTRICAL DRAWINGS FOR FURTHER INFORMATION REGARDING DEMOLITION OF ELECTRICAL
SYSTEMS.
11. BEFORE THE START OF WORK, IDENTIFY ANY REQUIRED DEMOLITION BEYOND THE IDENTIFIED PROJECT SCOPE WHETHER ABOVE, BELOW, OR OUTSIDE THE PROJECT AREA. NOTIFY AND COORDINATE WITH THE COR, PROVIDE DEMOLITION OF THESE AREAS AND PATCH THE SAME AS A PART OF THE SCOPE OF THE PROJECT.
12. ALL DEMOLITION WORK SHALL BE PERFORMED WITH DUE CARE AND DILIGENCE IN ORDER TO PREVENT ARBITRARY DAMAGE OR INTERRUPTION OF SERVICE OR CONCEALED UTILITIES INTENDED TO REMAIN IN SERVICE. DISCOVERY OF UTILITIES OR CONDITIONS LOCATED DIFFERING FROM THOSE INDICATED OR THAT
ARE NOT IDENTIFIED, SHALL BE REPORTED TO THE COR.
13. AFTER REMOVAL OF EXISTING SOLID CONCRETE MASONRY WALL, FILL FLOOR VOIDS UP TO FINISH CONCRETE
LEVEL AND PERFORM FLOOR LEVELING FOR ENTIRE AREA OF RENOVATION.
14. VERIFY ALL EXISTING CONDITIONS PRIOR TO BEGINNING WORK. NOTIFY COR AND ARCHITECT OF ANY
CONFLICTS PRIOR TO PROCEEDING WITH DEMOLITION.
15. ALL ITEMS BEING SALVAGED OR REMOVED SHALL REMAIN THE PROPERTY OF THE OWNER UNTIL CONFIRMATION HAS BEEN MADE AS TO WHETHER THE OWNER WILL RETAIN SUCH ITEMS. ALL ITEMS NOT BEING RETAINED BY THE OWNER OR DESIGNATED ON THE DRAWINGS, ARE TO BE RELOCATED OR
REINSTALLED FROM THE SITE BY CONTRACTOR IN APPROVED MANNER.
16. CONTRACTOR SHALL NOTIFY COR OF ANY AREA REQUIRING DEMOLITION OTHER THAN SHOWN IN THESE DRAWINGS DUE TO UNFORSEEN CONDITIONS, TO ACCOMMODATE INSTALLATION OF ALL OTHER TRADES (INCLUDING ROOF PENETRATIONS). AFTER SUCH DEMOLITION AND INSTALLATION, PATCH OR REPLACE
MATERIALS AND FINISHES WITH SAME QUALITY OR BETTER.
17. COORDINATE WITH COR FOR CONSTRUCTION ACCESS ROUTE AND LOCATIONS OF DUMPSTER AREA.
COORDINATE WITH COR FOR SCHEDULE OF USE OF ACCESS ROUTE FOR WASTE REMOVAL AND CONTRACTOR
USE OF FREIGHT ELEVATOR (AS REQUIRED).
WALL SECTION
SYMBOL
INTERIOR ELEVATION
SYMBOL
COLUMN GRID
ELEVATION SYMBOL
REVISION NOTE
ENLARGED DETAIL CALLOUT
ROOM DESIGNATION
SYMBOL
BREAK LINE
ROOF SLOPE
DIRECTION SYMBOL
TYPICAL GRAPHIC SCALE
DETAIL #
PAGE #
DETAIL #
PAGE #
VIEW NORTH ARROW
A8.1
EXTERIOR ELEVATION
SYMBOL
DETAIL #
PAGE #
A8.1
A8.1
A8.1
BUILDING SECTION
SYMBOL
DETAIL #
PAGE #
A8.1
A8.1
DETAIL SECTION
SYMBOL
DETAIL #
PAGE #
A8.1
WALL GRID
(REPRESENTS
FACE OF EXISTING
WALL)
XX.X
XX.X
ELEVATION
0'-0"
ROOM
NAME
101A
NORTHNORTH
0 4 8 16
Engineers Architects
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/4
/2
:0
:2
P M
C U s e rs
\c k u rk u l\ D o c u m e n ts
\A
-1
Y
-Q
-V
A Y o rk
S e c I m p ro v -T
N c k u rk u lG
V Y
H
.r v t
A-001
ARCHITECTURAL GENERAL NOTES
1 4NPM
IMPROVE SECURITY YORK
CAMPUS
ALVIN C. YORK VA MEDICAL CENTER
3400 LEBANON RD.
MURFREESBORO, TN 37129 MARCH 8, 2024
BID DOCUMENTS
626A4-20-10322-199Y
WVS
ABBREVIATIONS
ARCHITECTURAL SYMBOL LEGEND
GENERAL NOTES
DEMOLITION NOTES
GENERAL SYMBOL LEGEND
EXISTING WALL TO REMAIN
EXISTING DOOR TO REMAIN
DEMOLISH WALL
DEMOLISH DOOR
DEMOLISH WINDOW
EXISTING WINDOW TO REMAIN
DEMO & ICRA LEGEND
TEMPORARY WALL 1 HR
TEMPORARY DOOR
PLASTIC ZIPPER BARRIER
STICKY MAT
A
B
C
D
E
F
G
302625.5876 13
RECEIVING
TEARDOWN
G12V
CORRIDOR
G12W
HD
STAGING
G12X
OFFICE
G12H
ANTE
G12J
CHEMO
DISPENSING
G12B
VAULT
G12P
PAT ED
BOOTHS
G12M
WAITING
G12
CORRIDOR
G28
VAULT,
G12D
TECH
G12H
RECEIVING
G12G
PICK
G12M
PRO
TECH
G12J
SUPER
G12F
PHARM
PROCESS
G12G
OFFICE 4
G08C
OFFICE 3
G08D
OFFICE 2
G08E
TECH
G12E
PHARMACY
BULK
G12D
COMPOUNDING
G12O
MULTI-PURPOSE
G08
HAC
G12A
CORR.
G30A
STAIR
G10
VESTIBULE
FILLING/ASSEMBLY
G12C
CART
STOR.
G12N
CORRIDOR
G12Q
107 18 17 16
G12
G12G
G30A
G12U
G12X
G12B
G12V
G12W
CR
CR
RECEIVING
G12G
T D
-0
PHASE 1 PHASE 2
PHASE 1 PHASE 2
TD-02
TD-04
2 2
3 3
CR
C R
TD-03
WORK AREA 1
WORK AREA 2 WORK AREA 3
WORK AREA 4
SCHEDULE
SEE
S E
E S
C H
E D
U L E
A 1
S E
E S
C H
E D
U L E
2"
SCHEDULE
SEE
2"
Engineers Architects
# KEY NOTES:
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
SHEET NOTES:
WALL RATING LEGEND
1 HR - FIRE SEPARATION
2 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREA
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
S S S S
/4
/2
:0
:2
P M
C U s e rs
\c k u rk u l\ D o c u m e n ts
\A
-1
Y
-Q
-V
A Y o rk
S e c I m p ro v -T
N c k u rk u lG
V Y
H
.r v t
AD-100
GROUND FLOOR DEMOLITION AND
ICRA PLAN
2 4NPM
IMPROVE SECURITY YORK
CAMPUS
ALVIN C. YORK VA MEDICAL CENTER
3400 LEBANON RD.
MURFREESBORO, TN 37129 MARCH 8, 2024
BID DOCUMENTS
626A4-20-10322-199Y
WVS
N
KEY PLAN
SCALE: NO SCALE
AREA OF WORK
Scale: 1/4" = 1'-0"
GROUND FLOOR DEMOLITION AND ICRA PLAN
N O
R T
H
0 2 4 8
ICRA DOOR SCHEDULE
DOOR NO.
DOOR DOOR FRAME FIRE
RATING HDWR SET REMARKSWIDTH HEIGHT THICK ELEV MAT'L ELEV
HARDWARE SET 1.0
3 HINGES
1 DUST PROOF STRIKE PLATE
1 LATCH SET
1 DOOR CLOSER
2 KICK PLATES
1 GASKETING
MANUFACTURER'S
CORBIN RUSSWIN
MCKINNEY
PEMKO
ROCKWOOD
CO
MK
PE
RO
TA2714
VA CAMPUS STANDARD
DC6210XA11
K1050F
S888 X HEAD & JAMBS
32D
26D
32D
MK
RO
CO
RO
PE
NOTES:
HARDWARE MANUFACTURER'S LISTED AS BASIS OF DESIGN. ALTERNATE
MANUFACTURERS ACCEPTABLE, SUBJECT TO REVIEW BY ARCHITECT AND C.O.R.
FOR EQUAL QUALITY COMPLIANCE.
LATCH SET TO SUPPORT THAT WHICH ARE USED AT THIS FACILITY, COORDINATE
WITH C.O.R.
DOOR TYPE A TO BE HOLLOW METAL OR SOLID CORE WOOD VENEER AT
CONTRACTOR'S DISCRETION
TD-01 3'-0" 7'-0" 1 3/4" A HM 1 45 MIN. 1.0
TD-02 3'-0" 7'-0" 1 3/4" A HM 1 45 MIN. 1.0
TD-03 3'-0" 7'-0" 1 3/4" A HM 1 45 MIN. 1.0
1 DEMO WALL TO STUDS THIS SIDE ENTIRE
WALL. STUDS AND INSULATION ETR.
2 DEMO DOOR AND FRAME.
3 DEMO COUNTERTOP BOTH SIDES. SEE
PHASING NOTE THIS SHEET.
4 REMOVE PASS THRU.
5 COORDINATE ENCLOSING THIS AREA WITH
PHARMACY. DELIVERIES COME THROUGH
THIS AREA.
6 DEMOLISH EXISTING CARD READER.
A. WORK IN THE PHARMACY TO OCCUR IN TWO
PHASES. ONE COUNTERTOP AND WINDOW
TO REMAIN OPERATIONAL AT ALL TIMES
THROUGHOUT THE CONSTRUCTION PERIOD.
COMPLETE DEMO AND NEW WORK IN ITS
ENTIRETY BEFORE MOVING ON TO THE NEXT
PHASE.
B. TEMPORARY ENCLOSURES AND ICRA MEASURES
MUST BE IN PLACE PRIOR TO DEMOLITION WORK.
COORDINATE SEQUENCING OF WORK AREAS
WITH VA.
Scale: 1/2" = 1'-0"
ICRA DOOR, FRAME, AND SCHEDULE
TD-04 3'-0" 7'-0" 1 3/4" A HM 1 45 MIN. 1.0
NOTES:
DOOR SCHEDULE AND HARDWARE INFO FOR TEMPORARY DOORS ONLY
CR
CRCR
C R
A
B
C
D
E
F
G
302625.5876
RECEIVING
TEARDOWN
G12V
CORRIDOR
G12W
HD
STAGING
G12X
OFFICE
G12H
ANTE
G12J
CHEMO
DISPENSING
G12B
VAULT
G12P
PAT ED
BOOTHS
G12M
WAITING
G12
CORRIDOR
G28
VAULT,
G12D
TECH
G12H
RECEIVING
G12G
PICK
G12M
PRO
TECH
G12J
SUPER
G12F
PHARM
PROCESS
G12G
OFFICE 4
G08C
OFFICE 3
G08D
OFFICE 2
G08E
TECH
G12E
PHARMACY
BULK
G12D
COMPOUNDING
G12O
MULTI-PURPOSE
G08
HAC
G12A
CORR.
G30A
STAIR
G10
VESTIBULE
FILLING/ASSEMBLY
G12C
CART
STOR.
G12N
CORRIDOR
G12Q
A-601
A-601
107 18 17 16
G12U
G12X
G12V
G12W
G12G
G12
G30A
FAN
ROOM
G12A
RECEIVING
G12G
G12B
2 2
5 5
6 6 6
A-601
A-601
PHASE 1 PHASE 2
PHASE 1 PHASE 2
7 7
A-601
Engineers Architects
# KEY NOTES:
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
SHEET NOTES:
WALL RATING LEGEND
1 HR - FIRE SEPARATION
2 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREA
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
S S S S
/4
/2
:0
:2
P M
C U s e rs
\c k u rk u l\ D o c u m e n ts
\A
-1
Y
-Q
-V
A Y o rk
S e c I m p ro v -T
N c k u rk u lG
V Y
H
.r v t
A-100
GROUND FLOOR PLAN
3 4NPM
IMPROVE SECURITY YORK
CAMPUS
ALVIN C. YORK VA MEDICAL CENTER
3400 LEBANON RD.
MURFREESBORO, TN 37129 MARCH 8, 2024
BID DOCUMENTS
626A4-20-10322-199Y
WVS
Scale: 1/4" = 1'-0"
GROUND FLOOR PLAN
N O
R T
H
0 2 4 8
N
KEY PLAN
SCALE: NO SCALE
AREA OF WORK
1 ATTACH 3 5/8" 16 GA. STUDS TO EXISTING STUDS,
WELD NEW 9 GA. DIAMOND SECURITY MESH
OVER, SCREW 7/16" BALLISTIC LEVEL 3
FIBERGLASS PANELS. NEW GYP BD OVER AND
PAINT. EVERYTHING TO DECK ENTIRE WALL.
2 NEW PLASTIC LAMINATE OVER EXISTING
SUBSTRATE. P-LAM TO BE SELECTED BY VA
INTERIOR DESIGNER.
3 24" x 24" x 24" STAINLESS STEEL WITH GLASS
FRONT, INTERLOCKING PASS THRU CHAMBER BT
TERRA UNIVERSAL INC. OR EQUAL. STANDARD
MOUNTING BRACKETS WITH BRACING TO
PHARMACY SIDE. INSTALL AT EXISTING HOLE TO
EXISTING DEMOLISHED PASS THRU.
4 INFILL WALL WHERE EXISTING PASS-THRU WAS
REMOVED. CONCRETE BLOCK THICKNESS TO
MATCH EXISTING, METAL STUDS AND GYP BD,
PAINT TO MATCH EXISTING.
5 NEW DOOR AND FRAME, DUAL AUTHENTICATION
CARD READER. SEE SCHEDULE SHEET A-601.
6 INSTALL NEW WINDOW FILM BOD 3M S70X.
APPROXIMATE WINDOW SIZE IS 27" X 62"
7 EXISTING GLAZING TO REMAIN. EXISTING
GLAZING MEETS UL 752 LEVEL 3.
8 PAINT WALL.
A. WORK IN THE PHARMACY TO OCCUR IN TWO
PHASES. ONE COUNTERTOP AND WINDOW
TO REMAIN OPERATIONAL AT ALL TIMES
THROUGHOUT THE CONSTRUCTION PERIOD.
COMPLETE DEMO AND NEW WORK IN ITS
ENTIRETY BEFORE MOVING ON TO THE NEXT
PHASE.
GROUND FLOOR
0"
CEILING
8' - 0"
G30AG12B
A-601
A-601
PAINT ENTIRE WALL. COLOR
TO BE SELECTED BY VA
INTERIOR DESIGNER.
DISPENSING
G12B
WAITING
G12
DECK ABOVE
REMOVE 4'-0" OF EXISTING ACT
AND GRID AND STORE.
REMOVE GYP BD AND SECURITY
MESH
REMOVE FIBERGLASS PANELS
AND BATTENS
SECTION
FLOOR LEVEL
PLAN
SECTION
TOP OF WALL
GYPSUM BOARD REMAINS
ON THIS SIDE OF WALL
DISPENSING
G12B
WAITING
G12
SECTION
FLOOR LEVEL
PLAN
SECTION
TOP OF WALL DECK ABOVE
RE-USE ACT AND GRID UPON
COMPLETION OF WALL CONSTRUCTION
SPOT WELD NEW 9 GA. DIAMOND
SECURITY MESH TO 16 GA. METAL
STUDS @ 16" O.C. BOTH WAYS
3 5/8" 16 GA. MET'L STUDS ATTACH TO
EXIST. STUDS ENTIRE WALL
7/16" BALLISTIC LEVEL 3 FIBERGLASS
PANELS SCREW TO STUDS. BASIS OF
DESIGN: TOTAL SECURITY SOLUTIONS OR
EQUAL. SUBMITTAL REQUIRED.
5/8" TYPE 'X' GYP BD AND PAINT
RUBBER BASE
SECURITY MESH AND BALLISTIC
PROTECTION TO RUN TIGHT TO
UNDERSIDE OF DECK
1 2
2" 2"
SCHEDULE
SEE 2"
SCHEDULE
SEE 2"
S E
E S
C H
E D
U L E
S E
E S
C H
E D
U L E
GF
S E
E S
C H
E D
U L E
SCHEDULE
SEE
S E
E S
C H
E D
U L E
SCHEDULE
SEE
1'-8"8"
CAULK BOTH SIDES OF
DOOR - CONTINUOUS
EXISTING WALL
DOOR & FRAME - SEE
SCHEDULE
EXISTING WALL
DOOR & FRAME -
SEE SCHEDULE
SEE DOOR
SCHEDULE
DOOR AND FRAME -
SEE DOOR SCHEDULE
CAULK BOTH SIDES OF
DOOR - CONTINUOUS
METAL STUDS TO
FORM HEADER
SEE DOOR
SCHEDULE
TYPES
SEE PARTITION
DOOR AND
FRAME - SEE
DOOR SCHEDULE
CAULK BOTH
SIDES OF DOOR -
CONTINUOUS
METAL STUDS
TO FORM JAMB
DOOR AND FRAME - SEE
DOOR SCHEDULE
CAULK BOTH SIDES OF
DOOR - CONTINUOUS
(2) METAL STUDS TO
FORM JAMB
T Y
P E
S
S E
E P
A R
T
IT
IO
N
DOOR AND FRAME -
SEE DOOR SCHEDULE
CAULK BOTH SIDES OF
DOOR - CONTINUOUS
(2) METAL STUDS TO
FORM BOX BEAM
SEE DOOR
SCHEDULE
TYPES
SEE PARTITION
METAL FRAMED
WALL ASSEMBLY
5/8" GYP BD
GROUND FLOOR
0"
CEILING
8' - 0"
G12B
A-601
A-601
PAINT ENTIRE WALL. COLOR
TO BE SELECTED BY VA
INTERIOR DESIGNER.
NEW BASE TO MATCH
EXISTING.
GROUND FLOOR
0"
CEILING
8' - 0"
SUPPORT BRACKET
INTERLOCKING
STAINLESS STEEL PASS
THROUGH CHAMBER
MANUFACTURER'S MOUNTING
BRACKETS. SHOP DRAWINGS
REQUIRED.
V A
R
IE
S
DISPENSING
G12B
WAITING
G12
GROUND FLOOR
0"
V A
R
IE
S
11" +/-1'-6" +/-
EXISTING TELLER WINDOW
AND FRAME TO REMAIN
EXISTING STAINLESS
STEEL PASS THRU
DEPRESSION TO REMAIN.
REINSTALL AFTER NEW
PLAM INSTALLATION
EXISTING SHEATHING TO
REMAIN
REMOVE EXISTING P-LAM
AND REPLACE WITH NEW.
SELECTION BY THE VA.
DISPENSING
G12B
WAITING
G12
NO P-LAM ON UNDERSIDE
Engineers Architects
Revisions: Date
Drawing Title
Approved
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Office of Construction and Facilities Management
CONSULTANTS: PROJECT MANAGER
Date Checked Drawn
FULLY SPRINKLERED
ACG Project Number
Headquarters:
Apogee Consulting Group, P.A.
1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.
/4
/2
:0
:2
P M
C U s e rs
\c k u rk u l\ D o c u m e n ts
\A
-1
Y
-Q
-V
A Y o rk
S e c I m p ro v -T
N c k u rk u lG
V Y
H
.r v t
A-601
DOOR SCHEDULE AND DETAILS
4 4NPM
IMPROVE SECURITY YORK
CAMPUS
ALVIN C. YORK VA MEDICAL CENTER
3400 LEBANON RD.
MURFREESBORO, TN 37129 MARCH 8, 2024
BID DOCUMENTS
626A4-20-10322-199Y
WVS
CR= CARD READER
ETR= EXISTING TO REMAIN
HM= HOLLOW METAL
PNT= PAINT
SCW= SOLID CORE WOOD
STN= STAIN
WD= WOOD
DOOR SCHEDULE
DOOR DOOR FRAME HEAD
DETAIL NO.
JAMB
DETAIL NO. LBL
HDWR
SET REMARKSNO. WIDTH HEIGHT THICK MAT'L FINISH ELEV MAT'L FINISH ELEV
GROUND FLOOR
G12 3' - 6" 7' - 0" 1 3/4" WD STN F ETR PNT 2 7 3 45 MIN. 1.0 CR
G12B 3' - 0" 7' - 0" 1 3/4" WD STN F HM PNT 1 8 4 45 MIN. 1.0 CR
G12G 6' - 0" 7' - 0" 1 3/4" WD STN G HM PNT 1 6 2 2.0 CR
G30A 3' - 6" 7' - 0" 1 3/4" WD STN F HM PNT 2 7 3 45 MIN. 1.0 CR
Scale: 1/4" = 1'-0"
PHARMACY/DISPENSING INTERIOR ELEVATION
Scale: 3/4" = 1'-0"
PHARMACY DISPENSING WALL - DEMO
Scale: 3/4" = 1'-0"
PHARMACY DISPENSING WALL - NEW
Scale: 1/4" = 1'-0"
FRAME ELEVATIONS
Scale: 1/4" = 1'-0"
DOOR ELEVATIONS
Scale: 1 1/2" = 1'-0"
JAMB DETAIL @ CMU
Scale: 1 1/2" = 1'-0"
HEAD DETAIL @ CMU
Scale: 1 1/2" = 1'-0"
HEAD DETAIL @ METAL STUD
Scale: 1 1/2" = 1'-0"
JAMB DETAIL @ METAL STUD
Scale: 1 1/2" = 1'-0"
JAMB DETAIL @ METAL STUD
Scale: 1 1/2" = 1'-0"
HEAD DETAIL @ METAL STUD
Scale: 1/4" = 1'-0"
LOBBY INTERIOR ELEVATION
Scale: 3/4" = 1'-0"
PASS THROUGH DETAIL
Scale: 3/4" = 1'-0"
TELLER COUNTER SECTION
NOTES:
HM FRAME PAINT COLOR TO BE SELECTED BY VA
INTERIOR DESIGNER. SUBMITTAL REQUIRED.
L L
SPKR SPEAKER
SP SPARE
SR SURFACE RACEWAY
SS STAINLESS STEEL
SSW SELECTOR SWITCH
STD STANDARD
SURF SURFACE MOUNTED
SW SWITCH
SWBD SWITCHBOARD
SYM SYMMETRICAL
SYS SYSTEM
TC TIMECLOCK
TEL TELEPHONE
TEL/DATA TELEPHONE/DATA
TERM TERMINAL
TP TWISTED PAIR
TPS TWISTED PAIR SHIELDED
TR TAMPER RESISTANT
T-STAT THERMOSTAT
TTB TELEPHONE TERMINAL BOARD
TTC TELEPHONE TERMINAL CABINET
TV TELEVISION
TYP TYPICAL
UC UNDER COUNTER
UE UNDERGROUND ELECTRICAL
UG UNDERGROUND
UH UNIT HEATER
UL UNDERWRITER'S LABORATORY
UT UNDERGROUND TELEPHONE
UTP UNSHIELDED TWISTED PAIR
UTIL UTILITY
UV UNIT VENTILATOR OR
ULTRAVIOLET
V VOLT
VA VOLT-AMPERES
VERT VERTICAL
VFD VARIABLE FREQUENCY DRIVE
VOL VOLUME
W WATT
W/ WITH
WH WATER HEATER
W/O WITHOUT
WP WEATHERPROOF
XFMR TRANSFORMER
XFR TRANSFER
ANGLE
@ AT
DELTA
' FEET
" INCHES
# NUMBER
Φ PHASE
C CENTER LINE
P PLATE
MTR MOTOR, MOTORIZED
MTS MANUAL TRANSFER SWITCH
NA NOT APPLICABLE
NC NORMALLY CLOSED
NEC NATIONAL ELECTRICAL CODE
NEMA NATIONAL ELECTRICAL
MANUFACTURER'S ASSOCIATION
NFDS NON-FUSED SAFETY DISCONNECT
SWITCH
NIC NOT IN CONTRACT
NL NIGHT LIGHT
NO NORMALLY OPEN
NTS NOT TO SCALE
OC ON CENTER
OD OUTSIDE DIAMETER
OH OVERHEAD
OL OVERLOAD
PA PUBLIC ADDRESS
PB PULL BOX OR PUSHBUTTON
PBPU PREFABRICATED BEDSIDE PATIENT
UNIT
PCB POLYCHLORINATED BIPHENYL
PC PHOTOELECTRIC CELL
PED PEDESTAL
PEND PENDANT
PF POWER FACTOR
PH PHASE
PIV POST INDICATING VALVE
PNL PANEL
POE POWER-OVER-ETHERNET
PR PAIR
PRI PRIMARY
PROJ PROJECTION
PRV POWER ROOF VENTILATOR
PT POTENTIAL TRANSFORMER
PVC POLYVINYL CHLORIDE (CONDUIT)
PWR POWER
QTY QUANTITY
R RELOCATE/RELOCATED
RCP REFLECTED CEILING PLAN
RCPT RECEPTACLE
REQD REQUIRED
RGS RIGID GALVANIZED STEEL
RM ROOM
RMS ROOT MEAN SQUARE
RTU ROOF TOP UNIT
SC SURFACE CONDUIT
SEC SECONDARY
SF SQUARE FEET/FOOT
SHT SHEET
SI INTERNATIONAL SYSTEM OF UNITS
SIM SIMILAR
S/N SOLID NEUTRAL
SPEC SPECIFICATION
1P 1 POLE (2P, 3P, 4P, ETC.)
1PH 1 PHASE
2/C TWO-CONDUCTOR (3/C, 4/C, ETC.)
2W TWO-WIRE (3W, 4W, ETC.)
3PH 3 PHASE
A AMPERE
AAP ALARM ANNUNCIATOR PANEL
AC ABOVE COUNTER
AIR CONDITIONER
ALTERNATING CURRENT
ACC ACCESSIBLE
ACLG ABOVE CEILING
ADO AUTOMATIC DOOR OPENER
A/E ARCHITECT/ENGINEER
AF AMP FRAME
AFC AVAILABLE FAULT CURRENT (KILOAMPS)
AFF ABOVE FINISHED FLOOR
AFG ABOVE FINISHED GRADE
AFI ARC FAULT CIRCUIT INTERRUPTER
AHJ AUTHORITY HAVING JURISDICTION
AHU AIR HANDLING UNIT
AIC AMPERE INTERRUPTING CAPACITY
AL ALUMINUM
ALT ALTERNATE
AMP AMPERE
APPROX APPROXIMATELY
ARCH ARCHITECT, ARCHITECTURAL
AT AMP TRIP
ATS AUTOMATIC TRANSFER SWITCH
AUTO AUTOMATIC
AUX AUXILIARY
AV AUDIO VISUAL
AWG AMERICAN WIRE GAUGE
BAS BUILDING AUTOMATION SYSTEM
BATT BATTERY
BC BARE COPPER
BD BOARD
BFF BELOW FINISHED FLOOR
BLDG BUILDING
BMS BUILDING MANAGEMENT SYSTEM
BYP BYPASS
C CONDUIT
CAB CABINET
CALC CALCULATED
CAP CAPACITY
CAT CATALOG, CATEGORY
CATV COMMUNITY ANTENNA TELEVISION
CB CIRCUIT BREAKER
CCR CONTROL CONTACTOR
CCT CORRELATED COLOR TEMPERATURE
CCTV CLOSED CIRCUIT TELEVISION
cd CANDELA
CD CONSTRUCTION DOCUMENTS
CF CONTRACTOR-FURNISHED
CKT CIRCUIT
CLG CEILING
CO CONTRACTING OFFICER
COAX COAXIAL CABLE
COMM COMMUNICATION
CONN CONNECTION
CONST CONSTRUCTION
CONT CONTINUATION OR CONTINUOUS
CONTR CONTRACTOR
COORD COORDINATE
COR CONTRACTING OFFICER'S
REPRESENTATIVE
CPT CONTROL POWER TRANSFORMER
CRI COLOR RENDERING INDEX
CT CURRENT TRANSFORMER
CTV CABLE TELEVISION
CTR CENTER
CU COPPER
CU FT CUBIC FEET
D DEMOLITION
dB DECIBEL
DB DIRECT BURIAL
DC DIRECT CURRENT
DEG C DEGREES CELSIUS
DEG F DEGREES FAHRENHEIT
DEMO DEMOLISH/DEMOLITION
DEPT DEPARTMENT
DIA DIAMETER
DISC DISCONNECT
DIST DISTRIBUTION
DN DOWN
DS SAFETY DISCONNECT SWITCH
DT DOUBLE THROW
DWG DRAWING
EC ELECTRICAL CONTRACTOR
EG EQUIPMENT GROUND
ELEC ELECTRIC, ELECTRICAL
ELEV ELEVATOR
EM EMERGENCY
EMI ELECTROMAGNETIC INTERFERENCE
EMS ENERGY MANAGEMENT SYSTEM
EMT ELECTRICAL METALLIC TUBING
EPO EMERGENCY POWER OFF
EQUIP EQUIPMENT
ESMT EASEMENT
ETR EXISTING TO REMAIN
EWC ELECTRIC WATER COOLER
EWH ELECTRIC WALL HEATER
ELECTRIC WATER HEATER
EX EXISTING
EXP EXPLOSION PROOF
FA FIRE ALARM
FAAP FIRE ALARM ANNUNCIATOR PANEL
FACP FIRE ALARM CONTROL PANEL
FC FOOTCANDLE
FCU FAN COIL UNIT
FIXT FIXTURE
FLR FLOOR
FU FUSE
FUDS FUSED SAFETY DISCONNECT
SWITCH
FVR FULL VOLTAGE REVERSING
FVNR FULL VOLTAGE NON-REVERSING
GAL GALLON
GALV GALVANIZED
GC GENERAL CONTRACTOR
GEN GENERATOR
GFI GROUND FAULT CIRCUIT INTERRUPTER
GND GROUND
GRS GALVANIZED RIGID STEEL (CONDUIT)
GYP BD GYPSUM BOARD
HID HIGH-INTENSITY DISCHARGE
HOA HAND-OFF-AUTOMATIC
HP HORSEPOWER
HT HEIGHT
HTR HEATER
HV HIGH VOLTAGE
HVAC HEATING, VENTILATING AND AIR
CONDITIONING
IES ILLUMINATION ENGINEERING SOCIETY
IG ISOLATED GROUND
IMC INTERMEDIATE METAL CONDUIT
IR INFRARED
I/W INTERLOCK WITH
IWH INSTANTANEOUS WATER HEATER
J-BOX JUNCTION BOX
KV KILOVOLT
KVA KILOVOLT-AMPERE
KVAR KILOVOLT-AMPERE REACTIVE
KW KILOWATT
KWH KILOWATT HOUR
LED LIGHT-EMITTING DIODE
LF LINEAR FEET/FOOT
LM LUMEN
LRA LOCKED ROTOR AMPS
LT LIGHT
LTG LIGHTING
LTNG LIGHTNING
LV LOW VOLTAGE
MATV MASTER ANTENNA TELEVISION SYSTEM
MAX MAXIMUM
MC MECHANICAL CONTRACTOR
METAL-CLAD (CONDUIT)
MCA MINIMUM CIRCUIT AMPACITY
MCB MAIN CIRCUIT BREAKER
MCC MOTOR CONTROL CENTER
MDP MAIN DISTRIBUTION PANEL
MECH MECHANICAL
MFR MANUFACTURER
MFS MAIN FUSED DISCONNECT SWITCH
MH MANHOLE
MIC MICROPHONE
MIN MINIMUM
MISC MISCELLANEOUS
MLO MAIN LUGS ONLY
MOA MULTIOUTLET ASSEMBLY
MSBD MAIN SWITCHBOARD
MT MOUNT
A1 b
E1 c d
T1
'LPN'
THE LIGHTING FIXTURE TYPE IS INDICATED BY AN UPPER CASE LETTER OR AN UPPER
CASE LETTER AND NUMBER.
THE SWITCH DESIGNATION (IF NEEDED) IS INDICATED BY A LOWER CASE LETTER.
EXAMPLE: LIGHTING FIXTURE TYPE 'A1' IS CONTROLLED BY SWITCH 'b'.
EXIT SIGNS: STEM INDICATES WALL MOUNTING. NO STEM INDICATES CEILING
MOUNTING. SHADED AREA INDICATES ILLUMINATED FACE(S). ARROW INDICATES
DIRECTIONAL ARROW ON ILLUMINATED FACE(S).
DEVICES: THE SWITCH DESIGNATION IS INDICATED BY A LOWER CASE LETTER.
THE CONTROL DEVICE DESIGNATION IS INDICATED BY A LOWER CASE LETTER.
TRANSFORMERS: THE TRANSFORMER TYPE IS INDICATED BY A NUMBER
FOLLOWING THE UPPER CASE LETTER 'T'. SEE THE TRANSFORMER SCHEDULE OR
THE SINGLE LINE DIAGRAM FOR THE TRANSFORMER DESCRIPTION AND
REQUIREMENTS.
PANELBOARDS: PANELBOARD DOORS MAY BE SHOWN TO INDICATE OPENING
SIDE OF RECESSED PANELBOARDS. SEE PANELBOARD IDENTIFICATION FOR
DESIGNATION CODES.
SHEET KEY NOTE: SEE THE SHEET KEY NOTES ON THAT SHEET FOR THE NOTE
NUMBER INDICATED IN THE HEXAGON.
HOME RUN TO BRANCH CIRCUIT PANEL: THE PANEL DESIGNATION AND CIRCUIT
DESIGNATION ARE SHOWN ADJACENT TO THE HOME RUN ARROW.
CIRCUIT BREAKER SIZES (AMPS/NUMBER OF POLES) ARE SHOWN IN THE PANEL
SCHEDULE WITH THE CORRESPONDING PANEL AND CIRCUIT DESIGNATION.
SYMBOL NOTATIONS: UPPER CASE LETTERS ADJACENT TO SYMBOLS INDICATE
A UNIT TYPE. SEE APPROPRIATE SCHEDULE OR SPECIFICATIONS.
'LPN'-1,3,5
EXAMPLE 1: WALL MOUNTED EXIT SIGN TYPE 'E1' WITH SINGLE FACE
AND DIRECTIONAL ARROW.
EXAMPLE 2: CEILING MOUNTED EXIT SIGN TYPE 'E2' WITH DOUBLE
FACE AND DIRECTIONAL ARROWS.E2
EXAMPLE: SPLIT DUPLEX RECEPTACLE; ONE RECEPTACLE OUTLET IS
CONTROLLED BY SWITCH 'c'.
EXAMPLE: SINGLE POLE SWITCH 'd' TO CONTROL LIGHTING FIXTURES INDICATED BY 'd'.
EXAMPLE: TRANSFORMER TYPE 'T1'.
EXAMPLE: HOME RUN TO PANELBOARD 'LPN'; CIRCUITS 1, 3, 5.
DEMOLITION KEY NOTE: SEE THE SHEET KEY NOTES ON THAT SHEET FOR THE
NOTE NUMBER INDICATED IN THE SQUARE.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
ALL ELECTRICAL DEVICES, FIXTURES, EQUIPMENT AND FEEDERS SHALL BE INSTALLED IN ACCORDANCE WITH THE PROJECT SPECIFICATIONS, THE MANUFACTURER'S RECOMMENDED PROCEDURES, ALL APPLICABLE LOCAL AND STATE CODES, AMERICANS WITH DISABILITIES ACT AND WITH THE…