C21AvionicsUpgrade_Request_for_Information-Contractor_Questions.docx

DOCX document 15 KB Posted

Attached to
C-21 AUP RFP Federal contract opportunity
Solicitation number
C21AvionicsUpgrade
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Tinker Air Force Base

View the file

Other files for this federal contract opportunity

Other files attached to C-21 AUP RFP, newest first.
File Type Posted
Amended_RFP_Questions_2_May_16.docx DOCX document
FA810616R0003_______0002.pdf PDF
RFP_Answer_18_May_16.docx DOCX document
RFP_Questions_17_May_16.docx DOCX document
RFP_Questions_2_May_16.docx DOCX document
Attachment_4_C-21_AUP_FAR_52.212-1_Addendum_dated_4_May_16.doc DOC document
FA810616R0003_______0001.pdf PDF
Draft_RFP_Contractor_Questions_18_Apr_2016.docx DOCX document
Attachment_6_Scheduled_GFP.pdf PDF
Attachment_2_C-21_AUP_STATEMENT_OF_OBJECTIVES_dated_11_Apr_16.docx DOCX document
Attachment_5_C-21_AUP_FAR52.212-2_Addendum.doc DOC document
Attachment_4_C-21_AUP_FAR_52.212-1_Adendum.doc DOC document
FA810616R0003.pdf PDF
Attachment_1-_C-21_Pricing_Matrix_Protected_28_Mar_16.xlsx XLSX spreadsheet
Attachment_3_C-21AUP_SRD_dated_7_Apr_16.docx DOCX document
EXPORT_CONTROLLED 1 .pdf PDF
Tech_Data_Access_Request.docx DOCX document
dd2345.pdf PDF
FA810616R0003.pdf PDF
Attachment_5_C-21_AUP_FAR52.212-2_Adendum.doc DOC document
Attachment_4_C-21_AUP_FAR_52.212-1_Adendum.doc DOC document
Attachment_1-C-21_Pricing_Matrix_Protected_8_Jan_16.xlsx XLSX spreadsheet
C-21_AUP_LIST_OF_DOCUMENTS.docx DOCX document
Attachment_2_C-21_AUP_STATEMENT_OF_OBJECTIVES_dated_16_Nov_15.docx DOCX document
Attachment_3_C-21AUP_SRD_dated17Dec15.docx DOCX document
C21A_Equipment_list_Oct_15_(2).xls XLS spreadsheet
Industry_Day_Questions_Nov_2015.pdf PDF
C-21_Avionics_Upgrade_Industry_Day_6-7_Oct_15.pptx PPTX presentation
C-21_Industry_Day_Sign_in_Sheet.pdf PDF
C-21_AUP_Requirements_Document_22_Sep_15.docx DOCX document
Notice_of_Industry_Dayr1.docx DOCX document
C21AvionicsUpgrade_Request_for_Information-Contractor_Questions_4.docx DOCX document
C21AvionicsUpgrade_Request_for_Information-Contractor_Questions_3.docx DOCX document
Updated_Navigation_System_List.docx DOCX document
C-21_Instrument_Panel_PDF.pdf PDF
C21AvionicsUpgrade_Request_for_Information-Contractor_Questions_2.docx DOCX document
Navigation_System_List.docx DOCX document
RFI_on_Avionics_Communication_Suite_Upgrade_on_C-21A_Aircraft.pdf PDF
Show all 38

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

C21AvionicsUpgrade Request for Information Contractor Questions

1. Is there a repair station requirement?

Answer: Yes, work must be performed at a FAR Part 145 Repair Station with appropriate ratings for the work being performed.

1. What are the security requirements?

Answer: Security requirement per commercial contract and FAA certified facility/airfield requirements.

1. Are there any special personnel qualifications required?

Answer: IAW FAR Part 145 Repair Station Requirements.

1. Will the contractor be required to operate under DCMA 8210 guidelines and DCMA/GFR oversight?

Answer: DCMA quality assurance oversight required.

5. Are there any AS9102 requirements above the STC?

Answer: Yes, ISO certification required.

6. Are the aircraft in a standard configuration?

Answer: Yes, the aircraft are in a standard configuration.

7. What aircraft maintenance is expected above the avionics upgrade?

Answer: Over and Above maintenance related to the avionics upgrade, safety of flight, receive and launch aircraft, pre/post flight requirements. Also includes STC maintainability to include any SBs or ADS issued against the items.