C12_Att_08-Bid_Form.xlsx

XLSX spreadsheet 23 KB Posted

Attached to
Bldg 38 / 233 Emergency Eyewash Stations to be Installed
Solicitation number
N0025325Q0015
Issued by

About this file

The file is a Bid Form for Solicitation Number N0025325Q0015, detailing a construction project for installing emergency eyewash stations at Naval Base Kitsap in Keyport, WA. The solicitation, issued by the Department of the Navy Naval Sea Systems Command, seeks a small business contractor to install two emergency eyewash stations in Buildings 38 and 233, with specific requirements including tepid water configuration (60-100°F), piping modifications, valve installations, and complete system integration.

The bid form provides a template for contractors to itemize costs, including labor, materials, equipment, and other project-related expenses. The government estimates the project value between $30,000 and $75,000, with a target award date of August 15, 2025. The solicitation is 100% set aside for small businesses, uses the NAICS code 238220 (Plumbing, Heating, and Air-Conditioning Contractors), and will be evaluated using Low Price Technically Acceptable criteria. A mandatory site visit is scheduled for July 17, 2025, and contractors must be registered in the System for Award Management (SAM) database to be eligible.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Form

Bid Form Solicitation Number:N0025325Q0015Contractor:
PID Description:Date:
Project Location:Naval Base Kitsap, Keyport, WA
Note:Refer to Statement of Work
Instructions:Contractor to complete for all items required. Description should be sufficient to allow for technical and price evaluation in accordance with Section L instructions. Example rows are provided for guidance only to demonstrate the expected level of detail and should be deleted by contractor prior to completion.

Please leave all formulas utilized in calculating totals as formulas, rather than hard entering numbers in the "total" cells.

CLIN 0001 - Base BidQuantityUnitUnit RateMaterial TotalLabor TotalEquipment TotalLine Item Total
0
ITEMDESCRIPTION OF TASKS
A (example)Air Handler1Unit$1,000.00$1,000.00$1,000.00
A (example)Labor to Install Air Handler: HVAC Tech15Hrs$65.00$975.00$975.00
A (example)Labor to Install Air Handler: Electrician3Hrs$85.00$255.00$255.00
A (example)Misc. Materials to install Air Handler (piping, ducting, electrical supplies, etc)1Lot$250.00$250.00$250.00
A (example)Equipment (scissor lift)2day$100.00$200.00$200.00
B (example)Site mobilization/demobilization$0.00
B (example)Labor for site mob/demob: General Laborer15Hrs$45.00$675.00$675.00
B (example)Labor for site mob/demob: SSHO2Hrs$85.00$170.00$170.00
B (example)Equipment (Truck and Trailer to haul air handler and materials to job site)1day$450.00$450.00$450.00
B (example)Equipment (dump trailer for debris haul off)2day$250.00$500.00$500.00
1
2
3
4
5
6
7
8
9
10
11
12
13
14<OFFEROR TO INSERT ROWS AS NECESSARY>
Subcontractor Performance Value
Prime Contractor & Project Management Costs
Subtotal
General Home Office Overhead (%)
General Field Overhead (%)
General and Administrative (%)
Profit (%)
Bond
CLIN 0001 Firm Fixed Price Proposal Amount