C12_Att_08_Bid_Form.xlsx

XLSX spreadsheet 26 KB Posted

Attached to
Bldg 81 Repair Awning Federal contract opportunity
Solicitation number
N0025325Q0013
Issued by
Department of the Navy Naval Sea Systems Command

About this file

The file is a Bid Form for Solicitation Number N00253, associated with a Naval Base Keyport, Washington project for Building 81 Awning Repair. The bid form provides a template for contractors to detail their pricing, including line items for materials, labor, equipment, and associated costs. The form includes example entries demonstrating how to break down costs for tasks such as air handler installation, with columns for quantity, unit rates, material costs, labor costs, and equipment expenses.

The related federal contract opportunity involves replacing the existing 100' awning on Building 81's east side with two smaller awnings: one 6' deep by 12' long covering two doorways, and another 6' wide by 6' long covering one exterior doorway. The project requires asbestos and lead abatement, removal of old piping/conduit, installation of new conduit and exterior lighting, and surface repairs and repainting. It is a small business set-aside with a government estimate between $35,000 and $75,000, targeting a September 3, 2025 award date, with the solicitation to be issued around June 19, 2025, under NAICS code 238190 and Product Service Code Z2AZ.

View the file

Other files for this federal contract opportunity

Other files attached to Bldg 81 Repair Awning, newest first.
File Type Posted
CUI Bldg. 81 Repair Awning Photos.pdf PDF
N0025325Q0013-00001.docx DOCX document
C11B_Att_02_WD_WA20250109_20250627.pdf PDF
C12_Att_01_-_Material_Equipment_In_Place_List.xlsx XLSX spreadsheet
C12_Att_06_Schedule_of_Values.xlsx XLSX spreadsheet
C11d_Att_07_Past_Performance_References.docx DOCX document
C12_Att_09_PPI_Form.docx DOCX document
25Q0013_Bldg81_RFQ.pdf PDF
C11B_Att_02_WD_WA20250109_20250307.pdf PDF
C12_Att_05_OPSEC_Guide_for_Defense_Contractors.pdf PDF
C12_Att_03_Safety_Requirements_for_Contractors_and_Subcontractors.pdf PDF
C12_Att_04_Kpt_EV_Guide_for_Contractors_Jan_2025.pdf PDF
C12_Att_10_Safety_Data_Sheet.docx DOCX document
C12_Att_11_OSHA_Calculating_Injury_and_Illness_Incident_Rate.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Form

Bid Form Solicitation Number:N00253<>Contractor:
PID Description:Date:
Project Location:Naval Base Kitsap, Keyport, WA
Note:Refer to Statement of Work
Instructions:Contractor to complete for all items required. Description should be sufficient to allow for technical and price evaluation in accordance with Section L instructions. Example rows are provided for guidance only to demonstrate the expected level of detail and should be deleted by contractor prior to completion.

Please leave all formulas utilized in calculating totals as formulas, rather than hard entering numbers in the "total" cells.

CLIN 0001 - Base BidQuantityUnitUnit RateMaterial TotalLabor TotalEquipment TotalLine Item Total
0
ITEMDESCRIPTION OF TASKS
A (example)Air Handler1Unit$1,000.00$1,000.00$1,000.00
A (example)Labor to Install Air Handler: HVAC Tech15Hrs$65.00$975.00$975.00
A (example)Labor to Install Air Handler: Electrician3Hrs$85.00$255.00$255.00
A (example)Misc. Materials to install Air Handler (piping, ducting, electrical supplies, etc)1Lot$250.00$250.00$250.00
A (example)Equipment (scissor lift)2day$100.00$200.00$200.00
B (example)Site mobilization/demobilization$0.00
B (example)Labor for site mob/demob: General Laborer15Hrs$45.00$675.00$675.00
B (example)Labor for site mob/demob: SSHO2Hrs$85.00$170.00$170.00
B (example)Equipment (Truck and Trailer to haul air handler and materials to job site)1day$450.00$450.00$450.00
B (example)Equipment (dump trailer for debris haul off)2day$250.00$500.00$500.00
1
2
3
4
5
6
7
8
9
10
11
12
13
14<OFFEROR TO INSERT ROWS AS NECESSARY>
Subcontractor Performance Value
Prime Contractor & Project Management Costs
Subtotal
General Home Office Overhead (%)
General Field Overhead (%)
General and Administrative (%)
Profit (%)
Bond
CLIN 0001 Firm Fixed Price Proposal Amount