C1 - Contractor Cost Workbook - Union HS.xlsx
XLSX spreadsheet 68 KB Posted
- Attached to
- CM - REQUEST FOR QUALIFICATIONS
- Solicitation number
- RFP GRP 270000000007 1
- Issued by
- Michigan
About this file
This is a Contractor Cost Workbook for construction management services related to a Union High School project in Grand Rapids Public Schools, Michigan. The project utilizes a Construction Manager as Constructor (CMc) delivery method with an estimated total construction cost of $5,326,740 and a building area of 264,800 square feet. The preconstruction phase is scheduled to begin on January 1, 2027, and conclude on November 15, 2027 (11 months, 45 weeks, 318 days), followed by a construction phase running from June 15, 2027, through August 5, 2028 (14 months, 60 weeks, 417 days). The workbook details staffing allocations, with a Senior Project Manager (Joe 'Example' Dirt) assigned at $10.00 per hour for 40 hours during both the preconstruction and construction phases.
The cost workbook indicates minimal general conditions expenses totaling $810, comprised of $400 in labor costs and $10 in permits and insurance costs, representing only 0.02% of the total construction cost. Personnel rate increases are limited to three percent annually after December 31, 2025, based on a 40-hour work week. The workbook notes that general liability insurance may only be applied to the Construction Manager's Fee and not the Cost of the Work. All staffing is managed under prevailing wage rules, with 40 preconstruction hours and 40 construction hours allocated. The document serves as a template cost proposal for the construction management services RFP issued by Grand Rapids Public Schools, prepared by Plante Moran Realpoint, LLC.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| GRPS CM RFQ 10.2026.pdf | ||
| C1 - Contractor Cost Workbook - Union HS Performing Arts.xlsx | XLSX spreadsheet | |
| C1 - Contractor Cost Workbook - Harrison Park.xlsx | XLSX spreadsheet | |
| C1 - Contractor Cost Workbook - Campus Elementary.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Summary
| CONTRACTOR COST WORKBOOK: | Union High School | ERROR:#REF! |
| NAME OF CM FIRM |
| ESTIMATED COST OF THE WORK: | $ 5,326,740 | |
| CONSTRUCTION DELIVERY METHOD: | CMc | Construction Manager as Constructor |
| Preconstruction | Construction | CMc | Construction Manager as Constructor | |||
| START DATE: | 1/1/27 | 6/15/27 | CMa | Construction Manager as Advisor | ||
| FINISH DATE: | 11/15/27 | 8/5/28 | DB | Design-Build, with GMP or Cost plus a Fee | ||
| GC | General Contractor, with GMP or Cost plus a Fee | |||||
| Months | Weeks | Days | TBD | To be Determined | ||
| PROJECT DURATION: | Pre-construction | 11 | 45 | 318 | ||
| Construction | 14 | 60 | 417 |
| ESTIMATED BUILDING AREA: | 264,800 | Sq. Ft. | |||||
| GENERAL CONDITIONS RECAP SUMMARY | |||||||
| EQ. & MATL. | LABOR | SUB-CON | TOTAL | ||||
| DESCRIPTION | TOTAL | TOTAL | TOTAL | COST | |||
| PRECONSTRUCTION SERVICES | $ - 0 | $ 400 | $ - 0 | $ 400 | |||
| PRECONSTRUCTION SERVICES REIMBURSABLE EXPENSES | $ - 0 | $ - 0 | $ - 0 | ||||
| CONSTRUCTION PERSONNEL | $ - 0 | $ 400 | $ - 0 | $ 400 | |||
| CM REIMBURSABLES | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| PERMITS, INSURANCE & TAXES | $ 10 | $ - 0 | $ - 0 | $ 10 |
TOTAL GENERAL CONDITIONS $ 10 $ 800 $ - 0 $ 810
| GENERAL CONDITIONS AS % OF CONSTRUCTION COST = | 0.02% |
| CONSTRUCTION MANAGER'S OVERHEAD & PROFIT (%) = |
| Voluntary Alternate Add: | $ - 0 | Project Managed Under Prevailing Wage Rules | ||
| Preconstruction Hours: | 40 | |||
| Construction Hours: | 40 |
| TOTAL ESTIMATED CONSTRUCTION SERVICES AS % OF CONSTRUCTION COST = | 0.02% | ||
| TOTAL ESTIMATED CONSTRUCTION SERVICES COST = | $ 810 | ||
| NOTES: | |||
| 1. Personnel rates include the salaries of personnel and the portion of the cost of their mandatory and customary contributions and benefits related thereto, such as employment taxes and other statutory employee benefits, insurance, sick leave, holidays, vacations, pensions, and similar contributions and benefits. |
2. Personnel rate increases are limited to three (3%) percent per year, after 12/31/2025. Hourly Rates shall be based on a forty (40) hour work week/salaried position and while the Construction Manager’s Personnel may work overtime, the Owner shall never be charged overtime rates.
3. General Liability Insurance may only be applied to Construction Manager’s Fee, and not the Cost of the Work
GRAND RAPIDS PUBLIC SCHOOLS
REQUEST FOR PROPOSAL (RFP) – CONSTRUCTION MANAGEMENT SERVICES
COST WORKBOOK
&"Helvetica,Regular"&8File Name = &F/&A Run Date = &D &"Helvetica,Regular"&8&P of &N &"Helvetica,Regular"&8Intellectual Property of Plante Moran Realpoint, LLC
Staff Hours
| NAME OF CM FIRM | 0 | ||||||||||||||||||||||||||||||||||||||||
| Populate all staff and associated rates you intend to charge to the project. Add any staff you intend to charge. | |||||||||||||||||||||||||||||||||||||||||
| SUMMARY OF STAFF HOURS | |||||||||||||||||||||||||||||||||||||||||
| Project Month (Overall) | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | |
| 2024 | 2025 | 2026 | 2027 | ||||||||||||||||||||||||||||||||||||||
| Jul-24 | Aug-24 | Sep-24 | Oct-24 | Nov-24 | Dec-24 | Jan-25 | Feb-25 | Mar-25 | Apr-25 | May-25 | Jun-25 | Jul-25 | Aug-25 | Sep-25 | Oct-25 | Nov-25 | Dec-25 | Jan-26 | Feb-26 | Mar-26 | Apr-26 | May-26 | Jun-26 | Jul-26 | Aug-26 | Sep-26 | Oct-26 | Nov-26 | Dec-26 | Jan-27 | Feb-27 | Mar-27 | Apr-27 | May-27 | Jun-27 | Jul-27 | Aug-27 | Sep-27 | Oct-27 |
| Pre-Construction Phase Project Hours | Pre-Construction | |||||||||||||||||||||||||||||||||||||||||||
| Personnel/Name | Function | Hourly Rate | Hours | Cost | ||||||||||||||||||||||||||||||||||||||||
| Project Exec. | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Joe 'Example' Dirt | Sr. Proj. Mgr. | $ 10.00 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 40 | $ 400 |
| Proj. Mgr. 1 | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Pre-Con Mgr. | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Sr. Estimator | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Estimator 1 | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Mech. Est. | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Elect. Est. | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Scheduler | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Proj. Supt. | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Accountant | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Admin. Asst. | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| $ - 0 | - 0 | $ - 0 | ||||||||||||||||||||||||||||||||||||||||||
| $ - 0 | - 0 | $ - 0 | ||||||||||||||||||||||||||||||||||||||||||
| $ - 0 | - 0 | $ - 0 | ||||||||||||||||||||||||||||||||||||||||||
| $ - 0 | - 0 | $ - 0 | ||||||||||||||||||||||||||||||||||||||||||
| $ - 0 | - 0 | $ - 0 | ||||||||||||||||||||||||||||||||||||||||||
| Pre-Construction Hours: | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 40 | $ 400 | ||
| Construction Months | ||||||||||||||||||||||||||||||||||||||||||||
| Construction Phase Project Hours | Construction | |||||||||||||||||||||||||||||||||||||||||||
| Personnel/Name | Function | Hourly Rate | Hours | Cost | ||||||||||||||||||||||||||||||||||||||||
| Project Exec. | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Joe 'Example' Dirt | Sr. Proj. Mgr. | $ 10.00 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 40 | $ 400 |
| Proj. Mgr. 1 | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Proj. Mgr. 2 | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Proj. Mgr. 3 | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Proj. Mgr. 4 | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Proj. Engr. 1 | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Proj. Engr. 2 | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Proj. Engr. 3 | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Proj. Engr. 4 | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Safety Engr. | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| General Supt. | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Proj. Supt. 1 | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Proj. Supt. 2 | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Proj. Supt. 3 | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Proj. Supt. 4 | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Accountant | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Admin. Asst. | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| Expeditor | $ - 0 | - 0 | $ - 0 | |||||||||||||||||||||||||||||||||||||||||
| $ - 0 | - 0 | $ - 0 | ||||||||||||||||||||||||||||||||||||||||||
| $ - 0 | - 0 | $ - 0 | ||||||||||||||||||||||||||||||||||||||||||
| $ - 0 | - 0 | $ - 0 | ||||||||||||||||||||||||||||||||||||||||||
| $ - 0 | - 0 | $ - 0 | ||||||||||||||||||||||||||||||||||||||||||
| Construction Hours: | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 40 | $ 400 |
&"Verdana,Regular"&8File Name=&F/&A Date=&D &"Verdana,Regular"&8&P of &N &"Verdana,Regular"&8Intellectual Property of
Construction Support
NAME OF CM FIRM 0
| Preconstruction | Construction | |
| START DATE: | 1/1/27 | 6/15/27 |
| FINISH DATE: | 11/15/27 | 8/5/28 |
| Populate all categories you intend to charge to the project. Add any other costs you intend to charge. | ||||
| Months | Weeks | Days | ||
| PROJECT DURATION: | Pre-construction | 11 | 45 | 318 |
| Construction | 14 | 60 | 417 |
| CODE | DESCRIPTION | QTY. | UNIT | UNIT | (E) EQUIP. & | (S) SUB- | TOTAL | |
| NO. | PRICE | MAT'L | (L) LABOR | CONTRACTOR | COST |
CM REIMBURSABLES
| E | TEMPORARY TOILETS - 1 | MO | $ - 0 | $ - 0 | $ - 0 | $ - 0 | TRUE |
| E | TEMPORARY TOILETS - 2 | MO | $ - 0 | $ - 0 | $ - 0 | $ - 0 | TRUE |
| DUMPSTERS | LS | $ - 0 | $ - 0 | $ - 0 | $ - 0 | TRUE | |
| TEMPORARY FENCE | MO | $ - 0 | $ - 0 | $ - 0 | $ - 0 | TRUE | |
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | TRUE | |||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | TRUE | |||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | TRUE | |||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | TRUE | |||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | TRUE | |||
| $ - 0 | $ - 0 | $ - 0 | $ - 0 | TRUE |
CM REIMBURSABLES TOTAL $ - 0 $ - 0 $ - 0 $ - 0
PERMITS, INSURANCE & TAXES
| E | BUILDING PERMIT | 1.0 | LS | $ 10.00 | $ 10 | $ - 0 | $ - 0 | $ 10 | TRUE |
| E | SPECIAL PERMITS | LS | $ - 0 | $ - 0 | $ - 0 | $ - 0 | TRUE | ||
| E | SPECIAL FEES | LS | $ - 0 | $ - 0 | $ - 0 | $ - 0 | TRUE | ||
| E | SITE PLAN REVIEW | LS | $ - 0 | $ - 0 | $ - 0 | $ - 0 | TRUE | ||
| E | BUILDERS RISK INSURANCE | LS | $ - 0 | $ - 0 | $ - 0 | $ - 0 | TRUE | ||
| 100% PLM Bond | % | $ - 0 | $ - 0 | $ - 0 | $ - 0 | TRUE | |||
| E | GENERAL LIABILITY INSURANCE | LS | $ - 0 | $ - 0 | $ - 0 | $ - 0 | TRUE |
| PERMITS, INSURANCE & TAXES TOTAL | $ 10 | $ - 0 | $ - 0 | $ 10 | ||
| SUMMARY & ERROR CHECK | ||||||
| LABOR SUBTOTAL: | $ - 0 | TRUE | ||||
| TOTAL: | $ 10.00 | FALSE |
&"Helvetica,Regular"&8File Name = &F/&A Run Date = &D &"Helvetica,Regular"&8&P of &N &"Helvetica,Regular"&8Intellectual Property of
Staff Cashflow
NAME OF CM FIRM 0
| STAFFING CASHFLOW | |||||||||||||||||||||||||
| Project Month (Overall) | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 |
| 2024 | 2025 | ||||||||||||||||||||||||
| Jan-24 | Feb-24 | Mar-24 | Apr-24 | May-24 | Jun-24 | Jul-24 | Aug-24 | Sep-24 | Oct-24 | Nov-24 | Dec-24 | Jan-25 | Feb-25 | Mar-25 |
| Pre-Construction Phase Project Hours | Pre-Construction | ||||||||||||||||||||||||||||
| Personnel | Function | Hrly Rate | Hours | Cost | |||||||||||||||||||||||||
| 0 | Project Exec. | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 0 | $ - 0 |
| Joe 'Example' Dirt | Sr. Proj. Mgr. | $ 10.00 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 40 | $ 400 |
| 0 | Proj. Mgr. 1 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 0 | $ - 0 |
| 0 | Pre-Con Mgr. | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 0 | $ - 0 |
| 0 | Sr. Estimator | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 0 | $ - 0 |
| 0 | Estimator 1 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 0 | $ - 0 |
| 0 | Mech. Est. | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 0 | $ - 0 |
| 0 | Elect. Est. | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 0 | $ - 0 |
| 0 | Scheduler | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 0 | $ - 0 |
| 0 | Proj. Supt. | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 0 | $ - 0 |
| 0 | Accountant | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 0 | $ - 0 |
| 0 | Admin. Asst. | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 0 | $ - 0 |
| 0 | 0 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 0 | $ - 0 |
| 0 | 0 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 0 | $ - 0 |
| 0 | 0 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 0 | $ - 0 |
| 0 | 0 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 0 | $ - 0 |
| 0 | 0 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | 0 | $ - 0 |
| Pre-Con Staff Costs: | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 40 | $ 400 |
| Construction Months | |||||||||||||||||||||||||||||
| Construction Phase Project Hours | Construction | ||||||||||||||||||||||||||||
| Personnel | Function | Hrly Rate | Hours | Cost | |||||||||||||||||||||||||
| 0 | Project Exec. | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| Joe 'Example' Dirt | Sr. Proj. Mgr. | $ 10.00 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 40 | $ 400 |
| 0 | Proj. Mgr. 1 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | Proj. Mgr. 2 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | Proj. Mgr. 3 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | Proj. Mgr. 4 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | Proj. Engr. 1 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | Proj. Engr. 2 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | Proj. Engr. 3 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | Proj. Engr. 4 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | Safety Engr. | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | General Supt. | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | Proj. Supt. 1 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | Proj. Supt. 2 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | Proj. Supt. 3 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | Proj. Supt. 4 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | Accountant | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | Admin. Asst. | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | Expeditor | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | 0 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | 0 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | 0 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| 0 | 0 | $ - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | - 0 | $ - 0 |
| Construction Staff Costs: | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 40 | $ 400 |
Staff Cost Cashflow: 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 80 800
&"Verdana,Regular"&8File Name=&F/&A Date=&D &"Verdana,Regular"&8&P of &N &"Verdana,Regular"&8Intellectual Property of
File details come from the government source that posted it. Updated .