This document is Addendum No. One for the Hemlock Filtration Plant HVAC Upgrades project issued by the City of Rochester's Department of Environmental Services, Bureau of Architecture and Engineering. The addendum provides instructions to bidders regarding the New York State Public Work Contractor and Subcontractor Registry, specifically noting that starting December 30, 2024, all contractors and subcontractors submitting bids or performing construction work on public projects must be registered with the New York State Department of Labor. The addendum requires bidders to replace specific pages in the contract documents, sign and date the addendum, and return it with their bid proposal. The bid is for HVAC upgrades at the Hemlock Filtration Plant, with project number 21009 and bid number C07230.
The addendum includes a comprehensive bid proposal submissions checklist that outlines required documentation, including apprenticeship agreements, workforce goal certifications, bid bonds, and subcontractor data. Bidders must meet specific requirements, such as performing a minimum of 20% of contract work with their own organization and meeting workforce goals of 20% minority and 6.9% women participation. The project includes upgrading HVAC equipment for lab space, involving roof-mounted chiller replacement, fume hood updates, fan coil unit replacements, exhaust fan updates, and LED lighting fixture installations. The total project estimate is $1,164,656, with the contract to be divided into three lump sum contracts: General Construction, Mechanical Contractor, and Electrical Contractor.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 21009 Bid Set - Project Manual.pdf | ||
| 21009 Bid Set - Proposal Section.pdf | ||
| 21009 Bid Set - Stamped Drawings.pdf | ||
| C07230 ADD #2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID PROPOSAL SUBMISSIONS CHECKLIST
Complete and sign this checklist to verify that all required submissions are attached to the Bid.
An incomplete bid package that is missing the required forms will be declared informal and will not be considered for award.
No required apprenticeship material will be accepted after Bids have been opened.
Included Item Notes
_____ Bid Proposal
_____ Addenda issued for the Bid Sign and date each addendum issued for this Bid
OR
OR
Bidder’s Apprenticeship Agreement(s)
Bid plus add alternates does not exceed $250,000
OR (multiple may be checked)
Bid plus add alternates exceeds $250,000
_____ AT-10 form(s) of Bidder attached
_____ AP3 form(s) of Bidder attached, if needed
_____ AP1.1 form
_____ Subcontractor AT-10 and AP3, if needed, for Subcontractors proposed for each subcontract that exceeds $100,000
AP1.2 Apprenticeship Waiver Request Form and supporting documentation submitted with bid.
OR
_____ Write “NONE” in Subcontractor data area if no subcontract greater than $100,000 is proposed; and Submit Form
Required if Bid is greater than $250,000 See Special Instructions for Bidders SIB 9 and SLR 17 for details
New York State Department of Labor Form AT-10 for program sponsor
City of Rochester Form AP3 if Bidder is not the program sponsor
New York State Department of Labor Form AT-10 for program sponsor and City of Rochester Form AP3 if Subcontractors are not the program sponsor
City of Rochester Form AP1.2 required for Apprenticeship Agreement waiver(s) to be considered.
Subcontractor AT-10 and AP3 Forms are only required with this proposal if the Bid plus add alternates exceeds $250,000
_____ Contract Work Certification
The Bidder certifies understanding of and commitment that a minimum of 20% of the contract work must be performed by the Bidder’s own organization as required by SIB 6
_____ Workforce Goals Certification
The Bidder certifies understanding of and commitment to meet the 20% M and 6.9% W workforce goals incorporated in this contract per SIB 9 and SLR 20
(Page 1 of 2 – continued on Page ADD1-2)
ADD 1 - 1
ADD 1 - 2
(Page 2 of 2 – continued from Page ADD1-1)
_____ Incentive Program Payment The Bidder expects to apply for the Incentive Program Payments upon completion of the project per SIB 15 and SLR 18 (check if Yes)
_____ Bid Bond Submit Bid Bond - not required for bids less than
$100,000 (page P-8)
Apprenticeship Forms AP1.1, AP1.2 if required and AP3
Complete forms, sign and date (pages P-11 thru P-
16)
_____ MWBE Form P.1 and P.2, if required
Submit MWBE PARTICIPATION PLAN, pages 1 and
2, and page 3 if required per SIB 9 and SLR 19
(pages P-18 thru P-22)
_____ Consultant/Contractor Information Form Complete form (pages P-23 thru P-24)
_____ “Subcontractor Data”
Sealed Envelope A separate sealed envelope with a list of subcontractors and contract amount(s) (GC, M, E, and/or P as applicable) for NY State Wicks Law. Refer to Section SIB 16 for details).
_____ NYS DOL Public Work Contractor Registry Documentation of registry with the New York State Public Work Contractor Registry (https://dol.ny.gov/contractor-and-subcontractor-registry-landing)
I am an authorized representative for the Bidder named below. The Bidder understands that its Bid may be deemed informal and not considered for contract award by the City if the information required above is not submitted with the Bid
Signature: ____________________________________________ Corporate Seal:
Signed By (print): ______________________________________
Title: ________________________________ Date: __________
Hemlock Filtration Plant HVAC Upgrades City Project No. 21009
DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC 230923 - Page 10 of 65
1.8 WARRANTY
A. Special Warranty: Manufacturer and Installer agree to repair or replace products that fail in materials or workmanship within specified warranty period.
1. Adjust, repair, or replace failures at no additional cost or reduction in service to Owner.
2. Include updates or upgrades to software and firmware if necessary to resolve deficiencies.
a. Install updates only after receiving Owner's written authorization.
3. Perform warranty service during normal business hours and commence within 8 hours of
Owner's warranty service request.
4. Warranty Period: Two year(s) from date of Substantial Completion.
a. For Gateway: Two-year parts and labor warranty for each.
PART 2 - PRODUCTS
2.1 DIRECT DIGITAL CONTROL (DDC) SYSTEM FOR HVAC
A. Manufacturers: Provide the Basis-Of-Design indicated, or an equivalent product by one of the following:
1. Basis-Of-Design: Johnson Controls Inc. (JCI).
2. Trane.
3. Schneider Electric, EcoStruxure.
4. Automated Logic.
2.2 DDC SYSTEM DESCRIPTION
A. Microprocessor-based monitoring and control including analog/digital conversion and program logic. A control loop or subsystem in which digital and analog information is received and processed by a microprocessor, and digital control signals are generated based on control algorithms and transmitted to field devices to achieve a set of predefined conditions.
1. DDC system consisting of high-speed, peer-to-peer network of distributed DDC controllers, other network devices, operator interfaces, and software.
B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.
2.3 WEB ACCESS
A. DDC system to be web compatible.
1. Web-Based Access to DDC System:
SS-260
ADD 1 - 3
| 011000 FL - Summary |
| 011200 FL - Multiple Contract Summary |
| 013300 FL - Submittal Procedures |
| 014000 FL - Quality Requirements |
| 015000 FL - Temporary Facilities and Controls |
| 017300 FL - Execution |
| 017419 FL - Construction Waste Management and Disposal |
| 017700 FL - Closeout Procedures |
| 017823 FL - Operation and Maintenance Data |
| 017839 FL - Project Record Documents |
| 017900 FL - Demonstration and Training |
| 019113 General Commissioning Requirements |