C05_04_140R2024Q0125_Solicitation_Shasta_TCD_Hanger_Rod_Replacement.pdf

PDF 2 MB Posted

Attached to
NCAO SHASTA DAM TCD HANGER ROD INSTALLATION
Solicitation number
140R2024Q0125
Issued by

About this file

This document is a solicitation for a contract to replace the left side, upstream hanger rod assembly on the Shasta Dam Temperature Control Device (TCD) located at Shasta Dam in California. The work includes removing the existing temporary hanger rod assembly and installing a new government-furnished replacement assembly. The estimated price range is $100,000 to $250,000, and the contract is set aside for small businesses under NAICS code 237990. Performance is required within 30 calendar days after the contractor receives the notice to proceed, with potential liquidated damages of $600 per day for late completion. The solicitation includes detailed requirements for the contractor's submittals, safety program, coatings, and quality control testing, as well as government security requirements. Drawings and specifications are provided to support the statement of work.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No.140R2024Q0125

Shasta Dam Temperature Control Device Hanger Rod Installation

Northern California Area Office (NCAO)

This page intentionally left blank.

TABLE OF CONTENTS

SECTION A - Solicitation, Offer and Award Form (SF 1442)

SECTION B - Pricing Schedule

SECTION C - Statement of Work

SECTION D - Packaging and Marking

SECTION E - Inspection and Acceptance

SECTION F - Deliveries or Performance

SECTION G - Contract Administration Data

SECTION H - Special Contract Requirements

SECTION I - Contract Clauses

SECTION J - List of Documents, Exhibits, and Other Attachments

SECTION K - Representations, Certifications and Other Statements of Offerors

SECTION L - Instructions, Conditions and Notices to Offerors

SECTION M - Evaluation Factors for Award

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION CALL

a. NAME

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

0040661203

Bureau of Reclamation

Mid-Pacific Region

Regional Office Division of Acquisition Services

R20

2800 Cottage Way, Room E-1815

Sacramento CA 95825-1898

8. ADDRESS OFFER TO

Bureau of Reclamation - Interior Region 10

2800 Cottage Way, Rm. E-1815

Sacramento, CA 95825-1898 rgamo@usbr.gov

Ronald Gamo

b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

(916)978-4304

108/07/2024

140R2024Q0125

INVITATION FOR BID

REQUEST FOR PROPOSAL

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

A. Shasta Dam Temperature Control Device Hanger Rod Installation

B. Work Site Location: Work is located at the Shasta Dam, Shasta, CA.

C. Estimated Price Range: $100,000.00 to $250,000.00.

D. Set-aside Information: This requirement is being procured as a Total Small business set-aside under the Simplified Acquisition Procedures, Federal Acquisition Regulation (FAR) Part 13. NAICS Code: 237990 and applicable size standard $45 million.

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

7 30 calendar days and complete it within ________________ ________________ calendar days after receiving

Section F

09/06/2024

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 12/2022)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d) x

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

Bureau of Reclamation Mid-Pacific Region

Regional Office Division of Acquisition Services

R20

2800 Cottage Way, Room E-1815

Sacramento CA 95825-1898

Abelardo Lopez

28. NEGOTIATED AGREEMENT 29. AWARD

and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

10 U.S.C. 3204(a) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 12/2022) BACK

Continued...

and return

(Contractor is not required to sign this document.) Your offer on this

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140R2024Q0125

00010

Section B - Supplies and Services and Prices "AU" - Activity Unit is used solely for the purpose of allowing progress payments under the Department of Interior's Financial Business System (FBMS)

Shasta Dam TCD Hanger Installation

Pricing Schedule: CLINS 1-3

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

1 AU

Shasta Dam Temperature Control Device Hanger Rod Installation Solicitation No. 140R2024Q0125

Shasta, California

Price Schedule

B - 1

CONTINUATION OF

SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

Shasta Dam Temperature Control Device Hanger Rod Installation

B.1 PRICE SCHEDULES

(a) Quotes will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.

(b) Quotes are subject to the terms and conditions of this solicitation.

(c) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory

Work, for CLIN 0010.

B.2 DEFINITIONS

(a) CLIN – Contract Line Item Number.

CLIN Section Supplies or Services Quantity and Unit

Unit

Price

Amount

0010 WBR

1452.232-81

Mobilization

& Preparation

For the lump sum of $

0020 C-SOW Removal of Existing

Hanger Rod Assemblies For the lump sum of $

0030 C-SOW Installation of New Hanger

Rod Assemblies For the lump sum of $

TOTAL FOR PRICE SCHEDULE $ ______________

Shasta Dam Temperature Control Device Hanger Rod Installation Solicitation No. 140R2024Q0125

Shasta, California

Price Schedule

B - 2

B.2. Provision:

WBR 1452.236-85 INSTRUCTION FOR MOBILIZATION AND MAR 2022

PREPARATORY WORK SCHEDULE LINE

ITEM – BUREAU OF RECLAMATION

The Contracting Officer estimates that the Section B Mobilization and Preparatory Work schedule line item should not exceed 10 percent of the total bid price. Your attention is directed to contract clause WBR 1452.232-81 Payment for Mobilization and Preparatory Work, which reflects how the Government will pay for this line item, including how payment will be made when the price bid for this schedule line item is higher than the percentage stated herein.

END OF SUPPLIES OR SERVICES AND PRICES

Shasta Dam Temperature Control Device

Shasta Hanger Rod Installation Solicitation No.140R2024Q0125

Statement of Work - 1

STATEMENT OF WORK

SHASTA DAM TEMPERATURE CONTROL DEVICE

HANGER ROD INSTALLATION

PART 1 GENERAL

1.01 BACKGROUND

A. The temperature control device (TCD) is a steel structure consisting of a shutter structure and low-level intake structure that are attached to the upstream face of Shasta Dam. The device encloses all five existing power penstock intakes and permits selective level withdrawal of reservoir water. High level withdrawal is controlled by the 250 ft-wide by

300 ft-high shutter structure. Construction of the TCD started in December 1994 and was substantially complete in December 1996.

B. A special climb inspection was performed March 6-8, 2023. Following the climb inspection, engineering analysis was completed on the hanger rod group located at the right side, downstream corner of Shutter No. 3. The inspection and analysis have confirmed that the Left Side Upstream (LS-US) hanger rod assembly no longer has the ability to provide structural support. With the loss of the LS-US hanger rod assembly, the entire hanger rod group at the right side, downstream corner of Shutter No. 3 is at risk of failure. These hanger rod assemblies are considered critical structural components because the loss of one of these corner hanger rod groups would likely lead to the failure of Shutter No. 3, and potential progressive failure of adjacent Shutter Nos 2 and 4.

C. In November 2023 an emergency contract was issued for the installation of a temporary hanger rod assembly to replace the left side, upstream (LS-US) hanger rod assembly within the hanger rod group at the right side, downstream corner of Shutter No. 3. The replacement hanger rod assembly was installed without coatings to a snug-tight condition.

1.02 LOCATION

A. Work is located at Shasta Dam, approximately 9 miles northwest of Redding, California in Shasta County.

B. The TCD is located on the upstream face of Shasta Dam.

Statement of Work - 2

1.03 SCOPE

A. Work to be performed under this Statement of Work consists of the removal and replacement of the one (1) temporary hanger rod assembly installed on November 2023.

1.04 OBJECTIVE

A. The objective of this project is to replace the one (1) temporary hanger rod assembly on the right side, downstream corner of Shutter No. 3 with a replacement hanger rod assembly that would be coated and pretensioned.

B. Replacement hanger rod assembly will be government-furnished.

1.05 RESERVOIR CONDITIONS, UNIT AND TCD OPERATIONS, TOP OF DAM

CLOSURES

1. Predicted Shasta Lake water surface elevations:

2. September 30, 2023: 1021.00 ft

3. October 31, 2023: 1014.00 ft

4. November 30, 2023: 1010.00 ft

5. December 31, 2023: 1011.00 ft

C. Unit Outages

1. The units on either side of the work (Units 2 and 3) will be locked out during times of above water work.

D. Top of Dam Closures:

1. Closure of the upstream lane of the Dam Crest Road is acceptable while contractor is mobilized for the work.

2. Two lane closure of the Dam Crest Road subject to approval by the Contracting

Offices Representative (COR).

1.06 REFERENCE STANDARDS

A. American Institute of Steel Construction (AISC)

1. AISC 303-22 Code of Standard Practice for Steel

Buildings and Bridges

2. AISC 325-22 Steel Construction Manual, 15th Edition

3. AISC 360-22 Specifications for Structural Steel Buildings

B. ASTM International (ASTM)

1. ASTM B117-19 Standard Practice for Operating Salt Spray

(Fog) Apparatus

Statement of Work - 3

2. ASTM C920-18 Elastomeric Joint Sealants

3. ASTM D870-17 Testing Water Resistance of Coatings Using

Water Immersion

4. ASTM D2794-93(2019) Resistance of Organic Coatings to the

Effects of Rapid Deformation (Impact)

5. ASTM D3276-15e1 Guide for Painting Inspectors

6. ASTM D4060-19 Abrasion Resistance of Organic Coatings by the Taber Abraser

7. ASTM D4285-83(2018) Indicating Oil or Water in Compressed Air

8. ASTM D4541-17 Pull-Off Strength of Coatings Using

Portable Adhesion Testers

9. ASTM D4587-11(2019) Conducting Tests on Paint and Related

Coatings and Materials Using a Fluorescent

UV-Condensation Light- and Water-

Exposure Apparatus

10. ASTM D5894-21 Cyclic Salt Fog/UV Exposure of painted

Metal, (Alternating Exposures in a Fog/Dry

Cabinet and a UV/Condensation Cabinet)

11. ASTM G8-96(2019) Cathodic Disbonding of Pipeline Coatings

C. International Organization for Standardization (ISO)

1. ISO 8502-3-92 Assessment of dust on Steel Surface

Prepared for Painting (Pressure-Sensitive

Tape Method)

D. Master Painters Institute (API) Approved Product List (APL)

1. MPI – APL

E. The Society for Protective Coatings (SSPC)/NACE International (NACE)

1. SSPC-Guide 15-13 Field Methods for Retrieval and Analysis of

Soluble Salts on Substrates and Other

Nonporous Substrates

2. SSPC-PA1-16 Shop, Field, and Maintenance Painting of

Steel

3. SSPC-PA2-22 Measurement of Dry Paint Thickness with

Magnetic Gages

4. SSPC-QP3-10/AISC 420 Evaluating the Qualification of Shop

Painting Contractors

5. SSPC-SP1-16 Solvent Cleaning

6. SSPC-SP2-04 Hand Tool Cleaning

Statement of Work - 4

7. SSPC-SP3-04 Power Tool Cleaning

8. SSPC-SP10/NACE 2-15 Near-White Blast Cleaning

9. SSPC-SP11-20 Power Tool Cleaning to Bare Metal, Level 3 minimum requirement

10. SSPC-VIS1-12 Guide and Reference Photographs for Steel

Surfaces Prepared by Abrasive Blast

Cleaning

11. SSPC-VIS3-07 Visual Standard for Power- and Hand-Tool

Cleaned Steel

12. SSPC Paint Manual Volume 1, Good Painting Practices, Fourth

Edition 2002

13. NACE SP 0188-06 Discontinuity (Holiday) Testing of New

Protective Coatings on Conductive

Substrates

14. NACE SP 0287-16 Field Measurement of Surface Profile of

Abrasive Blast Cleaned Steel Surfaces

Using a Replica Tape

15. NACE SP 0178-07 Detail, Finish, and Design Considerations for Immersion Service.

F. Reclamation

1. RSHS-14 Reclamation Safety and Health Standards

(https://www.usbr.gov/safety/rshs)

G. Occupational Safety and Health Administration

1. OSHA 1910.27 Scaffolds

1.07 SUBMITTALS

A. Definitions:

1. Days: Calendar days.

2. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.

B. Submittal Requirements:

1. General:

a) Prepare in English.

b) Label with contract number and title, and RSN.

c) Measurement Units: US Customary Units.

Statement of Work - 5

2. Drawings:

a) Minimum Identification in Title Block:

i. Contract number and title.

ii. Contractor’s or supplier’s title and drawing number.

iii. Date.

C. Submittal Procedures:

1. Submit complete sets of required materials for each RSN as specified in Submittal

List. A complete set includes all listed items for RSNs with multiple parts.

a) Electronic submittals:

i. In Portable Document Format (PDF).

ii. Optical Character Recognition (OCR).

iii. 508 compliant.

iv. RSNs having more than one requirement shall be bookmarked.

v. RSNs with requirements for files other than PDF

(e.g., .XER, .PLF, .DWGs, etc) shall be combined in a .ZIP file.

vi. Include RSN transmittal letter.

vii. Each submittal shall be submitted as one PDF, or

.ZIP (only when multiple file types are required).

D. Include the following information in transmittal letters:

1. Cover Letter:

a) Contract number and title.

b) RSN for each attached submittal.

c) Identify submittal as initial or resubmittal.

2. Submittal contents following cover letter. Include all listed items for RSNs with multiple parts.

E. Resubmittal of submittals not approved:

1. Mark changes such that they are readily identifiable and show revision date.

2. Resubmitted drawings shall include a revision block with date.

3. Describe reasons for significant changes in transmittal letter.

4. Resubmit returned submittals within 7-calendar days after receiving comments, unless otherwise directed.

5. Requirements for initial submittals apply to resubmittals.

Statement of Work - 6

6. Resubmittals shall be complete submittals.

F. Submit each RSN under a separate transmittal letter. Multiple RSNs submitted under a single letter will be returned for resubmittal.

G. Review of Submittals:

1. Time Required:

a) Submittal review will require 7 calendar days for review of each submittal or resubmittal, unless otherwise specified.

b) Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received.

2. Time in Excess of Specified:

a) Contracting Officer may extend contract completion date to allow additional time for completing work affected by excess review time.

i. Time extension will be to extent that excess review time caused delay to contract completion date.

ii. Time extension will not exceed time used in excess of specified number of days for review of submittals or resubmittals.

iii. Concurrent days of excess review time resulting from review of 2 or more separate submittals or resubmittals will be counted only once in extending contract completion date.

b) No time extension will be allowed if Contractor fails to make complete submittals in sequence and within time periods specified.

c) Adjustment for delay will be made only to extent that:

i. Approval was required under contract, and

ii. Requests for approval were properly and timely submitted and were approved.

d) Adjustment will be subject to terms of paragraphs (b) and

(c) of the clause at FAR 52.242-14, Suspension of Work;

however, no such delay shall be deemed to be a

“suspension order” as the term is used in that clause.

3. Submittal Response:

a) Response letter will indicate whether submittal is approved, not approved, acceptable, not acceptable, or acknowledged receipt.

Statement of Work - 7

i. Revise and resubmit submittals not approved or not acceptable.

ii. Do not change designs without approval of

Contracting Officer after drawings, documentation, and technical data have been approved.

b) Request For Information (RFI): A response will be provided within 7-calendar days.

c) General Correspondence to the Contracting Officer’s

Representative: A response will be provided within 7-calendar days.

H. Transmittal:

1. Email and attach any required files for all correspondence and transmittals.

I. Submittal List:

1. RSN 0001-1, Erection and Equipment Plans.

a) Drawings, data, and plans showing sequence and methods to remove, install, and pretension hanger rod assembly.

i. Include step by step procedure that details how existing rod assembly will be removed.

ii. Include step by step procedure that details how

Government furnished rod assembly will be installed.

iii. Include methods to protect personnel from accidents such as falls and drownings.

iv. Include timeframes for one- and two-lane closures of Dam Crest Road.

v. Include timeframes for above water work.

b) Methods and equipment for pretension hanger rod.

c) Describe erection equipment proposed for use.

i. Include attachment details between equipment and temperature control device and/or dam.

2. RSN 0001-2, Safety Program.

a) The contractor shall evaluate the conditions for access into the work area and shall provide a site-specific plan to safely access the work area, including provisions for rescue of an individual in the event of an emergency in accordance with

Reclamation Safety and Health Standards (RSHS) and

OSHA applicable standards.

Statement of Work - 8

i. The plan shall include an assessment that determines the feasibility to access the work by other means other than a rope descent system.

ii. Provide a rope descent plan for access to rope in accordance with OSHA 1910.27 Scaffolds and rope descent, if no other means of accessing the work is feasible.

b) Provide listing of all equipment/materials to be used in the

Safe Access Plan

c) Provide specific training records of individuals who will oversee and perform the work.

d) Follow outline in Appendix B of RSHS.

3. RSN 0001-3, Coatings Approval Data:

a) For each coating material:

i. Manufacturer’s product data, application, and

Safety Data Sheets (SDS) sheets.

ii. Supplier’s name, address, and phone number.

iii. Identification of “Items to be coated” including sub-letter and sub-number listed in Coating Tabulations.

b) For each caulk and filler:

i. Manufacturer’s product data, application, and SDS sheets.

ii. Supplier’s name, address, and phone number.

iii. Identification of areas of use including sub-letter and sub-number listed in Coating Tabulations.

iv. For each substituted coating material “equal” to specified product in Coating Tabulation:

v. List of not less than 5 similar successful material applications:

vi. Project name, location, type of structure, and application dates.

vii. Owner’s name, address, and telephone number.

c) Certification that material meets or exceeds specified requirements:

i. Manufacturer’s certification including technical representative’s signature and date of signature.

ii. Independent laboratory’s certified test reports.

4. RSN 0001-4, Coatings Final Approval Data:

Statement of Work - 9

a) For each coating material and thinner:

i. Purchase orders including order number, date, manufacturer’s designated product name, batch number(s), and quantity purchased.

5. RSN 0001-5, Coatings Qualifications:

a) Coating Applicator.

b) List of not less than 3 comparable jobs for each coating type including owner’s name, address, and telephone number.

c) Personnel shall be qualified to tradesman level as blast-cleaner, painter, applicator, etc. The personnel shall have relevant knowledge of health and safety hazards, use of protection equipment, coating materials, mixing, and thinning of coatings, coatings pot-life, and surface requirements.

d) Personnel not qualified to tradesman level shall document training and experience to the same level as a formalized tradesman education.

e) Coating Contractor Inspector Provide the Following:

i. Qualified to inspect specified coating materials by coating experience or certifications. Provide the following:

ii. Documentation of successful completion of training in the application and inspection of coating materials similar too materials and conditions specified. Provide documentation.

iii. Letter from contractor listing the personnel performing QC inspections, certified at a minimum as NACE Coating Inspector Level 1 (CIP) or as a

SSPC Protective Coatings Inspector (PCI), as they report directly to a QC Supervisor who shall be a

NACE Level 3 Coatings Inspector (CIP) or a SSPC

Protective Coatings Inspector (PCI).

6. RSN 0001-6, Coatings Contractor Quality Testing Report:

1) Comprehensive report of daily quality control test reports.

Statement of Work - 10

1.08 DRAWINGS

List of Drawings

Sheet

No.

Drawing No. Title

Metalwork:

1 FIGURE 1 Structural Steel – Location Plan and Sections

Information Drawings:

2 214-D-26281 Shasta Temperature Control Device – Middle Gate Relief

Panel Repair, Location Map

3 214-D-26282 Shasta Temperature Control Device – Middle Gate Relief

Panel Repair, Vicinity Map

4 214-D-22134 Shasta Temperature Control Device – General Arrangement

– Plans

5 214-D-22135 Shasta Temperature Control Device – General Arrangement

– Hoist Platform – Plan and Elevation

6 214-D-22136 Shasta Temperature Control Device – General Arrangement

– Elevation

7 214-D-22137 Shasta Temperature Control Device – General Arrangement

– Sections

8 214-D-22138 Shasta Temperature Control Device – General Structural

Design Data

9 214-D-22142 Shasta Temperature Control Device – Outline and

Reinforcement – Shutter Beams

10 214-D-22148 Shasta Temperature Control Device – Structural Steel – Key

Plan, Elevation, and General Notes

11 214-D-22157 Shasta Temperature Control Device – Structural Steel –

Shutter Structure No. 3 Section 125-125 and Section 126-

12 214-D-22169 Shasta Temperature Control Device – Shutter Structure No.

3 – Rigid Frame – Sections

13 214-D-22465 Shasta Temperature Control Device – Structural Steel –

Shutter Structures – Connection SC52

14 214-D-22417 Shasta Temperature Control Device – Structural Steel –

Shutter Structure – Rigid Frame Connection SC30 and SC31

Statement of Work - 11

List of Drawings

Sheet

No.

Drawing No. Title

15 214-D-22419 Shasta Temperature Control Device – Structural Steel –

Shutter Structures – Rigid Frame – Connections SC35 and

SC36

16 214-D-22434 Shasta Temperature Control Device – Dam Connections –

Connections DC2 and DC2A

17 214-D-22435 Shasta Temperature Control Device – Dam Connections –

Connections DC1, DC1A, DC2, DC2A - Details

18 214-D-22436 Shasta Temperature Control Device – Dam Connections –

Dam Connection DC3, DC3A, DC5, and DC5A

19 214-D-22440 Shasta Temperature Control Device – Dam Connections –

Connections DC8 and DC8A

20 214-D-22459 Shasta Temperature Control Device – Dam Connections –

Dam Connection Details

Standard Drawings:

21 40-D-7102 Government Drawing Format - Drawing Border, Sample

Title Block and Signature Lines

1.01 WORK TO BE PERFORMED

A. Replace the left side, upstream (LS-US) temporary hanger rod assembly within the hanger rod group at the right side, downstream corner of Shutter No. 3 with a

Government-furnished replacement hanger rod assembly.

1. All work shall be accomplished in the dry.

2. Minimize time when corner only has 3 rods.

a. Maximum time without existing or new rod assembly: 48 hours

B. Contractor shall provide all labor, tools, special tools, hoisting equipment, safety equipment, and consumable materials required to complete the work.

1.02 PRODUCTS

A. Replacement Hanger Rod Assembly

Statement of Work - 12

1. Government-furnished

2. Total assembled length 714 inches (59’-6”) (3 equal lengths) – 236.0 inches (with

2 couplers).

3. Available at Shasta Dam Visitor Center (16349 Shasta Blvd. Shasta Lake, CA

96019.

1.03 RECOMMENDED SEQUENCE

A. Removal and installation shall be completed within a single shift ensuring that there will be (4) hanger rods installed at all times between shifts.

B. Removal of Temporary Hanger Rod Assembly:

1. Support and remove the (1) temporary hanger rod assembly. Temporary hanger rod assembly is a 5¼”ø diameter rod with threaded ends. Approximately 60 feet in length, 3 equal length 20-foot sections with couplers and jam nuts.

a. If removal is to utilize flame cutting using Oxygen-acetylene (and related fuel) torches, heat shielding/protection must be provided for the adjacent rods such that the adjacent rods are not impacted adversely by radiant heat from cutting. Additionally, flame cutting shall not occur within 4 feet of

Connection SC31 (Refer to Figure 1).

2. Contractor to dispose of temporary hanger rod assembly.

C. Installation of Replacement Hanger Rod Assembly:

1. Assemble Government furnished hanger rod assembly.

a. Couplers and jam nuts shall fully engage hanger rod threads.

b. Apply fillers and caulk in accordance with PART 2 – COATINGS.

c. Apply coatings in accordance with PART 2 – COATINGS.

2. Install replacement hanger rod assembly where temporary assembly was removed.

Placement and alignment of the hanger rod assembly to the hanger plate as required. For both top and bottom connections, perform the following:

a. Nuts shall fully engage hanger rod threads.

b. Ensure top nut and plate washer have clean bearing surfaces and are in full contact, per AISC 360-22, Section M2.8.

c. Ensure threaded rod projects minimum of 6 inches above top heavy hex nut.

d. Bring replacement hanger rod assembly to a snug tight condition and tighten jam nuts against all couplers.

D. Pretension Replacement Hanger Rod Assembly:

1. Tension replacement hanger rod assembly to 200 kips.

Statement of Work - 13

2. The deflection of the Connection SC31 (Refer to Figure 1) shall be measured and monitored continuously during load distribution.

a. If vertical deflection exceeds ±½” the contractor shall stop work and notify the COR.

3. COR shall be present for, witness, and approve the final pretension. Contractor shall provide COR written notice 14 days prior to performing load distribution.

4. After balance condition is achieved, as approved by COR, tighten top heavy hex nuts to 300 ft-lbs at Connection Pl. CP2B (Refer to Figure 1).

5. Cut off excess rod length after pre-tensioning, provide 2-inch minimum concrete cover over rods. Field cutting should be done with an abrasive wheel or band saw.

6. Replacement Hanger Rod Assembly shall not be subjected to the heat of a torch after loading.

E. Complete:

1. Place replacement concrete, see Figure 1.

PART 2 COATINGS

2.01 DELIVERY, STORAGE, HANDLING

A. Deliver materials to jobsite in original, undamaged, unopened containers labeled with manufacturer’s name, designated product name, batch number, date of manufacture, and any special instructions.

B. Deliver materials in containers not larger than 5 gallons as packaged by manufacturer unless suitable equipment is provided at jobsite to handle and thoroughly mix materials in larger containers.

C. Store coating materials and thinners in accordance with the manufacturer's recommendations, and as a minimum, store off the ground, under cover, and at 50- to 95-degrees Fahrenheit (F).

D. Do not use coating material which has exceeded manufacturer’s specified storage stability period (shelf life).

2.02 AMBIENT CONDITIONS

A. Maintain environmental conditions to meet coating manufacturer’s requirements during surface preparation, coating application, and curing period. Provide heating or cooling, and dehumidification as needed. Complete curing before placing the coating systems into service.

B. Coatings shall be applied when the substrate surface temperature is 5 degrees F or more above the dew point temperature and for at least 8 hours after application.

Statement of Work - 14

2.03 PROJECT CONDITIONS

A. Galvanic isolation of dissimilar metals shall be required. Coatings in this specification section shall not serve as the primary galvanic isolation.

B. Contractor shall comply with applicable federal, state, and local air pollution and environmental control regulations for surface preparations, blast cleaning, disposal of spent materials and debris, and coatings application.

2.04 PRODUCTS

A. EQUIPMENT

1. Surface preparation and spray application equipment:

a. Sized in accordance with coating manufacturer’s recommendations.

b. Provide:

1) Pressure gauges and pressure regulators.

2) Air supply lines free from oil and moisture.

2.05 COATINGS

A. Specified in Coating Tabulations:

1. Apply only one coating system per option in Coating Tabulations.

2. Apply compatible products of same manufacturer for coating system components.

B. Volatile Organic Compounds (VOC): Do not exceed maximum permitted by Federal, State, and local air pollution control regulations as supplied in container or by addition of thinner material.

C. Factory color or tint only. Do not color or tint at jobsite.

D. Use manufacturer’s recommended thinners for coating materials.

E. Do not use accelerator products unless approved by COR.

2.06 FILLERS AND CAULKS

A. Caulks:

1. Coating manufacturer’s standard or compatible caulk material.

2. Polyurethane, silicone, or silicone acrylic caulk material: Meets or exceeds

ASTM C920 type S or M, grade NS, class 25, suitable for water immersion service.

B. Fillers:

1. Apply compatible products of same manufacturer as coating system components.

Statement of Work - 15

2. Approved fillers:

a. PPG Amercoat 114 A, as manufactured by PPG, www.ppgpmc.com.

3. Provide one of the above fillers, or equal with following essential characteristics:

a. Coating manufacturer’s standard filler material.

b. Approved use by manufacturer.

2.07 MISCELLANEOUS MATERIALS

A. Deionized Water.

B. Chlor-Rid as manufactured by Chlor-Rid, www.Chlor-rid.com, C. HoldTight 102 as manufactured by Holdtight Solutions, www.holdtight.com, D. Chlor-Gone, as manufactured by Aquron, www.aquron.com

E. Provide one of the above salt removers, or equal with following essential characteristics:

1. Commercially available additive for soluble salt removal.

2. Water soluble.

3. Biodegradable.

4. Zero volatile organic compounds.

2.08 EXECUTION

A. FIELD PAINTING

1. Follow specified information in the Coating Tabulations and/or coating manufacturer’s standard surface preparations and application instructions for field applied coatings.

B. PROTECTION OF ADJACENT SURFACES

1. Remove, mask, or otherwise protect items or surfaces not coated from contamination and damage during cleaning and coating operations.

2. Examples include protecting mating and machined surfaces, mechanical and electrical equipment (open or enclosed), instruction and similar plates, and wet and newly coated surfaces.

C. SURFACE PREPARATION

1. Remove or repair surface irregularities and impart profile as specified:

a. Substrate defects:

1) Pitting, gouges, scratches, porosity, and similar:

a) Grind smooth.

http://www.chlor-rid.com/ http://www.holdtight.com/ http://www.aquron.c/

Statement of Work - 16

b) Defects exceeding 20-percent reduction in wall thickness require weld repairs.

b. Grind full length of edges and corners smooth to a radius of at least 1/16-inch.

2. Surface preparation method:

a. See Coating Tabulations.

1) Method A: SSPC-SP1.

2) Method C-1: Field touch-up and repair of defective or damaged coated areas.

a) For metal substrate:

i. SSPC-SP1.

ii. SSPC-SP11.

iii. Level 1 shall be required with no amount of residue permitted in pit bottoms and surface a profile of 1-mil minimum unless a higher value is specified.

b) For surrounding intact coating (nominal 2- to 3-inch margin):

i. SSPC-SP1.

ii. Feather abrupt edges and around repair area by hand or power tool with non-woven pad into adjacent tightly bonded coatings.

iii. Roughen or abrade surface in accordance with manufacturer’s recommendations to achieve matted or lusterless finish.

b. Compare prepared steel surfaces to following visual reference photographs for allowable visible contaminants and stains:

1) SSPC-VIS3 for power and hand tool cleaning.

c. Assessment of dust contaminants:

1) Perform clear tape test method in accordance with ISO 8502-3.

2) Perform three tests per shift.

3) Acceptance Criteria: Degree of cleanliness shall meet Class 3.

3. Surface profile:

a. Prepare as specified in Coating Tabulations.

b. Where not specified, prepare in accordance with manufacturer’s instructions for metallic substrates or existing coating surfaces and service environment.

Statement of Work - 17

c. Where manufacturer’s instructions do not specify a surface profile, prepare blasted surfaces to following profile:

1) Atmospheric Service Environments: 1-mil or greater angular profile and less than specified millage of first applied coat.

2) Burial and Immersion Service Environments: Angular profile 2-mil or greater and less than specified millage of first applied coat.

d. Inspect surface profile in accordance with NACE SP 0287:

1) Use replica tape suitable for surface profile depth range.

2) Perform at least two tests per 1,000-square feet.

4. Soluble salts:

a. Measure concentration of chlorides, nitrates and sulfates in accordance with SSPC Guide 15.

b. Perform on each uncoated threaded area prior to assembly.

c. Acceptance criteria: Do not exceed 3-micrograms per square centimeter for chlorides and 5-micrograms per square centimeter for nitrates and sulfates.

1) If salt contamination exceeds allowable limits, clean area and re-perform test till acceptance criteria is met.

5. Re-clean or perform additional surface preparation of contaminated surfaces before coating application.

D. COMPRESSED AIR EQUIPMENT

1. Keep air compressor and spray application equipment lines free of oil and moisture during work.

2. Compressed air quality:

a. Perform tests in accordance with ASTM D4285.

b. Perform test at the beginning of every shift.

E. FILLERS AND CAULK APPLICATION

1. Prior to setting jam nuts, caulk around rod at top and bottom of couplers.

2. After final coat has cured dry-to-handle, apply caulking around rod at the top and bottom coupler jam nuts.

a. Only complete if coating Option 2 in Tabulation 1 selected.

3. Caulk areas including crevices, gaps, and seams.

4. Apply in a uniform texture, neatness, and color matched appearance.

5. Apply in accordance with manufacturer’s instructions and achieve tight bond to substrate or previous coats.

Statement of Work - 18

F. COATING APPLICATION

1. Coating shall be done in a workmanlike manner to produce an even film of uniform thickness. The finished surfaces shall be free from runs, drops, ridges, waves, laps, sags, curtains, brush marks, and variations in color, texture, and finish.

2. Shop coated and lined equipment shall be primed and finished in the shop and touched up in the field with a coating material from Coating Tabulation 1 after installation and in accordance with the coating manufacturer’s application instructions.

3. Follow specified systems in the Coating Tabulations and coating manufacturer’s application instructions for surface preparation and coatings application. In event of a conflict, the more stringent requirement shall apply.

4. Apply number of coats and coating thickness specified in Coating Tabulations.

a. Alternate coat colors to differentiate between coats.

b. Apply in accordance with manufacturer’s instructions.

c. Apply in accordance with SSPC PA1.

5. Re-clean contaminated surfaces between coats.

6. Dry Film Thickness (DFT):

a. After each coat, inspect hardened coating system for DFT compliance in accordance with SSPC PA2.

b. Acceptance Criteria: no single spot measurement less than 80 percent minimum or 120 percent maximum specified.

7. Discontinuity (Holiday) Testing:

a. Inspect in accordance with NACE SP 0188:

1) Use maximum test voltage for DFT as recommended by coating manufacturer to prevent coating damage.

G. CONTRACTOR FIELD QUALITY TESTING

1. Inspection Equipment:

a. Calibrate inspection devices and equipment in accordance with the manufacturer’s instructions.

b. Verify calibration prior to every use.

2. Qualified personnel shall conduct tests and sign reports.

a. Perform tests in presence of the COR:

b. Provide rigging for COR to observe inspections.

3. Make daily reports for review by the COR, including:

a. Date of work.

Statement of Work - 19

b. Description of areas and work performed.

c. Environmental conditions.

d. Results from the following quality control tests:

1) Soluble salt.

2) Surface profile.

3) Visual comparison of prepared surfaces.

4) Assessment of dust contaminants.

5) Compressed air quality.

6) Dry film thickness (DFT).

7) Discontinuity (Holiday) testing.

8) Coating adhesion testing (when directed by the COR).

4. Final inspection will take place after repairs, but before placing into service.

a. Allow Government inspection of the rod, after installation and completion of coating work.

1) Contractor must notify COR to coordinate the inspection 14 days prior to the inspection taking place.

2) Government conducted final inspection does not relieve the contractor of their responsibilities for quality control and final inspection.

H. REPAIR AND REMEDIAL WORK

1. Repair defective or damaged areas of coatings in accordance with coating manufacturer’s recommendations.

Statement of Work - 20

I. COATING TABULATIONS

Tabulation No. 01

Items to be coated:

a. Exposed threaded areas on hanger rods after installation

b. Damaged areas of coating on hanger rod after installation

Coating materials – Option 1

Wax Tape

Number and thickness of coats

Surface preparation method

Trenton Corporation:

Temcoat 3000 Primer/

Wax-Tape #2A/ MCO110

Outerwrap

Use stretch wrap after application in accordance with manufacturer’s instructions.

Follow manufacturer’s instructions

Wax tape shall have an 75% overlap on itself

Wax tape wrap shall extend

3-6 inches past uncoated threads onto the existing coating.

SSPC-SP1

SSPC-SP2 or SSPC-SP3

Coating materials – Option 2

Epoxy

Number and thickness of coats

Surface preparation method

Statement of Work - 21

Tabulation No. 01

PPG:

Amerlock 400

Amerlock 2

Amercoat 240

Color and gloss:

manufacturer’s standard light gray or other light color and gloss

3 or more base coats apply at

6 to 8 mils DFT per coat, plus stripe coats.

Total base coat system excluding stripe coats:

18-mil DFT, minimum

24-mil DFT, maximum

Method C-1 or manufacturer’s instructions.

1-2 mil surface profile

Follow manufacturer’s surface preparation and application instructions to apply subsequent coats.

PERFORMANCE REQUIREMENTS:

Testing Protocol Acceptance Criteria

Fresh/deionized water immersion test, ASTM D 870:

passes, 2 years test with aerated water held at ambient temperature with no blisters evident on either scribed or unscribed sides.

Dilute Harrison immersion test, Modified

ASTM D 870:

passes, 2 years test with aerated water held at ambient temperature with no blisters evident on either scribed or unscribed sides.

Abrasion resistance, ASTM D 4060, CS-17 wheel, 1,000 cycles, 1-kg load:

Epoxy: 100 milligram loss or less

100% Epoxy: 60 milligram or less

Direct impact, ASTM D 2794: 40 inch-pounds

Pulloff adhesion, ASTM D 4541, annex A2, type II tester:

1000 psi or greater

Cyclic testing salt fog/UV, ASTM D 5894: 1/4 inch or less undercutting at 3000 hrs.

Cathodic disbondment, ASTM G 8: No disbondment at 120 day test

Tab IE-02.DOC

J. COLOR SCHEDULE (Reserved)

K. Colors are to be selected to match new coatings.

Statement of Work - 22

PART 3 OTHER REQUIREMENTS

3.01 GOVERNMENT FURNISHED PROPERTY

A. Electric power, compressed air, Government gantry crane, and non-potable water are not available for use by the Contractor.

3.02 DISPOSAL OF MATERIALS

A. Removal and disposal of temporary hanger rod assembly and waste products generated during the course of performing the work is the responsibility of the Contractor.

3.03 SAFETY

A. Work shall be performed safely and in accordance with RSHS.

B. Hazardous Energy Control Program (HECP) site specific training required for all contractor workers.

C. Submit Safety Program to Government for approval prior to mobilizing on site.

D. Contractor shall follow Government’s lockout/tagout procedures.

1. No underwater work is permitted.

2. Notify COR 24 hours in advance of required unit outage.

3.04 SECURITY

A. Shasta Dam is a secured government facility with public access. Contractor shall provide the names and photo identification (driver’s license) of personnel performing the work in order to obtain a contractor badge to access the site.

B. The Contractor’s personnel are only permitted to work in the immediate area of the TCD.

Solicitation No. 140R2024Q0125 j

D-1

SECTION D - PACKAGING AND MARKING

There are no clauses in this section.

E-1

SECTION E - INSPECTION AND ACCEPTANCE

Clause

Title

Date

52.246-12

Inspection of Construction

AUG 1996

F-1

SECTION F - DELIVERIES OR PERFORMANCE

Clause

Title

Date

52.242-14

Suspension of Work

APR 1984

FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND APR 1984

COMPLETION OF WORK

The Contractor shall be required to

(a) commence work under this contract within 7 calendar days after the date the Contractor receives the notice to proceed,

(b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than 30 calendar days after the date the

Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.

(End of clause)

FAR 52.211-12 LIQUIDATED DAMAGES – CONSTRUCTION SEP 2000

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $600.00 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

G-1

SECTION G - CONTRACT ADMINISTRATION DATA

G.1 This contract shall be administered by the California Great Basin Regional Office, 2800

Cottage Way, Sacramento, California 95825-1898.

G.2 DIAR 1452.201-70 AUTHORITIES AND DELEGATIONS SEP 2011

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

The COR will be named at time of award.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction

(written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the

Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the

COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting

Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

G-2

G.3. WBR 1452.201-80 CONTRACTING OFFICER’S MAY 2018

REPRESENTATIVE’S AUTHORITIES

AND LIMITATIONS – BUREAU OF

RECLAMATION

(a) Performance of the work under this contract shall be subject to the technical direction of the

Reclamation Contracting Officer's Representative (COR). The term “technical direction” is defined to include, without limitation:

(1) Inspecting and accepting or rejecting work performed under the contract.

(2) Representing the Government in technical phases of the work. The COR is responsible for the technical administration of the contract and will provide instructions and interpretations to the Contractor on all technical matters relating to the contract. The COR will supervise or oversee all Government technical and administrative personnel assigned to assist the COR.

(3) Reviewing and, where required by the contract, approving submittals of technical data, shop drawings, samples, literature, plans, or other data required to be delivered by the Contractor to the Government.

(b) The Contractor will receive a copy of the written COR designation from the Contracting

Officer. It will specify the extent of the COR's authority to act on behalf of the Contracting

Officer.

(c) Technical direction must be within the scope of work stated in the contract. Only the

Contracting Officer is authorized to determine if a change is within the scope of the contract;

therefore, the COR does not have the authority to, and may not, issue any technical direction that

(1) Constitutes a direction of additional work outside the Contract requirements;

(2) Constitutes a change as defined in the contract clause entitled “Changes;”

(3) In any manner causes an increase or decrease in the total contract cost, or the time required for contract performance;

(4) Changes any of the expressed terms, conditions or specifications of the contract; or

(5) Interferes with the Contractor's right to perform the terms and conditions of the contract.

(d) All technical direction shall be issued in writing by the COR.

(e) The Contractor must proceed promptly with the performance of technical direction duly issued by the COR in the manner prescribed by this clause and within its authority under the provisions of this clause. If, in the opinion of the Contractor, any instruction or direction by the

COR falls within one of the categories defined in (c)(1) through (c)(5) of this clause, the

Contractor must not proceed and must notify the Contracting Officer in writing within five (5) working days after receipt of any such instruction or direction and must request the Contracting

Officer to modify the contract accordingly. Upon receiving the notification from the Contractor, the Contracting Officer must -

(1) Advise the Contractor in writing after receipt of the Contractor's letter that the technical direction is within the scope of the contract effort and does not constitute a change under the

Changes clause of the contract; or

(2) Advise the Contractor that the Government will issue a written change order.

(f) A failure of the Contractor and Contracting Officer either to agree that the technical direction

G-3 is within the scope of the contract or to agree upon the contract action to be taken with respect to the technical direction will be subject to the provisions of the clause entitled “Disputes.”

H-1

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H.1 - INTERMEDIATE…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .