This is a Statement of Work (SOW) and associated specification sections for a federal construction project involving lead-based paint (LBP) abatement and deferred maintenance at the New Meadows Range Barn located at the Payette National Forest in New Meadows, Idaho.

The base work scope includes: (1) roof replacement consisting of removal of existing roofing, installation of plywood sheathing over skip sheathing, ice/water shield, and new corrugated metal roofing; (2) lead-based paint abatement of rafter tails, soffit, and fascia, followed by painting; (3) removal of lead-based paint siding and felt paper with installation of plywood sheathing, building wrap, new siding in-kind, new trim in-kind, and painting; and (4) replacement of approximately 10 feet of existing 1-inch SIDR 9 HDPE waterline, relocation of an existing hydrant 2 feet east, replacement with a new hydrant and drainage basin, and replacement of a galvanized barb fitting with a brass barb fitting. Optional work includes removal of existing wood decking and foundation piers and fabrication/installation of new expanded metal decking with steps over a metal frame with new foundation piers. The project start date is July 2027 with a contract duration of 90 calendar days. All workers performing lead abatement must have completed OSHA-approved lead abatement training within the previous five years. The contractor must provide insurance coverage of $500,000 single limit for bodily injury and $1,000,000 per occurrence for property damage. Associated specification sections detail measurement and payment procedures, mobilization requirements, submittal procedures, historic treatment procedures, selective demolition, lead abatement work practices, lead waste disposal, concrete work for limited applications, metal grating platforms and stairs, finish carpentry, roof preparation, formed metal roof panels, colors, and exterior painting requirements. The site will remain open to the public during construction; the contractor is responsible for signing and limiting public access. No overnight camping is permitted on-site, and temporary toilet facilities must be provided.

View the file

Other files

File Type Posted
C04b 1240LT27Q0027.pdf PDF
C04f WD Adams County Idaho 1240LT27Q0027.pdf PDF
C04d Drawings 1240LT27Q0027.pdf PDF
C04e Photos 1240LT27Q0027.pdf PDF
C04a SF-1442 1240LT27Q0027.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001

Statement of Work

GENERAL SPECIFICATIONS

NEW MEADOWS BARN LBP & DEFERRED MAINTENANCE

(Revised 10/26/2026)

1.1 SCOPE OF CONTRACT

A. This project consists of modifying an existing waterline and replacing a water hydrant, removing an existing wood deck and constructing a new metal deck, replacing the existing roof, abatement of lead-based paint, removing lead-based paint siding, installing new siding, and preparing and painting exterior surfaces of the New Meadows Range Barn located at the New Meadows Barracks administrative site located at 100 S Norris Ave. New Meadows, ID 83654.

B. Base work includes the following described below:

1. Removal of existing roofing, installation of plywood sheathing over the existing skip sheathing, installation of ice/water shield over the entire roof, and installation of new corrugated metal roofing.

2. Abatement of lead-based paint of rafter tails, soffit, & fascia; and painting of aforementioned surfaces.

3. Removal of lead-based paint siding and felt paper, installation of plywood sheathing and building wrap, installation of new siding in-kind, installation of new trim in-kind around the windows, doors, and corners and painting of all aforementioned surfaces.

4. Replacement of approximately 10-feet of existing 1-inch SIDR 9 HDPE waterline including moving the existing hydrant location 2-feet to the east along the side of the building and replacement of the existing hydrant with a new hydrant and drainage basin. Additionally, replacement of an existing galvanized barb fitting with a brass barb fitting is required.

C. Optional work includes the following described below:

1. Removal of existing wood decking and foundation piers and fabrication and installation of new expanded metal decking with steps over a metal frame with new foundation piers.

D. Quantities associated with these options are identified in the Schedule of Items.

1.2 PROJECT LOCATION

A. The project site is located at the Payette National Forest New Meadows Barracks Administrative Site, within the City of New Meadows, Idaho, at the following address:

100 S Norris Ave., New Meadows, ID 83654.

1.3 SITE INFORMATION AND LIMITATIONS

A. The following site conditions are considered indirect to the contract and the contractor will not be paid directly for any of the following items:

1. Construction site will be open to the public during construction. The Contractor will be responsible for signing and limiting public access.

2. The Contractor shall not disrupt existing utility service (water, power, telecom, sewer, etc.) to the site and on buildings without coordination and approval from the Contracting Officer’s Representative.

3. Water is available at the site for construction purposes.

4. Electricity is available at the site for construction purposes.

5. Other utilities are not available at the site for construction purposes.

6. The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work.

1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING

A. Signing and barricades shall be adequate enough to protect Forest Service employees.

This use will include access by Forest Service Employees. The contractor shall take special care to adequately sign and protect areas of work and construction from persons using these areas.

1.5 WORK CAMPS, STAGING AND STORAGE AREAS

A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers (work) on site.

B. Confine storage of materials and equipment as approved by the Contracting Officer.

C. Contractor shall maintain access to the facilities for Forest Service contracting personnel.

D. No overnight camping will be allowed on site.

1.6 INSPECTION OF WORKSITE

A. The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

1.7 START DATE

A. July 2027

1.8 CONTRACT TIME

A. 90 Calendar Days

1.9 SPECIFICATIONS

A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.

SECTION 011250 - MEASUREMENT AND PAYMENT

SECTION 011900 - MOBILIZATION

SECTION 013300 - SUBMITTAL PROCEDURES

SECTION 013591 - HISTORIC TREATMENT PROCEDURES

SECTION 017320 - SELECTIVE DEMOLITION

SECTION 024130 - LEAD ABATEMENT

SECTION 024134 - LEAD WASTE PRACTICES AND DISPOSAL

SECTION 033010 - CAST-IN-PLACE CONCRETE (LIMITED APPLICATIONS)

SECTION 055119 - METAL GRATING PLATFORMS, STAIR TREADS AND

RISERS

SECTION 062000 - FINISH CARPENTRY

SECTION 070150.19 - PREPARATION FOR REROOFING

SECTION 074113 - FORMED METAL ROOF PANELS

SECTION 099001 - COLORS

SECTION 099111 - EXTERIOR PAINTING

END OF SECTION C

March 2018

MEASUREMENT AND PAYMENT 011250-1

USDA FOREST SERVICE, R4

NEW MEADOWS BARN LBP & DEFERRED MAINTENANCE

SECTION 011250 - MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 SUMMARY

A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.

B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.

1.2 DETERMINATION OF QUANTITIES

A. The following measurements and calculations shall be used to determine contract quantities for payment.

1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.

2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.

3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.

4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.

5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.

6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.

B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."

MEASUREMENT AND PAYMENT 011250-2

1.3 UNITS OF MEASUREMENT

A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:

1. Acre: Make longitudinal and transverse measurements for area computations horizontally.

2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.

3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.

4. Cubic Yard (CY): A measurement computed by one of the following methods:

a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.

b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.

c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.

Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

5. Each (EA): One complete unit, which may consist of one or more parts.

6. Gallons (GAL): The quantity shall be measured by any of the following methods:

a. Measured volume in container.

b. Metered volume by approved metering system.

c. Commercially package volume.

7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.

8. Linear Foot (LF): Measurement of work along its length from point-to-point;

parallel to the base or foundation. Do not measure overlaps.

9. Lump Sum (LS): One complete unit.

10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.

11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.

12. Square Foot (SF): Measured on a plane parallel to the surface being measured.

13. Square Yard (SY): Measured on a plane parallel to the surface being measured.

14. Ton: Measured as a short ton consisting of 2,000 pounds.

1.4 METHOD OF MEASUREMENT

A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:

1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.

MEASUREMENT AND PAYMENT 011250-3

2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:

a. As a result of changes in the work authorized by the CO.

b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.

c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.

4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.

5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

END OF SECTION 011250

October 2026

MOBILIZATION 011900-1

NEW MEADOWS BARN LBP & DEFERRED MAINTENANCE

SECTION 011900 - MOBILIZATION

PART 1 - GENERAL

1.1 SUMMARY

A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.

1.2 MEASUREMENT AND PAYMENT

A. The measurement shall be lump sum for mobilization. Payment shall be as follows:

1. Bond premiums will be reimbursed after receipt of the evidence of payment.

2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.

3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.

4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.

5. Progress payments for mobilization and preparatory work shall be subject to retainage.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 011900

SUBMITTAL PROCEDURES 013300-1

NEW MEADOWS BARN LBP & DEFERRED MAINTENANCE

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals.

B. See other specification section within this package for additional requirements on submittal.

1.2 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Allow 14 days for processing each re-submittal.

4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

C. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.

3. Include the following information on label for processing and recording action taken:

a. Project name.

b. Date.

c. Name and address of Contractor.

SUBMITTAL PROCEDURES 013300-2

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. If more than one item is shown on submittal sheet, identify item.

D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.

1.3 MEASUREMENT AND PAYMENT

A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.

PART 2 - PRODUCTS

2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)

A. General: Prepare and submit Action Submittals required by individual Specification Sections.

1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Wiring diagrams showing factory-installed wiring.

f. Compliance with recognized trade association standards.

g. Compliance with recognized testing agency standards.

SUBMITTAL PROCEDURES 013300-3

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Include the following information, as applicable:

a. Dimensions.

b. Identification of products.

c. Fabrication and installation drawings.

d. Roughing-in and setting diagrams.

e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.

f. Notation of dimensions established by field measurement.

2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.

D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.

E. Samples: Prepare physical units of materials or products, including the following:

1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies.

2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."

B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.

C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.

D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.

SUBMITTAL PROCEDURES 013300-4

E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.

PART 3 - EXECUTION

3.1 GENERAL

A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.

B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.

D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.

F. Requests for substitutions will only be considered if contractor submits the following:

1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.

Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.

2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.

3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.

4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.

3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications.

SUBMITTAL PROCEDURES 013300-5

END OF SECTION 013300

HISTORIC TREATMENT PROCEDURES 013591-1

NEW MEADOWS BARN LBP & DEFERRED MAINTENANCE

SECTION 013591 - HISTORIC TREATMENT PROCEDURES

PART 1 - GENERAL

A. This Section includes special procedures for historic treatment on Project including, but not limited to, the following:

1. Storage and protection of existing historic materials.

2. Temporary protection of historic materials during construction.

3. Historic treatment procedures.

1.2 DEFINITIONS

A. "Preservation": To apply measures necessary to sustain the existing form, integrity, and materials of a historic property. Work may include preliminary measures to protect and stabilize the property.

B. "Rehabilitation": To make possible a compatible use for a property through repair, alterations, and additions while preserving those portions or features that convey its historical, cultural, or architectural values.

C. "Restoration": To accurately depict the form, features, and character of a property as it appeared at a particular period of time by means of the removal of features from other periods in its history and the reconstruction of missing features from the restoration period.

D. "Reconstruction": To reproduce in the exact form and detail a building, structure, or artifact as it appeared at a specific period in time.

E. "Stabilize": To apply measures designed to reestablish a weather-resistant enclosure and the structural reinforcement of an item or portion of the building while maintaining the essential form as it exists at present.

F. "Protect and Maintain": To remove deteriorating corrosion, reapply protective coatings, and install protective measures such as temporary guards; to provide the least degree of intervention.

G. "Repair": To stabilize, consolidate, or conserve; to retain existing materials and features while employing as little new material as possible. Repair includes patching, piecing-in, splicing, consolidating, or otherwise reinforcing or upgrading materials. Within restoration, repair also includes limited replacement in kind, rehabilitation, and reconstruction, with compatible substitute materials for deteriorated or missing parts of features when there are surviving prototypes.

H. "Replace": To duplicate and replace entire features with new material in kind.

Replacement includes the following conditions:

HISTORIC TREATMENT PROCEDURES 013591-2

1. Duplication: Includes replacing elements damaged beyond repair or missing.

Original material is indicated as the pattern for creating new duplicated elements.

2. Replacement with New Materials: Includes replacement with new material when original material is not available as patterns for creating new duplicated elements.

3. Replacement with Substitute Materials: Includes replacement with compatible substitute materials. Substitute materials are not allowed, unless otherwise indicated.

I. "Remove": To detach items from existing construction and legally dispose of them off-site unless indicated to be removed and salvaged or removed and reinstalled.

J. "Remove and Reinstall": To detach items from existing construction, repair and clean them for reuse, and reinstall them where indicated.

K. "Existing to Remain" or "Retain": Existing items of construction that are not to be removed and that are not otherwise indicated to be removed and salvaged, or removed and reinstalled.

L. "Material in Kind": Material that matches existing materials, as much as possible, in species, cut, color, grain, and finish.

1.3 SUBMITTALS

A. Historic Treatment Program: Submit a written plan for each phase or process including protection of surrounding materials during operations. Describe in detail materials, methods, and equipment to be used for each phase of work.

B. Historic Treatment Specialist Qualifications: A firm that employs personnel, including supervisory personnel, experienced and skilled in the processes and operations indicated.

Must demonstrate successful rehabilitation of similar projects.

1.4 QUALITY ASSURANCE

A. Historic Treatment Preconstruction Conference: Conduct conference at Project site.

B. When providing historic preservation or rehabilitation services, the work shall be accomplished by or under the direct supervision of someone meeting the Secretary of the Interior’s Professional Qualification Standards for Historic Architecture.

1.5 STORAGE AND PROTECTION OF HISTORIC MATERIALS

A. Removed and Reinstalled Historic Materials:

1. Clean and repair historic items to functional condition adequate for intended reuse.

2. Pack or crate items after cleaning and repairing. Identify contents of containers.

3. Protect items from damage during transport and storage.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

HISTORIC TREATMENT PROCEDURES 013591-3

B. Existing Historic Materials to Remain: Protect construction indicated to remain against damage and soiling during historic treatment. When permitted by the Contracting Officer’s Representative items may be removed to a suitable, protected storage location during historic treatment and cleaned and reinstalled in their original locations after historic treatment operations are complete.

C. Storage and Protection: When removed from their existing location, store historic materials within a weathertight enclosure where they are protected from wetting by rain, snow, or ground water, and temperature variations. Secure stored materials to protect from theft.

1. Identify removed items with an inconspicuous mark indicating their original location.

1.6 PROJECT-SITE CONDITIONS

A. Exterior Cleaning and Repairing:

1. Proceed with the work only when forecasted weather conditions are favorable.

a. Wet Weather: Do not attempt repairs during rainy or foggy weather. Do not apply primer, paint, putty, or epoxy when the relative humidity is above 80 percent. Do not remove exterior elements of structures when rain is forecast or in progress.

b. Do not perform exterior wet work when the air temperature is below 40 deg F.

c. Do not begin cleaning, patching, or repairing when there is any likelihood of frost or freezing.

d. Do not begin cleaning when either the air or the surface temperature is below

45 deg F unless approved means are provided for maintaining a 45 deg F temperature of the air and materials during, and for 48 hours subsequent to, cleaning.

2. Perform cleaning and rinsing of the exterior only during daylight hours.

1.7 MEASUREMENT AND PAYMENT

A. No separate measurement and/or payment will be made for this Section.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 PROTECTION, GENERAL

A. Comply with manufacturer's written instructions for precautions and effects of products and procedures on adjacent building materials, components, and vegetation.

B. Ensure that supervisory personnel are present when work begins and during its progress.

C. Temporary Protection of Historic Materials during Construction:

HISTORIC TREATMENT PROCEDURES 013591-4

1. Protect existing materials during installation of temporary protections and construction. Do not deface or remove existing materials.

D. Protect landscape work adjacent to or within work areas as follows:

1. Use coverings that allow plants to breathe and remove coverings at the end of each day. Do not cover plant material with a waterproof membrane for more than 8 hours at a time.

3.2 HISTORIC TREATMENT PROCEDURES

A. The principal aim of preservation work is to halt the process of deterioration and stabilize the item's condition, unless otherwise indicated. Repair is required where specifically indicated. The following procedures shall be followed:

1. Replace (2) sides of the building siding in-kind.

2. Use traditional replacement materials to match the existing. New work shall not be distinguishable to the trained eye, on close inspection, from old work.

3. Record the work before the procedure with preconstruction photos and during the work with periodic construction photos.

B. Prohibit smoking by personnel performing work on or near historic structures.

C. Obtain Contracting Officer’s review and written approval in the form of a Constructive Change Directive or Supplemental Instruction before making changes or additions to construction or removing historic materials.

D. Notify Contracting Officer of visible changes in the integrity of material or components whether due to environmental causes including biological attack, UV degradation, freezing, or thawing; or due to structural defects including cracks, movement, or distortion.

1. Do not proceed with the work in question until directed by Contracting Officer.

E. Where missing features are indicated to be repaired or replaced, provide features whose designs are based on accurate duplications rather than on conjectural designs, subject to the approval of the Contracting Officer’s Representative and Historic Treatment Specialist.

F. Where Work requires existing features to be removed, cleaned, and reused, perform these operations without damage to the material itself, to adjacent materials, or to the substrate.

G. Identify new or replacement materials and features with inconspicuous, permanent marks to distinguish them from original materials. Record the legend of identification marks and the locations of these marks on Record Drawings.

H. When cleaning, match samples of existing materials that have been cleaned and identified for acceptable cleaning levels. Avoid over cleaning to prevent damage to existing materials during cleaning.

END OF SECTION 013951

SELECTIVE DEMOLITION 017320-1

NEW MEADOWS BARN LBP & DEFERRED MAINTENANCE

SECTION 017320 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes demolition and removal of the following:

1. Selected portions of a building or structure.

2. Repair procedures for selective demolition operations.

1.2 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.

B. Remove and Salvage: Detach items from existing construction and deliver them to Government.

C. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated.

D. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.

1.3 MATERIALS OWNERSHIP

A. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Government property, demolished materials shall become Contractor's property and shall be removed from Project site.

1.4 SUBMITTALS

A. Proposed Control Measures: Submit statement or drawing that indicates the measures proposed for use, proposed locations, and proposed time frame for their operation.

Identify options if proposed measures are later determined to be inadequate. Include measures for the following:

1. Dust control.

B. Predemolition Photographs or Videotape: Show existing conditions of adjoining construction and site improvements that might be misconstrued as damage caused by selective demolition operations. Submit before Work begins.

C. Landfill Records: Indicate receipt and acceptance of hazardous wastes by a landfill facility licensed to accept hazardous wastes.

SELECTIVE DEMOLITION 017320-2

1.5 QUALITY ASSURANCE

A. Demolition Firm Qualifications: An experienced firm that has specialized in demolition work similar in material and extent to that indicated for this Project.

B. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

C. Standards: Comply with ANSI A10.6 and NFPA 241.

D. Predemolition Conference: Conduct conference at Project site.

1.6 PROJECT CONDITIONS

A. Government will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Government operations will not be disrupted. Provide not less than 72 hours' notice to CO of activities that will affect Government operations.

B. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.

1. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from authorities having jurisdiction.

C. Government assumes no responsibility for condition of areas to be selectively demolished.

1. Conditions existing at time of inspection for bidding purpose will be maintained by Government as far as practical.

D. Hazardous Materials: Hazardous materials are present in building to be selectively demolished.

1. Hazardous material remediation is specified elsewhere in the Contract Documents.

E. Storage or sale of removed items or materials on-site will not be permitted.

F. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

PART 2 - PRODUCTS

2.1 REPAIR MATERIALS

A. Use repair materials identical to existing materials.

1. If identical materials are unavailable or cannot be used for exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible.

SELECTIVE DEMOLITION 017320-3

2. Use materials whose installed performance equals or surpasses that of existing materials.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.

B. Inventory and record the condition of items to be removed and reinstalled and items to be removed and salvaged.

C. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to CO.

3.2 UTILITY SERVICES

A. Existing Utilities: Maintain services indicated to remain and protect them against damage during selective demolition operations.

B. Do not interrupt existing utilities serving occupied or operating facilities unless authorized in writing by CO and authorities having jurisdiction. Provide temporary services during interruptions to existing utilities, as acceptable to CO and to authorities having jurisdiction.

1. Provide at least 72] hours' notice to CO if shutdown of service is required during changeover.

C. Utility Requirements: Locate, identify, disconnect, and seal or cap off indicated utilities serving areas to be selectively demolished.

1. Arrange to shut off indicated utilities with utility companies.

2. If utility services are required to be removed, relocated, or abandoned, provide temporary utilities before proceeding with selective demolition that bypass area of selective demolition and that maintain continuity of service to other parts of building.

3. Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit after bypassing.

3.3 PREPARATION

A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

1. Do not close or obstruct streets, walks, walkways, or other adjacent occupied or used facilities without permission from CO and authorities having jurisdiction.

SELECTIVE DEMOLITION 017320-4

Provide alternate routes around closed or obstructed traffic ways if required by governing regulations.

2. Erect temporary protection, such as walks, fences, railings, canopies, and covered passageways, where required by authorities having jurisdiction.

3. Protect existing site improvements, appurtenances, and landscaping to remain.

B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

C. Temporary Enclosures: Provide temporary enclosures for protection of existing building and construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weathertight enclosure for building exterior.

D. Temporary Partitions: Erect and maintain dustproof partitions and temporary enclosures to limit dust and dirt migration and to separate areas from fumes and noise.

E. Temporary Shoring: Provide and maintain interior and exterior shoring, bracing, or structural support to preserve stability and prevent movement, settlement, or collapse of construction to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

3.4 POLLUTION CONTROLS

A. Dust Control: Use water mist, temporary enclosures, and other suitable methods to limit spread of dust and dirt. Comply with governing environmental-protection regulations.

B. Disposal: Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

C. Cleaning: Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

3.5 SELECTIVE DEMOLITION

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations.

1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.

2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

3. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

SELECTIVE DEMOLITION 017320-5

B. Existing Facilities: Comply with CO’s requirements for using and protecting elevators, stairs, walkways, loading docks, building entries, and other building facilities during selective demolition operations.

C. Removed and Salvaged Items:

1. Clean salvaged items.

2. Pack or crate items after cleaning. Identify contents of containers.

3. Store items in a secure area until delivery to Government.

4. Transport items to Government storage area designated by CO.

5. Protect items from damage during transport and storage.

D. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse. Paint equipment to match new equipment.

2. Pack or crate items after cleaning and repairing. Identify contents of containers.

3. Protect items from damage during transport and storage.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

E. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by CO, items may be removed to a suitable, protected storage location during selective demolition [and cleaned] and reinstalled in their original locations after selective demolition operations are complete.

3.6 PATCHING AND REPAIRS

A. General: Promptly repair damage to adjacent construction caused by selective demolition operations.

B. Repairs: Where repairs to existing surfaces are required, patch to produce surfaces suitable for new materials.

1. Completely fill holes and depressions in existing masonry walls that are to remain with an approved masonry patching material applied according to manufacturer's written recommendations.

C. Finishes: Restore exposed finishes of patched areas and extend restoration into adjoining construction in a manner that eliminates evidence of patching and refinishing.

D. Floors and Walls: Where walls or partitions that are demolished extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish color, texture, and appearance. Remove existing floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.

3.7 DISPOSAL OF DEMOLISHED MATERIALS

SELECTIVE DEMOLITION 017320-6

A. General: Promptly dispose of demolished materials. Do not allow demolished materials to accumulate on-site.

B. Burning: Do not burn demolished materials.

C. Disposal: Transport demolished materials off Government property and legally disposes of them.

END OF SECTION 017320

LEAD ABATEMENT 024130-1

NEW MEADOWS BARN LBP & DEFERRED MAINTENANCE

SECTION 024130 - LEAD ABATEMENT

PART 1 - GENERAL

1.1 SCOPE

A. The work under this section covers the removal and proper disposal of lead-based paint from the identified surfaces.

B. The contractor shall provide all labor, materials, tools, equipment, services, testing, supervision and incidentals necessary to perform work of lead paint abatement and repainting of all structures. After abatement, the areas disturbed shall be cleaned, and tested in accordance with the procedures outlined below.

1.2 GENERAL REQUIREMENTS

A. All workers who perform the work for lead paint abatement described herein shall have successfully completed a training course in lead abatement within the previous five (5) years approved by the Federal Occupational Safety and Health (OSHA) regulations.

1.3 INSURANCE

A. In addition to insurance requirements stated elsewhere in the specifications, the Contractor shall provide the U.S. Forest Service with certificates as evidence that he possesses insurance to cover lead paint abatement work a minimum of $500,000.00 single limit for bodily injury and property damage limits of $1,000,000.00 per occurrence.

1.4 RECORDS TO BE SUBMITTED

A. The Contractor shall provide the names and addresses of the Sub-Contractors responsible for the lead paint abatement procedures.

B. The starting and completion dates of the abatement work.

C. A summary of the techniques used to comply with these regulations.

D. The Contractor shall mark on as-built drawings a note in bold letters where all surfaces with lead paint have been removed under this contract, and describing such locations.

E. The Contractor shall maintain environmental and biological monitoring records in accordance with OSHA's standard 29 CFR 1910.20.

F. The Contractor shall submit for U.S. Forest Service information and records, copies of all records indicating that the abatement work has been performed in compliance with all applicable regulations.

1.5 SUBMITTALS

LEAD ABATEMENT 024130-2

A. Certificates of training for all personnel who will be performing the work under this contract shall be submitted to the U.S. Forest Service.

B. The Contractor shall submit to the U.S. Forest Service product data and samples required by the specification sections. Product data shall be manufacturer’s catalog sheets, brochures, diagrams, schedules, performance charts, illustrations, material safety data sheets (MSDS), and other standard descriptive data. Submittal data shall be clearly marked to identify pertinent materials, products, or models and show performance characteristics and capacities. Samples shall be of sufficient size and quantity to clearly illustrate the functional characteristics of the product or material with integrally related parts and attachment devices.

C. The contractor shall submit a work plan to the Contracting Officer for approval describing removal techniques and plans. The contractor will describe the work in clear detail and show how they will comply with OSHA and EPA Regulations.

1.6 MEASUREMENT AND PAYMENT: No separate measurement and/or payment will be made for this Section.

PART 2 - PRODUCTS—SEE PART 3.

PART 3 - EXECTUTION

3.1 WORKER PROTECTION

A. Training: Any worker entering a dwelling unit known to contain lead-based paint for the purpose of removing or disturbing lead-based paint must have successfully completed training in Lead Paint Abatement Health and Safety Training. Contractor will adhere to OSHA regulation CFR 1910.1200 and 1910.1025.

B. Biological Monitoring: All workers must have baseline and post abatement blood lead level screenings determined by the whole blood lead method, utilizing Vena-Puncture technique. In addition, the Contractor shall have a physical performed on each employee and the Contracting Officer will recommend laboratories and/or clinics to be used for obtaining blood level tests. The blood tests will also be required at the end of each 30 day period, if the employee is working on the job. Ths test must be performed before workers enter a lead contaminated work areas. A worker will be removed from the job if his blood lead level is 30 ug/dl or greater. The Contractor shall be responsible for medical surveillance and record keeping.

C. Air Monitoring to Determine Respiratory Protection

1. The Contractor will provide all workers, foremen, and superintendents with properly fitted half-faced respirators approved by NIOSH and OSHA. Authorized visitors (i.e. Federal, State and Local inspectors) must provide a curent health and medical report certifying them as approved to wear half-face respirators. When respirators and disposable filters are employed, sufficient replacement filters will be provided by the Contractor for the workers and any visitors.

LEAD ABATEMENT 024130-3

2. The minimum respiratory protection required for this project is as follows:

a. Negative pressure, half mask, air purifying respirators, equipped with HEPA filters for airborne lead dust levels not in excess of 0.5 mg/g (10XPEL).

Contractors will base their bids on this type of respirator.

b. Full face piece, air purifying respirator, with HEPA filters for airborne dust levels not in excess of 2.5 mg/g (50XPEL).

c. Pressure demand, full face, supplied air respirators for airborne lead dust concentrations are expected to meet or exceed 50 mg/m 1000 XPEL).

3. All workers inside the work area will wear the proper respirator for the lead dust level generated.

4. Workers must be properly trained in the care, use and maintenance of respirators.

the Engineer will require that these workers have been fit tested and see that a fit test is performed and passed a day before entering the work area. A formal respiratory protection program must be implemented in accordance with OSHA 29

CFR 1910.134.

5. Respirators will not be removed until the worker enters the washing area of the decontamination chamber.

3.2 PERSONAL PROTECTIVE EQUIPMENT

A. Workers will wear full body disposable suits with hoods and booties. A TYVEK or similar type of suit may be worn. Suits will be worn inside the work area after the area passes pre-abatement inspection and shall remain in use until the area passes final clearance inspection. Light-weight nylon clothes may be worn under the suit but these clothes must be changed before leaving the work area and should be laundered separately.

B. Goggles with side shield will be worn when working with a material that may spash or fragment, or if protective eye wear is specified on the Material Safety Data Sheet (MSDS) for that product.

C. Additional respiratory protection by supplemental filters, such as organic vapor cartridges, may be needed when handling some coating products. Consult the (Material Safety Data Sheets) MSDS and obtain the proper filters as necessary.

3.3 PERSONAL HYGIENE PRACTICES

A. Personal Hygiene Practices: The abatement Contractor…