C04_SOW_1240LT26Q0163.pdf
PDF 409 KB Posted
- Attached to
- DNF Duck Creek Bunkhouse Roof Repairs
- Solicitation number
- 1240LT26Q0163
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a federal contract specification document for roof repairs at the Duck Creek Bunkhouse, a facility owned by the Dixie National Forest and operated by the USDA Forest Service, Region 4.
The project involves replacing a portion of the existing roof and roof edge damaged by a tree fall, as well as removal and replacement of water-damaged areas from recent rainstorms. The bunkhouse is located approximately 30 miles from Cedar City, Utah on UT-14, turning south onto FRS 059. The contract has a base bid timeline of 45 calendar days with an ultimate completion date of November 6, 2026, contingent upon weather. The contractor must submit a Waste Management Plan in PDF format within 14 days of the Notice to Proceed and is responsible for daily debris pickup with weekly container emptying. Materials storage and staging areas require Contracting Officer approval, and overnight camping on site is prohibited. The work includes standing seam metal roofing (24 gauge with PAC-Clad Kynar 500 two-coat finish and 20-year warranty), thermal insulation (multiple types including extruded polystyrene, molded polystyrene, polyisocyanurate, glass-fiber blanket, and glass-fiber board), rough carpentry with plywood sheathing, sheet metal flashing and trim, and joint sealants. Ice dam membrane underlayment (Vycor Ultra or Stormguard HT) and type 30 asphalt saturated fiberglass roofing felt are required. Payment is structured as lump sum for mobilization, with 50 percent payable after completion of five percent of work and remaining portions paid after ten percent completion and final acceptance. All submittals including product data, construction schedule, quality control plan, and waste management plan require Contracting Officer approval. The contractor must provide quality control sampling and testing through an approved testing agency and maintain as-built drawings throughout the project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| C05_Q and A_1240LT26Q0163.pdf | ||
| C04_Drawings_1240LT26Q0163.pdf | ||
| C04_SOI_1240LT26Q0163.xlsx | XLSX spreadsheet | |
| C04_Wage Determination_1240LT26Q0163.pdf | ||
| C04_CSS_Commercial Construction_1240LT26Q0163.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
DUCK CREEK BUNKHOUSE ROOF REPAIRS
1.1 SCOPE OF CONTRACT
A. This contract involves replacing a portion of the existing roof and roof edge damaged due to a tree fall at the Duck Creek Bunkhouse. This contact also includes removal and replacement of water damaged areas from recent rainstorms. The bunkhouse facility is owned by the Dixie National Forest.
1.2 PROJECT LOCATION
A. From Cedar City, begin on UT-14 and continue for approximately 30 miles. Turn south onto FRS 059; the project location is a few hundred feet on the west side of the road.
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. The site will be occupied during construction. The Contractor will be responsible for signing and limiting access to materials and construction areas for the public.
2. Use of Site: Verify locations for materials storage and construction with COR. Do not disturb portions of site beyond areas in which the COR specifies.
3. There is electrical service available for use at the site.
4. Water is available at the site for construction purposes.
5. Toilet facilities are available at the site.
1.4 WASTE MANAGEMENT AND DISPOSAL
A. Waste Management Plan: Submit a pdf copy of the plan within 14 days of date established for the Notice to Proceed.
B. Waste material and debris shall be picked up and secured on a daily basis. Containers must be emptied on a weekly basis unless more frequent emptying is needed.
Construction materials and debris shall not be allowed to become airborne or migrate into adjacent properties.
1.5 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The
Contractor must request in writing for approval from the CO to stage trailers (work) on site.
B. No overnight camping will be allowed on site.
C. The contractor shall acknowledge they have taken the necessary steps to determine the nature and location of work and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2
relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
1.6 ULTIMATE COMPLETION DATE
A. November 6, 2026 – contingent upon weather allowing completion of project.
CONTRACT TIME
B. Base Bid: 45 Calendar Days
SPECIFICATIONS
C. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made:
SECTION 011250 - MEASUREMENT AND PAYMENT
SECTION 011900 - MOBILIZATION
SECTION 013300 - SUBMITTAL PROCEDURES
SECTION 014100 - QUALITY CONTROL
SECTION 024100 - WASTE MATERIAL DISPOSAL
SECTION 061000 - ROUGH CARPENTRY
SECTION 072100 - THERMAL INSULATION
SECTION 076200 - SHEET METAL FLASHING AND TRIM
SECTION 079200 - JOINT SEALANTS
END OF SECTION C
AUGUST 2026
MEASUREMENT AND PAYMENT 011250-1
USDA FOREST SERVICE, R4
DUCK CREEK BUNKHOUSE ROOF REPAIRS
SECTION 011250 - MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.
B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.
1.2 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
1.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
1. Acre: Make longitudinal and transverse measurements for area computations horizontally.
2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.
3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.
4. Cubic Yard (CY): A measurement computed by one of the following methods:
a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.
MEASUREMENT AND PAYMENT 011250-2
Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
5. Each (EA): One complete unit, which may consist of one or more parts.
6. Gallons (GAL): The quantity shall be measured by any of the following methods:
a. Measured volume in container.
b. Metered volume by approved metering system.
c. Commercially package volume.
7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.
8. Linear Foot (LF): Measurement of work along its length from point-to-point;
parallel to the base or foundation. Do not measure overlaps.
9. Lump Sum (LS): One complete unit.
10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.
11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.
12. Square Foot (SF): Measured on a plane parallel to the surface being measured.
13. Square Yard (SY): Measured on a plane parallel to the surface being measured.
14. Ton: Measured as a short ton consisting of 2,000 pounds.
1.4 METHOD OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:
a. As a result of changes in the work authorized by the CO.
b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
MEASUREMENT AND PAYMENT 011250-3
4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.
5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 011250
MOBILIZATION 011900-1
DUCK CREEK BUNKHOUSE ROOF REPAIRS
SECTION 011900 - MOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
1.2 MEASUREMENT AND PAYMENT
A. The measurement shall be lump sum for mobilization. Payment shall be as follows:
1. Bond premiums will be reimbursed after receipt of the evidence of payment.
2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
5. Progress payments for mobilization and preparatory work shall be subject to retainage.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 011900
SUBMITTAL PROCEDURES 013300-1
USDA FOREST SERVICE, R-4
DUCK CREEK BUNKHOUSE ROOF REPAIRS
SECTION 013300 - SUBMITTAL PROCEDURES
3.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.
B. See other specification section within this package for additional requirements on submittal.
3.2 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Allow 14 days for processing each re-submittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
SUBMITTAL PROCEDURES 013300-2
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. If more than one item is shown on submittal sheet, identify item.
D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
3.3 MEASUREMENT AND PAYMENT
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 4 - PRODUCTS
4.1 ACTION SUBMITTALS – (Submittals requiring CO approval)
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Type of copy: Submit PDF copy of each submittal, unless otherwise indicated. CO will return marked copy. Mark up and retain returned copy as a Project Record Document.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Compliance with recognized trade association standards.
g. Compliance with recognized testing agency standards.
SUBMITTAL PROCEDURES 013300-3
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
f. Notation of dimensions established by field measurement.
2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.
E. Samples: Prepare physical units of materials or products, including the following:
1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
4.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Type of Copy: Submit a PDF copy of each submittal, unless otherwise indicated.
CO will not return copies.
2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."
B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.
C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.
D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.
SUBMITTAL PROCEDURES 013300-4
E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
PART 5 - EXECUTION
5.1 GENERAL
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.
D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.
F. Requests for substitutions will only be considered if contractor submits the following:
1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.
Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.
2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.
3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.
4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.
5.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required
SUBMITTAL PROCEDURES 013300-5
submittals for the project - the table is to assist the Contractor and may not be all inclusive
– additional submittals may be required by specific specifications:
TABLE 013000-1
Spec.
Section Section Title Subsect ion Required Submittal
C General Specifications 1.4A Waste Management Plan 013300 Submittal Procedures 2.1D Construction Schedule 014100 Quality Control 1.3 A Contractor Quality Control Plan 061000 Rough Carpentry 1.3A Product Data 072100 Thermal Insulation 1.2A Product Data 074050 Standing Seam Metal Roof 1.02 Samples 076200 Sheet Metal Flashing and Trim 1.3A Product Data
079200 Joint Sealants 1.2A Product Data
END OF SECTION 013300
QUALITY CONTROL 014100-1
DUCK CREEK BUNKHOUSE ROOF REPAIRS
SECTION 014100 - QUALITY CONTROL
PART 1 - GENERAL
1.1 This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.
1.2 QUALITY CONTROL
A. The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.
B. Special Tests and Inspections: Contractor will engage a testing agency to conduct required special tests and inspections. The Contractor shall authorize the testing agency to perform the required testing and inspections on the work completed. The authority shall include:
1. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.
2. Testing agency will re-test and re-inspect corrected work.
C. Retesting/Reinspecting: Contractor shall provide quality-control services for retesting and reinspection for replaced construction work or for work that failed to comply with the requirements under the contract.
1.3 SUBMITTALS
A. Contractor Quality Control Plan
1.4 MEASUREMENT AND PAYMENT
A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION
3.1 QUALITY CONTROL SYSTEM
QUALITY CONTROL 014100-2
A. General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.
3.2 CONTRACTOR QUALITY CONTROL PLAN
A. At the time of the preconstruction conference, the Contractor shall submit for approval a written Contractor Quality Control Plan.
1. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.
2. The Government reserves the right to require changes in the plan during the contract period as necessary.
3. No change in the approved plan may be made without written concurrence by the Contracting Officer.
4. At a minimum, the plan shall include the following:
a. A list of personnel responsible for quality control and assigned duties.
Include each person's qualifications.
b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
d. Methods of performing, documenting, and enforcing quality control of all work.
e. Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.
3.3 TEST AND INSPECTION REPORTS
A. Submit three copies of complete test results no later than three calendar days after the test was performed.
B. Submit failing test results and proposed remedial actions within four hours of noted deficiency.
C. Testing and Inspection Reports shall include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples, tests, or inspections.
5. Names of individuals performing tests and inspections.
6. Reference Specification Section(s).
7. Complete test or inspection data.
8. Test and inspection results and an interpretation of test results.
9. Ambient conditions at time sample was taken, tested, or inspected.
10. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.
QUALITY CONTROL 014100-3
11. Name and signature of laboratory inspector.
12. Recommendations on retesting and re-inspecting.
3.4 PERMITS, LICENSES, AND CERTIFICATES
A. For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.
3.5 AS-BUILT DRAWINGS
A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions.
These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.
3.6 SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS
A. Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification. The following table is a summary of the required sampling, testing, and certification for the project - the table is to assist the Contractor, but may not be all inclusive – additional submittals may be required by specific specification section:
END OF SECTION 014100
WASTE MATERIAL DISPOSAL 024100-1
DUCK CREEK BUNKHOUSE ROOF REPAIRS
SECTION 024100 - WASTE MATERIAL DISPOSAL
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the loading, handling, hauling, and placing of excess excavation material, unsuitable excavation material, clearing and grubbing debris, and construction and demolition debris.
1.2 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for work in this Section. Waste material disposal is considered incidental to other items of work shown in the Schedule of Items.
PART 2 - PRODUCTS – NOT APPLICABLE
PART 3 - EXECUTION
3.1 WASTE MATERIAL TO BE HAULED TO A LANDFILL
A. If no asbestos is detected during the preliminary investigations: All demolition materials, garbage, and other refuse generated shall be removed from the project site and legally disposed off of Government property in an approved landfill.
B. If asbestos is detected during the preliminary investigations: All demolition materials, garbage, and other refuse generated shall be removed from the project site and legally disposed at a landfill that accepts Category I nonfriable asbestos waste. This work and costs would be provided under the optional bid item.
C. All stumps, slash and other clearing and grubbing debris shall be hauled to a landfill.
D. The contractor is responsible for all costs and permits associated with landfill disposal.
E. The Government is not responsible for waste material upon its departure from the project site.
END OF SECTION 024100
ROUGH CARPENTRY 061000-1
DUCK CREEK BUNKHOUSE ROOF REPAIRS
SECTION 061000 - ROUGH CARPENTRY
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Wood blocking, cants, and nailers, plywood sheathing
1.2 DEFINITIONS
A. Dimension Lumber: Lumber of 2 inches nominal or greater but less than 5 inches nominal in least dimension.
B. Lumber grading agencies, and the abbreviations used to reference them, include the following:
1. NeLMA: Northeastern Lumber Manufacturers' Association.
2. NLGA: National Lumber Grades Authority.
3. RIS: Redwood Inspection Service.
4. WCLIB: West Coast Lumber Inspection Bureau.
5. WWPA: Western Wood Products Association.
1.3 ACTION SUBMITTALS
A. Product Data: For each type of process and factory-fabricated product.
1.4 MEASUREMENT AND PAYMENT
A. There will be separate measurement or payment for roof plywood sheathing work in this section. Payment will be included in the contract unit price for items shown in the schedule of items.
PART 2 - PRODUCTS
2.1 WOOD PRODUCTS, GENERAL
A. Lumber: DOC PS 20 and applicable rules of grading agencies indicated. If no grading agency is indicated, comply with the applicable rules of any rules-writing agency certified by the ALSC Board of Review. Grade lumber by an agency certified by the ALSC Board of Review to inspect and grade lumber under the rules indicated.
1. Factory mark each piece of lumber with grade stamp of grading agency.
2. For exposed lumber indicated to receive a stained or natural finish, mark grade stamp on end or back of each piece.
3. Dress lumber, S4S, unless otherwise indicated.
ROUGH CARPENTRY 061000-2
B. Maximum Moisture Content of Lumber: 19 percent unless otherwise indicated.
2.2 MISCELLANEOUS LUMBER
A. General: Provide miscellaneous lumber indicated and lumber for support or attachment of other construction, including the following:
1. Blocking.
2. Nailers.
3. Cants.
4. Grounds.
B. Dimension Lumber Items: Standard, Stud, or No. 3 grade lumber of any species.
C. Concealed Boards: Treated, 15 percent maximum moisture content and any of the following species and grades:
1. Northern species; No. 2 Common grade; NLGA.
2. Western woods; Construction or No. 2 Common grade; WCLIB or WWPA.
2.3 FASTENERS
A. General: Fasteners shall be of size and type indicated and shall comply with requirements specified in this article for material and manufacture.
1. Where rough carpentry is exposed to weather, in ground contact, pressure-preservative treated, or in area of high relative humidity, provide fasteners with hot-dip zinc coating complying with ASTM A 153/A 153M or of Type 304 stainless steel as noted in drawings.
B. Power-Driven Fasteners: Fastener systems with an evaluation report acceptable to authorities having jurisdiction, based on ICC-ES AC70.
C. Post-Installed Anchors: Fastener systems with an evaluation report acceptable to authorities having jurisdiction, based on ICC-ES AC01 as appropriate for the substrate.
D. Nails, Brads, and Staples: ASTM F 1667.
E. Power-Driven Fasteners: NES NER-272.
F. Wood Screws: ASME B18.6.1.
G. Lag Bolts: ASME B18.2.1.
H. Bolts: Steel bolts complying with ASTM A 307, Grade A; with ASTM A 563 hex nuts and, where indicated, flat washers.
I. Expansion Anchors: Anchor bolt and sleeve assembly of material indicated below with capability to sustain, without failure, a load equal to 6 times the load imposed when installed in unit masonry assemblies and equal to 4 times the load imposed when installed in concrete as determined by testing per ASTM E 488 conducted by a qualified independent testing and inspecting agency.
ROUGH CARPENTRY 061000-3
1. Material: Carbon-steel components, zinc plated to comply with ASTM B 633, Class Fe/Zn 5.
2. Material, where indicated: Stainless steel with bolts and nuts complying with ASTM F 593 and ASTM F 594, Alloy Group 1 or 2.
PART 3 - EXECUTION
3.1 INSTALLATION, GENERAL
A. Framing Standard: Comply with AF&PA's WCD 1, "Details for Conventional Wood Frame Construction," unless otherwise indicated.
B. Set rough carpentry to required levels and lines, with members plumb, true to line, cut, and fitted. Fit rough carpentry accurately to other construction. Locate furring, nailers, blocking, grounds, and similar supports to comply with requirements for attaching other construction.
C. Comply with AWPA M4 for applying field treatment to cut surfaces of preservative-treated lumber.
D. Where wood-preservative-treated lumber is installed adjacent to metal decking, install continuous flexible flashing separator between wood and metal decking.
E. Securely attach rough carpentry work to substrate by anchoring and fastening as indicated, complying with the following:
1. Table 2304.9.1, "Fastening Schedule," in ICC's International Building Code (IBC).
2. Table R602.3(1), "Fastener Schedule for Structural Members," and
3. ICC-ES evaluation report for fastener.
F. Sort and select lumber so that natural characteristics will not interfere with installation or with fastening other materials to lumber. Do not use materials with defects that interfere with function of member or pieces that are too small to use with minimum number of joints or optimum joint arrangement.
G. Securely attach rough carpentry work to substrate by anchoring and fastening as indicated, complying with the following:
1. NES NER-272 for power-driven fasteners.
2. Table 2304.9.1, "Fastening Schedule," in ICC's International Building Code.
3. Table 23-II-B-1, "Nailing Schedule," and Table 23-II-B-2, "Wood Structural Panel
Roof Sheathing Nailing Schedule," in ICBO's Uniform Building Code.
H. Use common wire nails, unless otherwise indicated. Select fasteners of size that will not fully penetrate members where opposite side will be exposed to view or will receive finish materials. Make tight connections between members. Install fasteners without splitting wood; do not countersink nail heads, unless otherwise indicated.
I. For exposed work, arrange fasteners in straight rows parallel with edges of members, with fasteners evenly spaced, and with adjacent rows staggered.
ROUGH CARPENTRY 061000-4
1. Comply with indicated fastener patterns where applicable.
2. Use finishing nails, unless otherwise indicated. Indicate locations of other fasteners, such as wood screws, bolts, and lag screws, on Drawings.
3.2 WOOD GROUND, SLEEPER, BLOCKING, AND NAILER INSTALLATION
A. Install where indicated and where required for screeding or attaching other work. Form to shapes indicated and cut as required for true line and level of attached work.
Coordinate locations with other work involved.
B. Attach items to substrates to support applied loading. Recess bolts and nuts flush with surfaces, unless otherwise indicated.
C. Where wood-preservative-treated lumber is installed adjacent to metal decking, install continuous flexible flashing separator between wood and metal decking.
3.3 PROTECTION
A. Protect rough carpentry from weather. If, despite protection, rough carpentry becomes wet, apply EPA-registered borate treatment. Apply borate solution by spraying to comply with EPA-registered label.
END OF SECTION 061000
THERMAL INSULATION 072100-1
DUCK CREEK BUNKHOUSE ROOF REPAIRS
SECTION 072100 - THERMAL INSULATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes: (EDIT AS NEEDED: REVIEW “TYPES OF INSULATION
DOCUMENT IN THIS FOLDER. I REMOVED ROCK WOOL AND GRAPHITE
FACED POLYISO FROM THIS SPEC. PLEASE DELETE THIS BLUE TEXT)
1. Extruded polystyrene foam-plastic board insulation.
2. Molded (expanded) polystyrene foam-plastic board insulation.
3. Polyisocyanurate foam-plastic board insulation.
4. Glass-fiber blanket insulation.
5. Glass-fiber board insulation.
1.2 ACTION SUBMITTALS
A. Product Data: For the following:
1. Extruded polystyrene foam-plastic board insulation.
2. Molded (expanded) polystyrene foam-plastic board insulation.
3. Polyisocyanurate foam-plastic board insulation.
4. Glass-fiber blanket insulation.
5. Glass-fiber board insulation.
B. Sustainable Design Submittals:
1. Product Data: For adhesives, indicating VOC content.
2. Laboratory Test Reports: For adhesives, indicating compliance with requirements for low-emitting materials.
1.3 INFORMATIONAL SUBMITTALS
A. Installer's Certification: Listing type, manufacturer, and R-value of insulation installed in each element of the building thermal envelope.
1. Sign, date, and post the certification in a conspicuous location on Project site.
B. Product test reports.
C. Research reports.
1.4 MEASUREMENT AND PAYMENT
A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items for work listed in the Schedule of Items.
http://www.arcomnet.com/sustainable_design.aspx?topic=11
THERMAL INSULATION 072100-2
PART 2 - PRODUCTS
2.1 EXTRUDED POLYSTYRENE FOAM-PLASTIC BOARD INSULATION
A. Extruded Polystyrene Board Insulation, Type X ASTM C578, Type X, 15-psi minimum compressive strength; unfaced.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. DiversiFoam Products.
b. DuPont de Nemours, Inc.
c. MBCI; Cornerstone Building Brands.
d. Owens Corning.
e. The Dow Chemical Company.
2. Flame-Spread Index: Not more than 25 when tested in accordance with ASTM E84.
3. Smoke-Developed Index: Not more than 450 when tested in accordance with
ASTM E84.
4. Fire Propagation Characteristics: Passes NFPA 285 testing as part of an approved assembly.
5. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
B. Extruded Polystyrene Board Insulation, Type IV ASTM C578, Type IV, 25-psi minimum compressive strength; unfaced.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. DiversiFoam Products.
b. DuPont de Nemours, Inc.
c. Owens Corning.
d. The Dow Chemical Company.
2. Flame-Spread Index: Not more than 25 when tested in accordance with ASTM E84.
3. Smoke-Developed Index: Not more than 450 when tested in accordance with
ASTM E84.
4. Fire Propagation Characteristics: Passes NFPA 285 testing as part of an approved assembly.
5. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
C. Extruded Polystyrene Board Insulation, Type VI ASTM C578, Type VI, 40-psi minimum compressive strength
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. DiversiFoam Products.
b. DuPont de Nemours, Inc.
http://www.specagent.com/Lookup?ulid=11256 http://www.specagent.com/Lookup?uid=123457173052 http://www.specagent.com/Lookup?uid=123457184269 http://www.specagent.com/Lookup?uid=123457173060 http://www.specagent.com/Lookup?uid=123457173054 http://www.specagent.com/Lookup?uid=123457173053 http://www.specagent.com/Lookup?ulid=11257 http://www.specagent.com/Lookup?uid=123457173197 http://www.specagent.com/Lookup?uid=123457184270 http://www.specagent.com/Lookup?uid=123457173199 http://www.specagent.com/Lookup?uid=123457173198 http://www.specagent.com/Lookup?ulid=11259 http://www.specagent.com/Lookup?uid=123457173216 http://www.specagent.com/Lookup?uid=123457184272
THERMAL INSULATION 072100-3
c. Owens Corning.
d. The Dow Chemical Company.
2. Flame-Spread Index: Not more than 25 when tested in accordance with ASTM E84.
3. Smoke-Developed Index: Not more than 450 when tested in accordance with
ASTM E84.
4. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
D. Extruded Polystyrene Board Insulation, Type VII: ASTM C578, Type VII, 60-psi minimum compressive strength.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. DiversiFoam Products.
b. DuPont de Nemours, Inc.
c. Owens Corning.
d. The Dow Chemical Company.
2. Flame-Spread Index: Not more than 25 when tested in accordance with ASTM E84.
3. Smoke-Developed Index: Not more than 450 when tested in accordance with
ASTM E84.
4. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
E. Extruded Polystyrene Board Insulation, Type V ASTM C578, Type V, 100-psi minimum compressive strength.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. DuPont de Nemours, Inc.
b. Owens Corning.
c. The Dow Chemical Company.
2. Flame-Spread Index: Not more than 25 when tested in accordance with ASTM E84.
3. Smoke-Developed Index: Not more than 450 when tested in accordance with
ASTM E84.
4. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
2.2 MOLDED (EXPANDED) POLYSTYRENE FOAM-PLASTIC BOARD INSULATION
A. Molded (Expanded) Polystyrene Board Insulation, Type I ASTM C578, Type I, 10-psi minimum compressive strength.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Amvic Building System.
http://www.specagent.com/Lookup?uid=123457173218 http://www.specagent.com/Lookup?uid=123457173217 http://www.specagent.com/Lookup?ulid=11261 http://www.specagent.com/Lookup?uid=123457173231 http://www.specagent.com/Lookup?uid=123457184274 http://www.specagent.com/Lookup?uid=123457173233 http://www.specagent.com/Lookup?uid=123457173232 http://www.specagent.com/Lookup?ulid=11263 http://www.specagent.com/Lookup?uid=123457184276 http://www.specagent.com/Lookup?uid=123457173251 http://www.specagent.com/Lookup?uid=123457173250 http://www.specagent.com/Lookup?ulid=11264 http://www.specagent.com/Lookup?uid=123457174429
THERMAL INSULATION 072100-4
b. Atlas Molded Products, a division of Atlas Roofing Corporation.
c. DiversiFoam Products.
d. Insulfoam; Carlisle Construction Materials Company.
2. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
B. Molded (Expanded) Polystyrene Board Insulation, Type VIII: ASTM C578, Type VIII, 13-psi minimum compressive strength.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Atlas Molded Products, a division of Atlas Roofing Corporation.
b. DiversiFoam Products.
2. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
C. Molded (Expanded) Polystyrene Board Insulation, Type II: ASTM C578, Type II, 15-psi minimum compressive strength.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Amvic Building System.
b. Atlas Molded Products, a division of Atlas Roofing Corporation.
c. DiversiFoam Products.
d. Insulfoam; Carlisle Construction Materials Company.
2. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
D. Molded (Expanded) Polystyrene Board Insulation, Type IX: ASTM C578, Type IX, 25-psi minimum compressive strength.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Atlas Molded Products, a division of Atlas Roofing Corporation.
b. DiversiFoam Products.
c. Insulfoam; Carlisle Construction Materials Company.
2. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
2.3 POLYISOCYANURATE FOAM-PLASTIC BOARD INSULATION
A. Polyisocyanurate Board Insulation, Foil Faced ASTM C1289, foil faced, Type I, Class 1 or 2.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
http://www.specagent.com/Lookup?uid=123457173073 http://www.specagent.com/Lookup?uid=123457173065 http://www.specagent.com/Lookup?uid=123457173066 http://www.specagent.com/Lookup?ulid=11265 http://www.specagent.com/Lookup?uid=123457173266 http://www.specagent.com/Lookup?uid=123457173258 http://www.specagent.com/Lookup?ulid=11266 http://www.specagent.com/Lookup?uid=123457173087 http://www.specagent.com/Lookup?uid=123457173085 http://www.specagent.com/Lookup?uid=123457173077 http://www.specagent.com/Lookup?uid=123457173078 http://www.specagent.com/Lookup?ulid=11267 http://www.specagent.com/Lookup?uid=123457173277 http://www.specagent.com/Lookup?uid=123457173269 http://www.specagent.com/Lookup?uid=123457173270 http://www.specagent.com/Lookup?ulid=11270
THERMAL INSULATION 072100-5
a. Atlas Polyiso Roof and Wall Insulation.
b. Carlisle Coatings & Waterproofing Inc.
c. DuPont de Nemours, Inc.
d. Firestone Building Products.
e. Johns Manville; a Berkshire Hathaway company.
f. Rmax, Inc.
g. The Dow Chemical Company.
2. Fire Propagation Characteristics: Passes NFPA 285 testing as part of an approved assembly.
3. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
2.4 GLASS-FIBER BLANKET INSULATION
A. Recycled Content: Postconsumer recycled content plus one-half of preconsumer recycled content not less than 10 percent.
B. Glass-Fiber Blanket Insulation, Unfaced ASTM C665, Type I; passing ASTM E136 for combustion characteristics.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Certainteed; SAINT-GOBAIN.
b. Johns Manville; a Berkshire Hathaway company.
c. Knauf Insulation.
d. Owens Corning.
2. Flame-Spread Index: Not more than 25 when tested in accordance with ASTM E84.
3. Smoke-Developed Index: Not more than 50 when tested in accordance with
ASTM E84.
4. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
C. Glass-Fiber Blanket Insulation, Polypropylene-Scrim-Kraft Faced: ASTM C665, Type II (nonreflective faced), Class A (faced surface with a flame-spread index of 25 or less);
Category 1 (membrane is a vapor barrier).
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Certainteed; SAINT-GOBAIN.
b. Johns Manville; a Berkshire Hathaway company.
c. Knauf Insulation.
d. Owens Corning.
2. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
http://www.specagent.com/Lookup?uid=123457173310 http://www.specagent.com/Lookup?uid=123457173309 http://www.specagent.com/Lookup?uid=123457184277 http://www.specagent.com/Lookup?uid=123457173303 http://www.specagent.com/Lookup?uid=123457173311 http://www.specagent.com/Lookup?uid=123457173302 http://www.specagent.com/Lookup?uid=123457173300 http://www.arcomnet.com/sustainable_design.aspx?topic=30 http://www.specagent.com/Lookup?ulid=11272 http://www.specagent.com/Lookup?uid=123457173105 http://www.specagent.com/Lookup?uid=123457173098 http://www.specagent.com/Lookup?uid=123457173097 http://www.specagent.com/Lookup?uid=123457173099 http://www.specagent.com/Lookup?ulid=11273 http://www.specagent.com/Lookup?uid=123457173107 http://www.specagent.com/Lookup?uid=123457173108 http://www.specagent.com/Lookup?uid=123457173109 http://www.specagent.com/Lookup?uid=123457173110
THERMAL INSULATION 072100-6
D. Glass-Fiber Blanket Insulation, Kraft Faced: ASTM C665, Type II (nonreflective faced), Class C (faced surface not rated for flame propagation); Category 1 (membrane is a vapor barrier).
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Certainteed; SAINT-GOBAIN.
b. Johns Manville; a Berkshire Hathaway company.
c. Knauf Insulation.
d. Owens Corning.
2. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
E. Glass-Fiber Blanket Insulation, Reinforced-Foil Faced ASTM C665, Type III (reflective faced), Class A (faced surface with a flame-spread index of 25 or less); Category 1 (membrane is a vapor barrier), faced with foil scrim, foil-scrim kraft, or foil-scrim polyethylene.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Certainteed; SAINT-GOBAIN.
b. Johns Manville; a Berkshire Hathaway company.
c. Knauf Insulation.
d. Owens Corning.
2. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
F. Glass-Fiber Blanket Insulation, Foil Faced ASTM C665, Type III (reflective faced), Class B (faced surface with a flame-propagation resistance of 0.12 W/sq. cm); Category 1 (membrane is a vapor barrier), faced with foil scrim, foil-scrim kraft, or foil-scrim polyethylene.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Certainteed; SAINT-GOBAIN.
b. Johns Manville; a Berkshire Hathaway company.
c. Knauf Insulation.
d. Owens Corning.
2. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
2.5 GLASS-FIBER BOARD INSULATION
A. Recycled Content: Postconsumer recycled content plus one-half of preconsumer recycled content not less than 10 percent.
http://www.specagent.com/Lookup?ulid=11274 http://www.specagent.com/Lookup?uid=123457173118 http://www.specagent.com/Lookup?uid=123457173120 http://www.specagent.com/Lookup?uid=123457173119 http://www.specagent.com/Lookup?uid=123457173121 http://www.specagent.com/Lookup?ulid=11275 http://www.specagent.com/Lookup?uid=123457173129 http://www.specagent.com/Lookup?uid=123457173131 http://www.specagent.com/Lookup?uid=123457173130 http://www.specagent.com/Lookup?ulid=11276 http://www.specagent.com/Lookup?uid=123457173149 http://www.specagent.com/Lookup?uid=123457173142 http://www.specagent.com/Lookup?uid=123457173141 http://www.specagent.com/Lookup?uid=123457173143 http://www.arcomnet.com/sustainable_design.aspx?topic=30
THERMAL INSULATION 072100-7
B. Glass-Fiber Board Insulation, Unfaced ASTM C612, Type IA; unfaced.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Certainteed; SAINT-GOBAIN.
b. Johns Manville; a Berkshire Hathaway company.
c. Knauf Insulation.
d. Owens Corning.
2. Flame-Spread Index: Not more than 25 when tested in accordance with ASTM E84.
3. Smoke-Developed Index: Not more than 50 when tested in accordance with
ASTM E84.
4. Nominal Density: 3 lb/cu. ft. .
5. Thermal Resistivity: 4.3 deg F x h x sq. ft./Btu x in. at 75 deg F.
6. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
C. Glass-Fiber Board Insulation, Faced ASTM C612, Type IA; faced on one side with foil-scrim-kraft or foil-scrim-polyethylene vapor retarder.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a. Certainteed; SAINT-GOBAIN.
b. Johns Manville; a Berkshire Hathaway company.
c. Knauf Insulation.
d. Owens Corning.
2. Flame-Spread Index: Not more than 25 when tested in accordance with ASTM E84.
3. Smoke-Developed Index: Not more than 50 when tested in accordance with
ASTM E84.
4. Nominal Density: 3 lb/cu. ft..
5. Thermal Resistivity: 4.3 deg F x h x sq. ft./Btu x in. at 75 deg F
6. Labeling: Provide identification of mark indicating R-value of each piece of insulation 12 inches and wider in width.
2.6 MINERAL-WOOL BLANKET INSULATION
A. Mineral-Wool Blanket Insulation, Unfaced ASTM C665, Type I (blankets without membrane facing); consisting of fibers; passing ASTM E136 for combustion characteristics.
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
a.…