C04 SOW_1240LT26Q0078.pdf
PDF 483 KB Posted
- Solicitation number
- 1240LT26Q0078
- Issued by
-
Department of Agriculture Forest Service
About this file
This is a federal contract specification document for construction of a single vault precast concrete toilet facility at the Darby Canyon Wind Caves Trailhead in the Caribou-Targhee National Forest, Teton County, Wyoming, approximately 12.5 miles southeast of Driggs, Idaho.
The project scope includes hauling, excavating, installing a precast concrete single vault toilet structure, backfilling, site grading, and cleanup. The precast concrete vault restroom building must be manufactured in a PCI-certified plant and designed to meet snow loads of 200 lbs/ft², wind loads of 90 mph (Exposure C), and seismic Category E per the 2012 International Building Code, with ADA compliance. The vault structure requires a minimum 1,000-gallon capacity with a polyethylene liner, sloped floor (minimum 1 inch per foot toward cleanout), 12-inch diameter HDPE vent stack extending 3 feet above roof peak with bird screening, and a steel cleanout cover with gasket seal. Building components include 5-inch minimum floor slab thickness, 4-inch average wall thickness, 4.25-inch minimum roof thickness with sloped shed or gabled design, wood-textured barnwood form liners on walls, wood shake texture on roof, and colored concrete (roof and walls). Interior and exterior finishes include stains, sealers, paints in specified colors (Java Brown, Sand Beige, White, Gray), stainless steel hardware, steel doors with spring hinges and mortised deadbolts, grab bars, toilet paper dispensers, coat hooks, and ADA-compliant signage with raised pictograms and braille.
Site conditions include no utilities or toilet facilities available; all construction equipment must be pressure-washed before entering National Forest lands. The contractor must submit a traffic control plan approved by the Contracting Officer and Wyoming Department of Transportation per MUTCD standards. All concrete must achieve 4,500 psi minimum strength at 28 days with specified cement type (ASTM C150 Type II, IIA, or III), maximum water-cement ratio of 0.45, and proper curing for six days minimum. Excavation must be completed prior to building delivery with minimum one-week lead time; backfill shall be placed in 8-inch lifts with three passes of mechanical compactor. No separate payment is provided for mobilization beyond standard contract terms, traffic control, waste disposal, clearing and grubbing, or earthwork—all costs are considered incidental to the primary pay item for the installed precast vault restroom building. Payment is structured as lump sum for the complete installed building including all work within 10 feet of the structure.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
0415 CONST DARBY CANYON PRECAST SINGLE VAULT TOILET
1.1 SCOPE OF CONTRACT
A. This project includes hauling and installing a single vault precast toilet at the Darby Canyon Wind Caves Trailhead.
B. The work includes excavation, backfill and clean-up for the one-way haul and installation of a single vault precast toilet at the Darby Canyon Wind Caves Trailhead.
C. Quantities associated with these options are identified in the Schedule of Items.
1.2 PROJECT LOCATION
A. The project is located in the Teton Basin Ranger District of the Caribou-Targhee National Forest, Teton County, Wyoming, in Section 14, Township 43 North, Range 118 West. It is located approximately 12.5 miles Southeast of Driggs, Idaho. The project may be accessed from Idaho State Highway 33 and Darby Canyon Road. (43.6865°N, - 110.9691°W)
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:
1. Construction sites will be closed to the public during construction. The Forest Service will issue a closure order to the public. The Contractor will be responsible for signing and limiting public access.
2. All construction equipment shall be pressure washed before entering National Forest System lands. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.
3. Utilities are not available at the site for construction purposes.
4. Toilet facilities are not available at the site.
1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the COR and Wyoming Department of Transportation. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2
shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.
1.5 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage trailers on site.
B. No overnight camping will be allowed on site.
1.6 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature
1.7 and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
SPECIFICATIONS
A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.
SECTION 011250 - MEASUREMENT AND PAYMENT
SECTION 011900 - MOBILIZATION
SECTION 013300 - SUBMITTAL PROCEDURES
SECTION 014100 - QUALITY CONTROL
SECTION 017700 - CLOSEOUT PROCEDURES
SECTION 024100 - WASTE MATERIAL DISPOSAL
SECTION 133402 - PRECAST CONCRETE VAULT RESTROOM BUILDING
SECTION 311000 - CLEARING AND GRUBBING
SECTION 312000 - EARTHWORK
SECTION 321204 - CRUSHED AGGREGATE BASE OR SURFACE COURSE
END OF SECTION C
February 2026
MEASUREMENT AND PAYMENT 011250-1
USDA FOREST SERVICE, R4
0415 CONST DARBY CANYON PRECAST SINGLE VAULT TOILET
SECTION 011250 - MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.
B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.
1.2 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.
3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.
5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.
6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.
B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."
MEASUREMENT AND PAYMENT 011250-2
1.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
1. Acre: Make longitudinal and transverse measurements for area computations horizontally.
2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.
3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.
4. Cubic Yard (CY): A measurement computed by one of the following methods:
a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.
Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
5. Each (EA): One complete unit, which may consist of one or more parts.
6. Gallons (GAL): The quantity shall be measured by any of the following methods:
a. Measured volume in container.
b. Metered volume by approved metering system.
c. Commercially package volume.
7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.
8. Linear Foot (LF): Measurement of work along its length from point-to-point;
parallel to the base or foundation. Do not measure overlaps.
9. Lump Sum (LS): One complete unit.
10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.
11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.
12. Square Foot (SF): Measured on a plane parallel to the surface being measured.
13. Square Yard (SY): Measured on a plane parallel to the surface being measured.
14. Ton: Measured as a short ton consisting of 2,000 pounds.
1.4 METHOD OF MEASUREMENT
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.
MEASUREMENT AND PAYMENT 011250-3
2. DESIGNED QUANTITIES (DQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:
a. As a result of changes in the work authorized by the CO.
b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.
c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.
3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.
4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.
5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION (NOT APPLICABLE)
END OF SECTION 011250
MOBILIZATION 011900-1
0415 CONST DARBY CANYON PRECAST SINGLE VAULT TOILET
SECTION 011900 - MOBILIZATION
PART 1 - GENERAL
1.1 SUMMARY
A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
1.2 MEASUREMENT AND PAYMENT
A. The measurement shall be lump sum for mobilization. Payment shall be as follows:
1. Bond premiums will be reimbursed after receipt of the evidence of payment.
2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
5. Progress payments for mobilization and preparatory work shall be subject to retainage.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
END OF SECTION 011900
SUBMITTAL PROCEDURES 013300-1
0415 CONST DARBY CANYON PRECAST SINGLE VAULT TOILET
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.
B. See other specification section within this package for additional requirements on submittal.
1.2 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.
1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.
2. If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Allow 14 days for processing each re-submittal.
4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.
C. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
SUBMITTAL PROCEDURES 013300-2
c. Name and address of Contractor.
d. Name of manufacturer.
e. Unique identifier, including revision number.
f. Number and title of appropriate Specification Section.
g. Drawing number and detail references, as appropriate.
h. If more than one item is shown on submittal sheet, identify item.
D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.
E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.
F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.
1.3 MEASUREMENT AND PAYMENT
A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the schedule of items.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Compliance with recognized trade association standards.
g. Compliance with recognized testing agency standards.
SUBMITTAL PROCEDURES 013300-3
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.
1. Preparation: Include the following information, as applicable:
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
f. Notation of dimensions established by field measurement.
2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 5 day of commencement of work.
E. Samples: Prepare physical units of materials or products, including the following:
1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies.
2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."
B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.
C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.
D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.
SUBMITTAL PROCEDURES 013300-4
E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.
PART 3 - EXECUTION
3.1 GENERAL
A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.
B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.
C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.
D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.
F. Requests for substitutions will only be considered if contractor submits the following:
1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution.
Submit additional information if required by Contracting Officer. All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.
2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.
3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.
4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.
3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required
SUBMITTAL PROCEDURES 013300-5
submittals for the project - the table is to assist the Contractor and may not be all inclusive
– additional submittals may be required by specific specifications:
TABLE 013000-1
Spec.
Section
Section Title Subsection Required Submittal
C General Specifications 1.4A Traffic Control Plan
013300 Submittal Procedures 2.1D Construction Schedule
014100 Quality Control
1.3 A Contractor quality control
plan
014100 Quality Control
1.3 B Permits, Licenses, and
Certificates
014100 Quality Control 1.3 C Test and inspection reports
014100 Quality Control 1.3 D As-Built drawings
133402 Precast Concrete Vault Restroom Building
1.2A Manufacturer’s Literature
133402 Precast Concrete Vault Restroom Building
1.2B Shop Drawings
133402 Precast Concrete Vault Restroom Building
1.2C Design Calculations
133402 Precast Concrete Vault Restroom Building
1.2D Concrete Delivery Certificates
312000 Earthwork
1.3A Bedding and Backfill Certification
312000 Earthwork 1.3A Sieve Analysis
312000 Earthwork 1.3B Product Data
321204 Crushed Aggregate Base or Surface
Course
1.2A Aggregate Base – Source, Gradation, Material
Properties
END OF SECTION 013300
QUALITY CONTROL 014100-1
0415 CONST DARBY CANYON PRECAST SINGLE VAULT TOILET
SECTION 014100 - QUALITY CONTROL
PART 1 - GENERAL
1.1 This work shall consist of providing quality control in conformance with the inspection, testing, and product certification requirements of this contract to ensure compliance with the drawings and specifications. The Contractor shall provide all personnel, equipment, tests, and reports necessary to meet the requirements of the contract.
1.2 QUALITY CONTROL
A. The Contractor shall provide and maintain a quality control system that will ensure all services, supplies, and construction work required under this contract conforms to the contract requirements. The Contractor shall perform, or cause to be performed, the sampling, inspection, and testing required to substantiate that all services, supplies, and construction conform to the contract requirements.
B. Special Tests and Inspections: Contractor will engage a testing agency to conduct required special tests and inspections. The Contractor shall authorize the testing agency to perform the required testing and inspections on the work completed. The authority shall include:
1. Testing agency will interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the Contract Documents.
2. Testing agency will re-test and re-inspect corrected work.
C. Retesting/Reinspecting: Contractor shall provide quality-control services for retesting and reinspection for replaced construction work or for work that failed to comply with the requirements under the contract.
1.3 SUBMITTALS
A. Contractor Quality Control Plan
B. Permits, Licenses, and Certificates
C. Test and Inspection Reports
D. As-Built Drawings
1.4 MEASUREMENT AND PAYMENT
A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.
PART 2 - PRODUCTS (Not Applicable)
QUALITY CONTROL 014100-2
PART 3 - EXECUTION
3.1 QUALITY CONTROL SYSTEM
A. General: Perform required testing, inspections, sampling, and similar services per direction specified in the contract drawings and specifications and in accordance with established industry standards.
3.2 CONTRACTOR QUALITY CONTROL PLAN
A. At the time of the preconstruction conference, the Contractor shall submit for approval a written Contractor Quality Control Plan.
1. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.
2. The Government reserves the right to require changes in the plan during the contract period as necessary.
3. No change in the approved plan may be made without written concurrence by the Contracting Officer.
4. At a minimum, the plan shall include the following:
a. A list of personnel responsible for quality control and assigned duties.
Include each person's qualifications.
b. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
c. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
d. Methods of performing, documenting, and enforcing quality control of all work.
e. Methods of monitoring and controlling environmental pollution and contamination as required by all applicable regulations and laws.
3.3 TEST AND INSPECTION REPORTS
A. Submit three copies of complete test results no later than three calendar days after the test was performed.
B. Submit failing test results and proposed remedial actions within four hours of noted deficiency.
C. Testing and Inspection Reports shall include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples, tests, or inspections.
5. Names of individuals performing tests and inspections.
6. Reference Specification Section(s).
7. Complete test or inspection data.
QUALITY CONTROL 014100-3
8. Test and inspection results and an interpretation of test results.
9. Ambient conditions at time sample was taken, tested, or inspected.
10. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.
11. Name and signature of laboratory inspector.
12. Recommendations on retesting and reinspecting.
3.4 PERMITS, LICENSES, AND CERTIFICATES
A. For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.
3.5 AS-BUILT DRAWINGS
A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions.
These drawings shall be maintained in a current condition and shall be available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.
3.6 SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS
A. Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification.
END OF SECTION 014100
CLOSEOUT PROCEDURES 017700-1
0415 CONST DARBY CANYON PRECAST SINGLE VAULT TOILET
SECTION 017700 - CLOSEOUT PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:
1. Substantial Completion procedures.
2. Final completion procedures.
3. Warranties.
4. Final cleaning.
5. Repair work.
1.2 ACTION SUBMITTALS
A. Product Data: For cleaning agents.
B. Contractor's List of Incomplete Items: Initial submittal at Substantial Completion.
C. Certified List of Incomplete Items: Final submittal at Final Completion.
1.3 MAINTENANCE MATERIAL SUBMITTALS
A. Schedule of Maintenance Material Items: For maintenance material submittal items specified in other Sections.
1.4 SUBSTANTIAL COMPLETION PROCEDURES
A. Contractor's List of Incomplete Items: Prepare and submit a list of items to be completed and corrected (Contractor's punch list).
B. Submittals Prior to Substantial Completion: Complete the following a minimum of 10 days prior to requesting inspection for determining date of Substantial Completion. List items below that are incomplete at time of request.
1. Submit closeout submittals specified in other Division 01 Sections, including project record documents, operation and maintenance manuals, final completion construction photographic documentation, and similar final record information.
2. Submit closeout submittals specified in individual Sections, including specific warranties, workmanship bonds, maintenance service agreements, final certifications, and similar documents.
3. Submit maintenance material submittals specified in individual Sections, including tools, spare parts, extra materials, and similar items, and deliver to location designated by Construction Manager. Label with manufacturer's name and model number where applicable.
CLOSEOUT PROCEDURES 017700-2
4. Submit test/adjust/balance records.
5. Submit sustainable design submittals not previously submitted.
6. Submit changeover information related to Government’s occupancy, use, operation, and maintenance.
C. Procedures Prior to Substantial Completion: Complete the following a minimum of 10 days prior to requesting inspection for determining date of Substantial Completion. List items below that are incomplete at time of request.
1. Make final changeover of permanent locks and deliver keys to COR. Advise Government’s personnel of changeover in security provisions.
2. Instruct COR in operation, adjustment, and maintenance of products, equipment, and systems. Submit demonstration and training video recordings.
3. Terminate and remove temporary facilities from Project site, along with mockups, construction tools, and similar elements.
4. Complete final cleaning requirements, including touchup painting.
5. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.
D. Inspection: Submit a written request for inspection to determine Substantial Completion a minimum of 10 days prior to date the work will be completed and ready for final inspection and tests. On receipt of request the COR will either proceed with inspection or notify Contractor of unfulfilled requirements. The COR will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by the COR, that must be completed or corrected before certificate will be issued.
1. Reinspection: Request reinspection when the work identified in previous inspections as incomplete is completed or corrected.
2. Results of completed inspection will form the basis of requirements for final completion.
1.5 FINAL COMPLETION PROCEDURES
A. Preliminary Procedures: Before requesting final inspection for determining final completion, complete the following:
1. Submit a final Application for Payment.
2. Certified List of Incomplete Items: Submit certified copy of COR’s Substantial
Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by COR. Certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.
3. Submit pest-control final inspection report and warranty.
4. Instruct Government’s personnel in operation, adjustment, and maintenance of products, equipment, and systems. Submit demonstration and training video recordings.
B. Inspection: Submit a written request for final inspection to determine acceptance. On receipt of request, COR will either proceed with inspection or notify Contractor of
CLOSEOUT PROCEDURES 017700-3
unfulfilled requirements. COR will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.
1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.
1.6 LIST OF INCOMPLETE ITEMS (PUNCH LIST)
A. Organization of List: Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.
1. Organize list of spaces in sequential order.
2. Organize items applying to each space by major element, including categories for ceiling, individual walls, floors, equipment, and building systems.
3. Submit list of incomplete items in the following format:
a. MS Excel electronic file. COR will return annotated copy.
1.7 SUBMITTAL OF PROJECT WARRANTIES
A. Time of Submittal: Submit written warranties on request of COR for designated portions of the Work where commencement of warranties other than date of Substantial Completion is indicated, or when delay in submittal of warranties might limit Owner's rights under warranty.
B. Organize warranty documents into an orderly sequence based on the table of contents of the Project Manual.
1. Bind warranties and bonds in heavy-duty, three-ring, vinyl-covered, loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8- 1/2-by-11-inch paper.
2. Provide heavy paper dividers with plastic-covered tabs for each separate warranty.
Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.
3. Identify each binder on the front and spine with the typed or printed title "WARRANTIES," Project name, and name of Contractor.
4. Provide a flash drive with training videos as a part of the manual.
C. Provide additional copies of each warranty to include in operation and maintenance manuals.
1.8 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for work in this section. Payment will be included at the contract unit price for items shown on the Schedule of Items.
PART 2 - PRODUCTS
CLOSEOUT PROCEDURES 017700-4
2.1 MATERIALS
A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.
1. Use cleaning products that comply with Green Seal's GS-37, or if GS-37 is not applicable, use products that comply with the California Code of Regulations maximum allowable VOC levels.
2. Select cleaning agents that are listed in the USDA Bio Preferred website.
https://www.biopreferred.gov/BioPreferred/faces/catalog/Catalog.xhtml
PART 3 - EXECUTION
3.1 FINAL CLEANING
A. General: Perform final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.
B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program. Comply with manufacturer's written instructions.
1. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a designated portion of Project:
a. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.
b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits.
c. Rake grounds that are neither planted nor paved to a smooth, even-textured surface.
d. Remove tools, construction equipment, machinery, and surplus material from Project site.
e. Remove snow and ice to provide safe access to building.
f. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Restore reflective surfaces to their original condition.
g. Sweep concrete floors broom clean in unoccupied spaces.
h. Clean transparent materials, including mirrors and glass in doors and windows. Remove glazing compounds and other noticeable, vision-obscuring materials. Replace chipped or broken glass and other damaged transparent materials. Polish mirrors and glass, taking care not to scratch surfaces.
i. Remove labels that are not permanent.
https://www.biopreferred.gov/BioPreferred/faces/catalog/Catalog.xhtml
CLOSEOUT PROCEDURES 017700-5
j. Leave Project clean and ready for occupancy.
3.2 REPAIR OF THE WORK
A. Complete repair and restoration operations before requesting inspection for determination of Substantial Completion.
B. Repair or remove and replace defective construction. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment. Where damaged or worn items cannot be repaired or restored, provide replacements. Remove and replace operating components that cannot be repaired. Restore damaged construction and permanent facilities used during construction to specified condition.
1. Remove and replace chipped, scratched, and broken glass, reflective surfaces, and other damaged transparent materials.
2. Touch up and otherwise repair and restore marred or exposed finishes and surfaces.
Replace finishes and surfaces that that already show evidence of repair or restoration.
a. Do not paint over "UL" and other required labels and identification, including mechanical and electrical nameplates. Remove paint applied to required labels and identification.
3. Replace parts subject to operating conditions during construction that may impede operation or reduce longevity.
END OF SECTION 017700
FEBRUARY 2022
WASTE MATERIAL DISPOSAL 024100-1
0415 CONST DARBY CANYON PRECAST SINGLE VAULT TOILET
SECTION 024100 - WASTE MATERIAL DISPOSAL
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the loading, handling, hauling, and placing of excess excavation material, unsuitable excavation material, clearing and grubbing debris, and construction and demolition debris.
1.2 MEASUREMENT AND PAYMENT
A. There will be no separate measurement or payment for work in this Section. Waste material disposal is considered incidental to other items of work shown in the Schedule of Items.
PART 2 - PRODUCTS – NOT APPLICABLE
PART 3 - EXECUTION
3.1 WASTE MATERIAL TO BE HAULED TO A DISPOSAL AREA
A. All excavated material not used in the construction of embankments or backfilling of trenches, or other excess material resulting from the excavation and embankment operation shall be hauled to a disposal area.
B. All stumps, slash and other clearing and grubbing debris shall be hauled to a disposal area.
C. Disposal Area: All waste material above shall be hauled to the disposal area on Government property as designated by the Contracting Officer.
1. Waste material shall be piled and compacted to form a dense layer.
2. The size and shape of the piled waste material shall be designated by the
Contracting Officer.
3. The piled material shall be covered with soil to a uniform depth of six inches minimum and sloped to 2:1 or flatter.
4. The disposal site shall be left suitable for seeding.
3.2 WASTE MATERIAL TO BE HAULED TO A LANDFILL
A. All demolition materials, garbage, and other refuse generated shall be removed from the project site and legally disposed off of Government property in an approved landfill.
B. The contractor is responsible for all costs and permits associated with landfill disposal.
WASTE MATERIAL DISPOSAL 024100-2
C. The Government is not responsible for waste material upon its departure from the project site.
END OF SECTION 024100
PRECAST CONCRETE VAULT RESTROOM BUILDING 133402-1
0415 CONST DARBY CANYON PRECAST SINGLE VAULT TOILET
SECTION 133402 - PRECAST CONCRETE VAULT RESTROOM BUILDING
PART 1 - GENERAL
1.1 SUMMARY
A. This section applies to the fabrication and installation of a precast concrete Vault Restroom building, including shipment to site, all work necessary to completely fabricate, and installation of other manufactured accessories needed or specified in this section for a complete Vault Restroom.
B. Related sections include the following:
1. Section 024100 “Waste Material Disposal.”
2. Section 311000 “Clearing and Grubbing.”
3. Section 312000 “Earthwork.”
4. Section 321204 “Crushed Aggregate Base or Surface Course.”
1.2 SUBMITTALS
A. Manufacturer’s Literature: Submit literature for the following items to the Contracting Officer (CO) for approval within 10 day after award of contract. Drawings and literature must be marked to show the exact model, size, and color proposed.
1. Door, louvered vents, and door hardware.
2. Paint, interior and exterior.
3. Caulk, ground and adhesive.
4. Concrete color additive, stains, concrete curing compound and concrete sealer.
B. Shop Drawings: Submit four sets of shop drawings of the Vault Restroom stamped by a Professional Engineer.
C. Design Calculations: Submit two sets of design calculations showing that the building is designed for the structural loads required, fabrication and transportation loads, and crack prevention and control.
D. Concrete Delivery Certificates: Supplier shall furnish a certificate with each truckload of concrete delivered showing the items in the following list. Submit these certificates to the CO upon delivery of the Vault Restroom.
1. Weight of cement in each load.
2. Weight of fine aggregate in each load.
3. Weight of coarse aggregate in each load.
4. Weight of water in each load.
5. Time of day cement was added to the aggregate and water.
1.3 MEASUREMENT AND PAYMENT
PRECAST CONCRETE VAULT RESTROOM BUILDING 133402-2
A. Payment will be lump sum for each Pre-cast Concrete Vault Restroom installed including all work within 10 feet of the building as shown on the drawings. Payment shall include all work associated with clearing, excavation, fill, aggregate, backfill and grading necessary to complete the item.
PART 2 - PRODUCTS
2.1 PRECAST VAULT RESTROOM
A. Design criteria
1. Snow Load: 200 lbs/ft2
2. Wind Load: 90 mph, exposure C from 2012 International Building Code
3. Seismic Load: Category E from 2012 International Building Code
4. Designed to meet the requirements of the Americans with Disabilities Act
Requirements and Uniform Federal Accessibility Standard including as of the date of these specifications.
5. Design incorporates all design aspects of Sweet Smelling Technology as outlined by Brian Cook for the U.S. Forest Service. ("In Depth Design and Maintenance Manual for Vault Toilets" - July 1991 - Publication No. 9123 1601)
B. Quality: Manufactured in a Precast Concrete Institute (PCI) Certified Plant for the type of product provided.
C. Manufacturers of precast concrete Vault Restrooms include, but are not limited to, the following:
1. CXT Incorporated- Building Division, Spokane, WA, (509) 921-8766, www.cxtinc.com
2. Missoula Concrete Construction, Missoula, MT, (406) 549-9682, www.missoulaconcrete.com
2.2 BUILDING WALLS AND SLAB
A. Floor Slab: 5-inch minimum thickness.
B. Walls: 4-inch average thickness, 3-inch minimum wall thickness at the top of the walls.
C. Roof: 4 ¼ inch minimum concrete thickness
2.3 OPTIONAL POST TENSIONING
A. The contractor may elect to circumferentially post tension reinforcing steel for the floor and roof slabs to protect against leaking and cracking. Should the Contractor elect to post tension reinforcement steel in the roof slab, fluid applied elastomeric roofing may be deleted.
2.4 WALL VENTS
PRECAST CONCRETE VAULT RESTROOM BUILDING 133402-3
A. Wall vents: Airolite No. 609B, size shown on the drawings, The Airolite Co., Marietta, OH, www.airolite.com; or HEAVY DUTY KICK PROOF VENT by Romtec, Roseburg, OR.; or an approved equal. Only one vent per toilet room should be installed – the contracting officer will specify the location of the vent (to be in a wall or the door – the side of the building with the prevailing wind)
2.5 ROOF
A. Sloped slab shed type or gabled type with a turned down edge to prevent water from migrating down the bottom edge of the roof panel and back into the building.
B. Minimum 6:12 pitch desired
2.6 VENT STACK
A. Vent Stack: shall be a minimum 12 inch diameter HDPE (with a DR of 32.5) and extend from the vault to a minimum of 3 feet higher than the roof peak. Vent Stack shall be black.
2.7 BIRD SCREEN:
A. Provide steel bird screen, secured with stainless steel screws for all stacks to prevent birds from entering the vault. https://tetonraptorcenter.org/our-work/poo-poo-project/ Screen shown in link or equal
2.8 PRECAST CONCRETE FORM WORK
A. Construct forms of plywood, lumber, or steel sheets or plates free of defects. Forms must be removable without injuring the concrete and must be constructed to maintain tolerances between mating surfaces of building components.
B. Form liners
1. Walls: Wood-textured appearance, Symons Corporation’s “Random Barnwood,” or an approved equal.
2. Roof: Wood shake appearance
C. Form coating: Non-staining type that will not leave residual matter on concrete surface or adversely affect proper bonding of subsequent coatings, caulking, grout or adhesive applied to concrete surfaces.
1. Form release agent or coating: As recommended by form liner manufacturer.
2. Coating containing mineral oils or other nondrying ingredients will not be permitted.
D. Vault:
1. Provide one concrete vault area per toilet riser.
2. Each concrete vault shall hold a minimum of 1,000 gallons of waste.
http://www.airolite.com/ https://tetonraptorcenter.org/our-work/poo-poo-project/
PRECAST CONCRETE VAULT RESTROOM BUILDING 133402-4
3. Concrete vault floor shall be sloped a minimum of 1 inch per foot towards the vault cleanout.
4. Vault Liner: Vault shall include a one-piece molded polyethylene (LDPE) liner with a minimum thickness of 0.10 inch and lip over top of vault. Liner shall be secured to sides of vault interior so that there are no voids between liner and sides of vault.
2.9 CONCRETE REINFORCEMENT
A. Reinforcing steel: ASTM A615, Grade 60.
B. Pre-stress strand (if used): ASTM A416, Grade 270.
C. All reinforcement shall be new, free from dirt, oil, paint, grease, loose mill scale, and loose or thick rust when placed.
2.10 CONCRETE MIX
A. Concrete supplier: Ready-mix or another approved precast concrete product firm.
B. Proportion cement, aggregate, and water to obtain concrete with good workability.
C. Concrete design
1. Aggregate: Coarse No. 67 (Table 2, ASTM C33)
2. Minimum cement content: 6.5 sacks per yd3
3. Cement type: ASTM C150 Type II, IIA, or III for building
4. Maximum water-cement ratio: 0.45
5. Slump: 3 to 5 inches by ASTM C143
6. Air content: 4-7% by ASTM C231
7. Minimum strength concrete: 4,500 psi at 28 days
8. Water: Potable
9. Admixtures:
a. Air-entraining agent: ASTM C260
b. Water reducing agent: ASTM C494, Type A
c. Use of other admixtures is subject to approval by the Contracting Officer
2.11 COLORED CONCRETE
A. Color additives: ASTM C979. Provide a 12”x 12”x 1” color sample to the Contracting Officer for approval. The following components shall contain colored concrete:
1. Building roof panels
2. Building wall panels
2.12 CONCRETE CURING COMPOUND AND ROOFING
A. Curing compound: Colorless, ASTM C309, Type 1 or 1-D.
PRECAST CONCRETE VAULT RESTROOM BUILDING 133402-5
B. Fluid Applied Elastomeric Roofing: Acrylic latex resin-base elastomeric roofing material applied in fluid form suitable for use over concrete roof slabs. If manufacturer elects to post-tension roof panel, the roofing material may be deleted.
1. Color: Brown.
2. Material: “Rapid Roof” as manufactured by the Conclin Company or an approved equal.
2.13 CAULKING, GROUT, ADHESIVE, AND MORTAR
A. Caulking shall remain flexible and non-sag at temperatures from -50° to 140° Fahrenheit.
1. Exterior, roof peak joint: 100% silicone caulk, clear; GE Silicone II or an approved equal.
2. Exterior joints (including roof/wall and wall panel joints): Tripolymer sealant caulk which compliments exterior color and has a minimum 5-year guarantee.
3. Interior joints: Paintable silicone-based caulking with a minimum 5-year guarantee.
B. Grout: Non-shrink type matching color of surrounding concrete as closely as possible.
C. Epoxy concrete adhesive: Two component, rigid, non-sag gel adhesive for bonding to dry or damp surfaces, moisture insensitive. Color to match surrounding concrete as closely as possible.
D. Portland cement mortar: One part Portland cement, three parts sand, and enough water to make a workable mixture.
2.14 FINISHES AND PAINTS
A. Paint and accessory materials: Similar to the “top-of-the-line” products of the manufacturer’s listed below.
1. Benjamin-Moore and Company, www.benjaminmoore.com
2. Columbia Paint Company, www.columbiapaint.com
B. Maximum lead content: 0.06 % by weight of lead.
C. Type of Paint
1. Metal, interior and exterior
a. Waterborne acrylic bonding primer, Columbia 04-022, or an approved equal.
b. Alkyd-oil Based Enamel, semi-gloss, Columbia 03-241, or an approved equal.
2. Exterior Concrete
a. Stain- pure acrylic water repellent penetrating stain
b. Sealer- clear acrylic anti-graffiti sealer
3. Interior Concrete
PRECAST CONCRETE VAULT RESTROOM BUILDING 133402-6
a.…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .