This is a Schedule of Items (SOI) pricing template for the Palisades Lagoon Liner & Effluent Sprinkler System Replacement project on the Santa Catalina Ranger District of the Coronado National Forest in Pima County, Arizona. The project involves replacing the existing lagoon liner system and effluent sprinkler system, reconstructing access roads, and implementing a temporary wastewater conveyance system to maintain uninterrupted wastewater services during construction at the Palisades Administrative Complex, located approximately 20 miles from Tucson.

The SOI contains 21 line items organized by pay item number and measurement methodology, including mobilization, temporary facilities, wastewater collection system design and management, effluent and sludge disposal, removal of existing systems, site grading, piping installation, geotextile and geomembrane liners, excavation, riprap, aggregate, and roadway reconditioning. Contractors must submit unit prices for all items, with quantities ranging from lump sum (LS) items to contract quantities measured in weekly periods (WK), gallons (GAL), cubic yards (CY), linear feet (LF), and individual units (EA). The file notes that one award will be made from this small business set-aside solicitation (NAICS 237110, $45 million size standard), and contractors must verify all calculations and pricing data. Unit prices will govern in case of extension errors, and the government reserves the right to award for quantities less than those stated.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Schedule of Items

SCHEDULE OF ITEMS

Palisades Lagoon Liner & Effluent Sprinkler System Replacement Santa Cantalina Ranger District Coronado National Forest

SCHEDULE OF ITEMS
ITEM NUMBERPAY

ITEM

NO. DESCRIPTION METHOD

OF

MEASUREPAY
UNITESTIMATED
QUANTITYUNIT
PRICETOTAL
0001AA017113 (01)MOBILIZATIONLSQLS1$ - 0$ - 0
0001AB015000 (01)TEMPORARY FACILITIES AND CONTROL - ELECTRICALLSQLS1$ - 0$ - 0
0001AC015120 (01)TEMPORARY WASTEWATER COLLECTION SYSTEM

- DESIGN

- INSTALLLSQLS1$ - 0$ - 0
0001AD015120 (02)MANAGEMENT & DISPOSAL OF WASTEWATER IN COLLECTION TANKSCQWK5$ - 0$ - 0
0001AE015120 (03)TEMPORARY TANK & PUMP SYSTEM RENTALCQWK5$ - 0$ - 0
0001AF021419 (01)EFFLUENT DISPOSAL IN LAGOONAQGAL249,000$ - 0$ - 0
0001AA021419 (02)SLUDGE DISPOSAL IN LAGOONAQGAL130,975$ - 0$ - 0
0001AG021419 (03)REMOVAL & DISPOSAL - EXISTING LAGOON LINER SYSTEMLSQLS1$ - 0$ - 0
0001AH021419 (04)REMOVAL & DISPOSAL - EXISTING EFFLUENT SPRINKLER SYSTEMLSQLS1$ - 0$ - 0
0001AI033000 (01)CONCRETE PIPE SUPPORTS, BAFFLE & STAFF GAUGELSQLS1$ - 0$ - 0
0001AJ312200 (01)SITE GRADING (GRADING & COMPACTION: LAGOON FLOOR, BERM, & EMBANKMENT) INCL MATERIALCQCY63$ - 0$ - 0
0001AK328000 (01)EFFLUENT SPRINKLER SYSTEM PIPING, 2" PVC, 1" PVC, 1" GSP INCLUDING MATERIAL & INSTALLATIONCQLF813$ - 0$ - 0
0001AL328000 (02)EFFLUENT SPRINKLER FITTINGS, RISERS & SPRINKLER HEADS ASSEMBLY INCL INSTALLATIONAQEA10$ - 0$ - 0
0001AM328000 (03)EFFLUENT SPRINKLER SYSTEM, DAYLIGHT DRAINS (INCLUDES VALVES & BOXES, MATERIAL & INSTALLATION)AQEA3$ - 0$ - 0
0001AN328000 (04)EFFLUENT SPRINKLER SYSTEM, PUMP & PLUMBING SYSTEM INCL. FOOT VALVELSQLS1$ - 0$ - 0
0001AO333600 (01)GEOTEXTILE, 8-OZ/SY NON-WOVENLSQLS1$ - 0$ - 0
0001AP334600 (01)GEOMEMBRANE LINER (PRIMARY LINER INCLUDES PIPE BOOTS, BERM VENTS, & ALL ACCESSORIES
& INSTALLATION)LSQLS1$ - 0$ - 0
0001AQ334600 (02)GEOMEMBRANE LINER (SECONDARY LINER) INCLUDING INSTALLATIONLSQLS1$ - 0$ - 0
0001AR204 (01)EXCAVATION AND EMBANKMENT
- BORROW EXCAVATION, TEMPORARY ACCESS AREA 18' X 58'LSQLS1$ - 0$ - 0
0001AS251.04 (01)RIP RAP (CLASS I) INSTALLEDCQCY20$ - 0$ - 0
0001AT301 (01)UNTREATED AGGREGATE, 3" COMPACTED IN PLACE, TABLE
703-3 - DESIGNATION HCQCY100$ - 0$ - 0
0001AU303 (01)ROADWAY RECONDITIONING, ACCESS ROAD, 00+00 - 06+60AQLF660$ - 0$ - 0

TOTAL BASE ITEM 0001 $ - 0

Designated Method of Measurement:
LSQ - lump sum quantities, AQ - Actual Quantities, CQ - Contract Quantities
NOTE 1: Contractor input Unit Prices
NOTE 2: Auto Calculated Values
NOTE 3: One award will be made from this solicitation. Contractor's must submit pricing for all items. In the event of an error in extending the proposed prices, unit prices will govern, unless otherwise determined by the Contracting Officer, in accordance with applicable regulations. The Government reserves the right to make award for quantities less than those stated on the Schedule of Items.
NOTE 4: Submission of the SOI represents the Contractors commitment to the data herein. It is the responsibility of the Contractor to verify that all values presented in the SOI, including auto-calculated cells, accurately represent the Contractor's intended price elements. The Government shall not be held liable for any errors in calculation or pricing data.
NOTE 5: Payment for bond premiums in accordance with AGAR Clause 452.232-71, Progress Payments for Commercial Construction Contracts, shall not be in addition to the contract price, but may be included under Mobilization.