C04_Attachment 1 SOW 1232SA26Q0801.docx
DOCX document 59 KB Posted
- Attached to
- Emergency Indoor Air Quality Remediation
- Solicitation number
- 1232SA26Q0801
About this file
This is a Performance Work Statement (PWS) for Indoor Air Quality Remediation services at the USDA Agricultural Research Service Sugarcane Field Station in Canal Point, Florida. The contractor shall provide comprehensive IAQ remediation for the Administration and Laboratory Buildings, including labor, supervision, materials, equipment, containment systems, and all necessary tools and transportation. Work encompasses installation of containment systems and barriers, protection of interior contents with 4-mil plastic sheeting, HEPA vacuuming of all accessible surfaces (walls, ceilings, floors, vents, registers) to remove dust, mold spores, and particulate matter, application of EPA-registered antimicrobial agents to hard surfaces, building disinfection using approved fogging or spray systems, and hot thermal fog deodorization to eliminate persistent odors. HVAC remediation tasks include cleaning and decontaminating supply and return ductwork, accessing interior duct surfaces for cleaning and treatment, HEPA vacuuming and sanitizing duct interiors, cleaning air handler components including evaporator coils and blower motor assemblies, applying EPA-registered antimicrobial agents, and resealing all HVAC access points.
All work shall be conducted while facilities remain occupied unless otherwise coordinated, with services performed during regular weekday hours from 7:00 a.m. to 4:00 p.m., excluding holidays. The contractor must comply with NADCA ACR and IICRC S520 performance criteria, OSHA Standard 29 CFR 1910, state of Florida mold remediator licensing requirements, and federal facility security protocols. Key deliverables include a work plan and schedule (due five calendar days prior to mobilization), a safety plan with Safety Data Sheets of all chemicals, progress reports, before and after photographs, and a final completion report. The contractor shall assign a project manager responsible for managing resources, deliverables, schedule adherence, and communication with USDA points of contact. Any travel expenses must be included as a line item in the service proposal pricing. The related solicitation (1232SA26Q0801) is a Request for Quotation set aside for small business concerns under NAICS code 562910 with a size standard of $25 million.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Performance Work Statement
Indoor Air Quality Remediation – Administration and Laboratory Buildings ARS/Sugarcane Field Station
12990 US HWY 441 NORTH
Canal Point, FL 33438
Contents
| Project | 3 |
| General Information | 3 |
| 1.0 Scope of Work | 3 |
| 2.0 Background | 4 |
| Contractor Requirements | 4 |
| 3.0 Technical Requirements / Tasks | 4 |
| 4.0 Government Furnished | 5 |
| 5.0 Deliverables / Schedule | 5 |
| 6.0 Travel | 6 |
| 7.0 Contractor’s Key Personnel | 6 |
| 8.0 Security Requirements | 6 |
| 9.0 Data Rights | 6 |
| 10.0 Section 508 – Electronic and Information Technology Standards | 6 |
| 11.0 – Attachments | 6 |
Project Indoor Air Quality Remediation – Administration and Laboratory Buildings at Sugarcane Field Station, Canal Point, Florida.
General Information
1.0 Scope of Work
The Contractor shall provide all labor, supervision, materials, equipment, containment systems, engineering controls, tools, and transportation necessary to perform indoor air quality (IAQ) remediation within the Administration and Laboratory Buildings at the USDA Agricultural Research Service (ARS) Sugarcane Field Station located at 12990 US Highway 441 North, Canal Point, FL 33438.
Contractor must be able to provide service to Canal Point, Florida location which is located in a rural area.
Work tasks include, but are not limited to:
· Installation of containment systems and barriers to prevent cross‑contamination.
· Protection of all interior contents, office equipment, research materials, and furnishings using plastic sheeting of no less than 4‑mil thickness.
· HEPA vacuuming of walls, ceilings, floors, vents, registers, and all accessible surfaces to remove dust, mold spores, and particulate matter.
· Application of EPA‑registered antimicrobial agents to hard surfaces including walls, ceilings, floors, desks, shelves, and HVAC grilles.
· Building disinfection using approved fogging or spray systems appropriate to building size.
· Hot thermal fog deodorization following disinfection to eliminate persistent microbial odors.
HVAC Remediation Tasks (Performance‑Based) The Contractor shall perform HVAC remediation cleaning and sanitation necessary to restore indoor environmental quality.
Tasks include:
· Cleaning and decontaminating supply and return ductwork.
· Accessing interior duct surfaces to perform cleaning and antimicrobial treatment (minimal access cuts permitted where required).
· HEPA vacuuming and sanitizing duct interiors to remove dust, microbial residue, and contaminants.
· Cleaning air handler components including evaporator coils, blower motor assemblies, drip pans, wires, and interior air handler cabinets.
· Application of EPA‑registered antimicrobial agents following cleaning.
· Resealing all HVAC access points to original or better condition.
· Performance Standard: HVAC systems shall be restored to a clean, sanitary, and properly functioning state in accordance with NADCA ACR and IICRC S520 performance criteria.
General Requirements:
All work shall be conducted in accordance with federal, state, and industry IAQ standards, while facilities remain occupied unless otherwise coordinated.
The submitted project bid shall be turnkey, and all bids will be evaluated on best-overall value for the USDA Agricultural Research Service.
2.0 Background
The Administration and Laboratory Buildings have exhibited mold and mildew presence within the HVAC system and on interior surfaces. To ensure a safe and healthy indoor environment, USDA-ARS requires professional IAQ remediation services that can be performed while the facilities remain occupied, except when specific tasks must be scheduled during non-duty hours or weekends.
Contractor Requirements
3.0 Technical Requirements / Tasks
The Contractor shall:
3.1 Protect building contents
· All interior contents, equipment, and research materials shall be covered with plastic sheeting of no less than 4-mil thickness.
· Ensure that protective coverings do not obstruct critical equipment or violate safety protocols.
Performance Standard: No damage to contents; all surfaces covered prior to remediation.
3.2 HEPA Vacuuming of Walls and Surfaces
The Contractor shall:
Perform HEPA vacuuming of all accessible walls, ceilings, floors, vents, registers, and horizontal surfaces.
Use commercial HEPA filtration equipment designed for IAQ remediation.
Performance Standard: Removal of dust, mold spores, and visible particulate matter; no residual debris.
3.3 Application of Antimicrobial Agent
The Contractor shall:
· Apply EPA‑registered antimicrobial agents to all hard surfaces, including walls, ceilings, floors, desks, shelving, and HVAC grills.
· Follow all manufacturer instructions and safety requirements.
Performance Standard: Even application across treated surfaces; no damage or staining.
3.4 Building Disinfection (Fog/Spray Application)
The Contractor shall:
· Disinfect buildings using an approved fogging or spray system appropriate to building square footage.
· Coordinate timing with USDA to minimize disruption to occupied areas.
Performance Standard: Even dispersal throughout the designated spaces; no adverse effects on occupants or equipment.
3.5 Deodorization via Hot Thermal Fog
The Contractor shall:
· Conduct hot thermal fog deodorization after disinfection to eliminate residual odors.
· Ensure proper ventilation and re‑entry times per product specifications.
Performance Standard: Persistent musty odors are eliminated; building safe for re-entry within prescribed time.
3.6 HVAC Remediation
· Perform full HVAC cleaning and sanitation as described in the Scope.
Performance Standard: Meets NADCA/IICRC performance requirements.
3.7 Occupancy Considerations
· Remediation shall occur while buildings are occupied unless specific activities require temporary relocation or weekend work.
· The Contractor shall coordinate schedules with the COR.
Normative References:
· Policies and Procedures 242.1M-ARS ARS Facilities and Design Standards
· NADCA ACR Standard (Assessment, Cleaning, and Restoration)
· IICRC S520 Standard for Professional Mold Remediation
· State of Florida Mold Remediator Licensing Requirements
Submittals:
· Safety Data Sheets
· Before and After photos
· Final Remediation Report
Safety Requirements:
1. The Contractor will be responsible for ensuring that the requirements of Department of Labor, Occupational Safety and Health Administration (OSHA) Standard 29 CFR 1910 will be followed.
2. The Contractor will inform the SFS Safety Officer of the following:
a. Any injury incurred by Contractor employee or subcontractor on-site that requires more than basic first aid.
b. Any medical care received for such injury.
4.0 Government Furnished
Service shall be performed by the Contractor during regular weekday, daylight working hours (excluding holidays) 07:00 am to 4:00 pm. During period of work, Contractor will be given site access and issued a temporary contractors key badge.
5.0 Deliverables / Schedule
The period of performance shall be ________ to ________. The Contractor must submit a work schedule for approval at least five calendar days prior to mobilization.
Key Deliverables
| Item No. |
| Deliverable |
| Objective |
| Due |
| 1 |
| Work Plan and Schedule of work |
| Coordinate both contractor and USDA lab operations to meet optimal outcomes |
| 2 |
| Safety Plan and SDS of chemicals used |
| Review of SDS’s of disinfecting chemicals |
| 3 |
| Progress reports |
| Routine report on areas that will be affected by contractor activity |
| 4 |
| Before and After pictures |
| Document before and after conditions for area leadership |
| 5 |
| Final Completion report |
| Document work done and results. |
6.0 Travel
Any travel expenses incurred by Contractor must be a line-item in the service proposal or included in the final pricing prior to contract award.
7.0 Contractor’s Key Personnel
Contractor shall supply a project manager responsible for managing resources, deliverables, staying on schedule, and communicating with SFS POC’s.
8.0 Security Requirements
The Sugarcane Field Station is a controlled-access federal facility with restricted entry. Contractor shall abide by all security measures. Contractor shall return any key badges assigned to them upon completion of work.
9.0 Data Rights
No data rights assigned to this contract.
10.0 Section 508 – Electronic and Information Technology Standards No IT resources assigned to this contract.