This is an Independent Government Estimate (IGE) and Schedule of Items pricing template for two separate Forest Products Laboratory projects at the Department of Agriculture Forest Service.

The primary active project is "B50 Overhead Fire Door Inspection" (Requisition No. FY26-016607) with a period of performance from September 15, 2026 to October 15, 2026. This project requires inspection and drop testing of 17 overhead fire doors of various specifications and sizes, including models S015, W000, E000, W065, S065, E065, E070, N070, SA070, SB070, SC070, N055, WM035, EM035, E095, N095, and E110, ranging from 8x8 to 14x18 dimensions. Each door inspection and drop test is listed as a separate line item (items 0001-0017) with an estimated quantity of one unit each. The secondary section addresses a template for "Building 1 Emergency Roof Replacement" with a base period from May 1, 2023 to November 1, 2023, plus four optional years, though this section contains no completed data and appears to be an unfilled template for future use. The solicitation (12444626Q0076) is a Request for Quotation set aside as a Total Small Business Set-Aside, classified under NAICS code 561790, with award anticipated as a firm fixed price contract.

View the file

Other files

File Type Posted
VENDOR QUESTIONS AND ANSWERS 2 08 28 2026.docx DOCX document
Vendor Questions and answers 08 25 26.pdf PDF
C04 C - WD 12444626Q0076.pdf PDF
C04 D CSS_1444626Q0076.pdf PDF
C04 B STATMENT OF WORK 12444626Q0076.pdf PDF
12444626Q0076.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

INSTRUCTIONS: HOW TO USE THIS FORM

Independent Government Estimate (IGE)
No specific format is required for an IGE; however this must be an independent estimate and not a reiteration of a contractor quote. The selected format should generally be in the same level of detail and manner that the Schedule of Items pricing we request from contractors. The estimate should state any underlying assumptions or rationale used in formulating the estimate. Initially the CO will use the IGE to determine the estimated value of the procurement and to identify the appropriate procurement thresholds applicable to the solicitation. Later the IGE is compared to prices received to evaluate an offeror’s understanding of the government requirements and in supporting a price reasonableness determination.

EXPLANATION OF TABS

Stand Alone IGE:Use if the below do not apply to your requirement.
Stand Alone IGE w/options:Use if you have a requirement where you know you have an ongoing/recurring need year after year.
IDIQ:Use if you have a need that is reoccurring or multi-year requirement.
Task Order:Use if you want to issue a order against an existing contract or agreement.

CONTRACT (NO OPTIONS)

SCHEDULE OF ITEMS

Forest Products Laboratory PROJECT TITLE: B50 Overhead Fire Door Inspection WORKPLAN ACQUISITION PLAN/REQUISITION NO:FY26-016607

Period of Performance (Required for Services and A&E)Start Date - End date
Anticipated Delivery Date (Required for Supply and Construction)09/15/2026-10/15/2026
SCHEDULE OF ITEMS
ITEM
NUMBERDESCRIPTIONPAY UNITEST QTY
0001Inspect & Drop Test S015-12x12 Overhead Fire Door1
0002Inspect & Drop Test W000-12x12 Overhead Fire Door1
0003Inspect & Drop Test E000- 12x12 Overhead Fire Door1
0004Inspect & Drop Test W065-12x12 Overhead Fire Door1
0005Inspect & Drop Test S065- 12x12 Overhead Fire Door1
0006Inspect & Drop Test E065- 14x18 Overhead Fire Door1
0007Inspect & Drop Test E070- 14x18 Overhead Fire Door1
0008Inspect & Drop Test N070- 14x18 Overhead Fire Door1
0009Inspect & Drop Test SA070- 8x8 Overhead Fire Door1
0010Inspect & Drop Test SB070- 12x12 Overhead Fire Door1
0011Inspect & Drop Test SC070- 12x12 Overhead Fire Door1
0012Inspect & Drop Test N055- 12x12 Overhead Fire Door1
0013Inspect & Drop Test WM035-8x8 Overhead Fire Door1
0014Inspect & Drop Test EM035- 8x8 Overhead Fire Door1
0015Inspect & Drop Test E095- 14x18 Overhead Fire Door1
0016Inspect & Drop Test N095- 12x12 Overhead Fire Door1
0017Inspect & Drop Test E110- 14x18 Overhead Fire Door1

CONTRACT (WITH OPTION YRS)

FILL OUT THE AREAS IN RED BELOW

SCHEDULE OF ITEMS

Forest Products Laboratory PROJECT TITLE: Building 1 Emergency Roof Replacement WORKPLAN ACQUISITION PLAN/REQUISITION NO: (NUMBER)

SCHEDULE OF ITEMS
Period of Performance Base Year: 05/01/2023 - 11/01/2023
ITEM
NUMBERDESCRIPTIONPAY UNITEST QTY
0001
0002
0003
0004
0005
0006
Period of Performance Option Year 1: MM/DD/YR – MM/DD/YR
ITEM
NUMBERDESCRIPTIONPAY UNITEST QTY
1001
1002
1003
1004
1005
1006
Period of Performance Option Year 2: MM/DD/YR – MM/DD/YR
ITEM
NUMBERDESCRIPTIONPAY UNITEST QTY
2001
2002
2003
2004
2005
2006
Period of Performance Option Year 3: MM/DD/YR – MM/DD/YR
ITEM
NUMBERDESCRIPTIONPAY UNITEST QTY
3001
3002
3003
3004
3005
3006
Period of Performance Option Year 4: MM/DD/YR – MM/DD/YR
ITEM
NUMBERDESCRIPTIONPAY UNITEST QTY
4001
4002
4003
4004
4005
4006
EA - EACH

MO - MONTH Award anticipated to be a firm fixed price contract.