This document contains four technical specification sections for a federal construction contract related to vertical drilling and water line installation at a government site in Nevada and El Dorado Counties, California.
Section 001901 establishes mobilization requirements and compensation for the contractor's initial operations, including personnel and equipment movement, bond and insurance premiums, and well permit fees. Mobilization is measured as a lump sum with progressive payments: bond premiums reimbursed upon evidence of payment, 50% of the lump sum (not exceeding 5% of the original contract amount) paid after completion of 5% of contract work excluding mobilization, remaining portion up to 10% of original contract amount paid after 10% contract completion, and any excess paid after final acceptance. All progress payments are subject to retainage. Section 02223 specifies trenching, backfill, and compaction work including excavation of 12-24 inch wide trenches at minimum 24 inches deep with vertical banks, removal of roots over 3 inches in diameter, utility detection tape installation, and specific material requirements for native backfill, select backfill for PVC and metal pipe installations, and drain rock. Compaction standards vary by material type and location, with bedding material requiring mechanical compaction and select material hand-compacted in 6-inch lifts.
Section 024482 details vertical irrigation well drilling specifications requiring an 8"-12" diameter borehole drilled to 300 feet (or cessation if sufficient water is found earlier) capable of sustaining 10-30 gallons per minute water production. Equipment requirements include a rig anchored to ground with adequate hydraulic capacity, 8-inch thermoplastic well casing meeting ASTM F480, PVC casing meeting ASTM D1785 or D2241, and Type II or III Portland cement grout per ASTM C-150. The contractor must submit work plans, equipment specifications, materials data, and drilling logs; maintain daily project records; and perform work in accordance with California Building Standards Code and Department of Water Resources regulations. Section 331113 specifies water line and appurtenance installation including PVC solvent weld pressure pipe (Schedule 80 for sizes 3 inches and smaller), galvanized steel pipe Schedule 40, blue utility detection marking tape, nonconductive copper wire with colored insulation, and precast concrete valve boxes with H20 cast iron frames. All trenching, excavation, and backfill work references specification 02223, with pipes requiring protection during storage and installation, inspection of trench subgrade and bedding prior to pipe placement, and system testing in the presence of the Contracting Officer. Payment for water line work is incidental to the well drilling pay item.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| C04 - 10 - RFI Form.docx | DOCX document | |
| C04 - 1 - Solicitation Terms and Conditions - Badger Hill Seed Orchard Well - 127EAW26Q0058.pdf | ||
| C04 - 3 - Schedule of Items.docx | DOCX document | |
| C04 - 4 - Fire Plan.pdf | ||
| C04 - 9 - Contract Administration Data.pdf | ||
| C04 - 2 - Statement of Work.pdf | ||
| C04 - 5 - Drawings.pdf | ||
| C04 - 7 - Project Location.pdf | ||
| C04 - 8 - Davis-Bacon Act WD CA20260007 - Eldorado County.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 001901
MOBILIZATION FOR VERTICAL DRILLING
PART 1- GENERAL
1.1 Mobilization - This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project and well permit fees through Nevada County; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.
1.2 Method of Measurement - The measurement shall be lump sum for mobilization.
1.3 Basis of Payment-The lump sum price shall include full compensation for mobilization. Progress payments for mobilization will be made as follows:
A. Bond premiums will be reimbursed after receipt of the evidence of payment.
B. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.
C. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.
D. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.
Progress payments for mobilization and preparatory work shall be subject to retainage.
PART 2-PRODUCTS (Not Applicable}
PART 3 - EXECUTION (Not Applicable)