This is a Statement of Work for a window restoration project at the Lewis and Clark Interpretive Center in Great Falls, Montana. The base bid scope requires the contractor to restore water-tight functions of window assemblies, including replacement of damaged windows, replacement of all vinyl weather stripping, caulking of exterior window perimeters, and washing of all windows upon completion. The contractor is responsible for providing all labor, materials, and tools necessary to complete the work, as well as disposal of all waste and excess materials generated from construction in compliance with federal, state, and local laws.

The project is located at 4201 Giant Springs Road, Great Falls, MT 59405, and the contractor is allowed one 30-day work window to start and finish all work, with a completion deadline of September 30, 2026. No pre-bid tour is scheduled; prospective bidders are responsible for conducting their own site visits prior to submitting bids. An attached map indicates the project location.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

1.1 SCOPE OF CONTRACT

A. Base Bid:

a. This project is to restore the water-tight functions of window assemblies of the Lewis and Clark Interpretive Center.

b. Work includes the replacement of damaged windows, replacement of all vinyl weather stripping, caulking exterior window perimeters, and washing of all windows at the completion of work.

c. Contractor is responsible for all labor, materials, tools, etc. necessary to complete the work. All waste and excess materials generated from construction shall be disposed of off Forest Service lands and in compliance with governing federal, state, and local laws.

1.2 PROJECT LOCATION

A. (See attached Map) Lewis and Clark Interpretive Center 4201 Giant Springs Road Great Falls, MT 59405

1.3 PERIOD OF PERFORMANCE:

A. Contractor allowed one 30-day work window to start and finish the project. Work shall be completed by September 30, 2026.

1.4 PRE-BID TOUR:

A. No Pre-Bid Tour is scheduled for this project. Prospective bidders are responsible for visiting the site prior to bidding.