This document is the operating and maintenance instructions for a Burner Fire Twin Agent Model AF-DC-450-AFFF-150-1-HR fire suppression system, which is relevant to the City of Pembroke Pines' airport rescue firefighting truck retrofit project in Florida. The Twin Agent system consists of two independent discharge systems: a 150-gallon AFFF (aqueous film-forming foam) side and a 450-pound dry chemical side, each with dedicated nitrogen pressurization cylinders, manifolds with master valves, bleed valves, purge valves, and discharge capabilities. The system can discharge either agent independently or both simultaneously and is designed to be mounted on a skid configuration. Unit startup procedures require filling the AFFF tank with 145 gallons of freshwater and 5 gallons of 3% AFFF foam, charging nitrogen cylinders to 2200 PSI with regulated pressure at 200 PSI ±5 PSI, and conducting pressure and valve checks on both the AFFF and dry chemical manifolds before placing the system in service.
The document provides comprehensive operational procedures for discharge, including opening manifold master valves, opening nitrogen cylinders, pulling actuator handles, and aiming the discharge in sweeping motions at fire bases. Post-discharge purging procedures are specified to remove residual agents and prepare the system for recharging, which involves relieving all pressure, removing filler caps, refilling both tanks to proper levels, and replacing nitrogen cylinders with full ones. Maintenance and inspection schedules are detailed across multiple intervals: monthly inspections verify nitrogen pressure remains above 1750 PSI and check valve functionality; six-month inspections include pressure gauge verification, hose inspection, and agent level checks; yearly inspections require AFFF sample analysis and relief valve testing; and five-year inspections mandate pressure testing of discharge hoses at 250 PSI and internal inspection of the AFFF tank lining. Critical safety warnings emphasize never removing filler caps while cylinders are pressurized and never operating the system without regulators in place, as failure to follow these instructions could result in serious injury or death.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OPERATION / MAINTENANCE INSTRUCTIONS
TWIN AGENT
MODEL AF-DC-450-AFFF-150-1-HR
Headquarters: 1374 Petroleum Parkway, Broussard, LA 70518
Mailing Address: P.O. Box 53482, Lafayette, LA 70505
Tel: (337) 237-4547, Toll Free: (800) 864-4073, Fax: (337) 237-8510
Web: www.burnerfire.com, General Email: bfcinfo@burnerfire.com http://www.burnerfire.com/ mailto:bfcinfo@burnerfire.com
AF-DC-450-AFFF-150-1HR
UNIT START UP INSTRUCTIONS
After The Twin Agent System is installed at your Location, Check to see that NONE of the system nitrogen Regulators on the system are connected.
On the AFFF Side, you will need to do the following:
Open the 3/8” Master Valve.
Open 1/4” tank bleed valve on unit manifold.
Remove 4” fill cap.
Fill AFFF tank with 145 gallons of freshwater and 5 gallons of 3% AFFF.
Check to see that the O-Ring is installed in the fill cap Collar and is in good condition.
Replace fill cap securely.
Close 1/4” tank bleed valve and the 3/8” master valve.
Remove the protective cap from the AFFF nitrogen cylinder by rotating Cap counter clockwise.
The Victor Nitrogen Regulator connected to the AFFF Manifold will need to be connected to the 300 cu. ft. nitrogen cylinder on the Left side of the skid ensuring that it is tight. (Check to see that the 3/8” Master Valve on Unit Manifold is CLOSED.) After the regulator are connected, the nitrogen cylinder pressure will need to be checked.
AF-DC-450-AFFF-150-1HR UNIT START UP INSTRUCTIONS PAGE 2
To check the cylinder pressure you must first close the master valve on the AFFF Manifold. Open the nitrogen cylinder by rotating the wheel valve counter clockwise.
Check the nitrogen cylinder pressure ensuring the hi-pressure gauge reads at least 2200 psi, and the regulated pressure gauge reads 200 P.S.I. plus or minus 5 P.S.I.
Close the nitrogen cylinder by rotating the wheel valve clockwise and open the bleed to relieve the pressure from the manifold. CLOSE Bleed valve.
AFFF Manifold Final Valve Check to Put System In Service
Master Valve: CLOSED Bleed Valve: CLOSED Purge Valve: CLOSED
On the Dry Chemical Side, you will need to do the following:
Remove the protective caps from the Dry Chemical nitrogen cylinder by rotating Cap counter clockwise.
The Victor Nitrogen Regulator connected to the Dry Chemical Manifold will need to be connected to the 300 cu. ft. nitrogen cylinder on the Right side of the skid.
(Check to see that the 3/8” Master Valve on Unit Manifold is CLOSED.) After the regulator is connected, the nitrogen cylinder pressures will need to be checked.
To check the cylinder pressure you must first close the master valve on the Dry Chemical Manifold. Open the nitrogen cylinder by rotating the wheel valve counter clockwise. Check the nitrogen cylinder pressure on the cylinder ensuring the hi-pressure gauge reads at least 2200 psi, and the regulated pressure gauge reads 200 P.S.I. plus or minus 5 P.S.I. Close the nitrogen cylinder by rotating the wheel valve clockwise and open the bleed to relieve the pressure from the manifold.
CLOSE Bleed valve and CLOSE Master Valve.
Dry Chemical Manifold Final Valve Check to Put System In Service
Master Valve: CLOSED Bleed Valve: CLOSED Purge Valve: CLOSED
(SEE OPERATING AND MAINTENANCE MANUAL FOR RECHARGING
INSTRUCTIONS IF UNIT IS DISCHAGED.)
TWIN AGENT 450 LB 150 GAL AFFF
OPERATING INSTRUCTIONS FOR TWIN AGENT UNITS
READ AND UNDERSTAND ALL INSTRUCTIONS BEFORE ATTEMPTING TO
OPERATE THE UNITS.
FAILURE TO UNDERSTAND AND FOLLOW ALL INSTRUCTIONS COULD LEAD TO
SERIOUS INJURY OR DEATH.
As you face the unit, the right hand side and all associated hardware are dry chemical.
The Left hand side and all associated hardware are AFFF.
Each cylinder is fitted with independent manual actuator levers to cause the unit to discharge either agent independently or both agents simultaneously.
On the right hand side of the unit is the dry chemical manifold. The manifold is fitted with the following:
1) Master valve for operation of the dry chemical portion of the unit (labeled Master).
2) Bleed valve for bleeding the pressure off the extinguisher cylinder after discharge (labeled tank bleed).
3) Gauge to determine the pressure on the extinguisher cylinder.
4) Purge valve for clearing out the hose line after discharge (labeled Purge).
On the left hand side of the unit is the AFFF manifold. The manifold is fitted with the following.
1) Master valve for operation of the AFFF portion of the unit (labeled Master).
2) Bleed valve for bleeding the pressure off the extinguisher cylinder after discharge (labeled tank bleed).
3) Gauge to determine the pressure on the extinguisher cylinder.
4) Purge valve for clearing out the hose line after discharge (labeled Purge).
DISCHARGE INSTRUCTIONS
The Burner Twin Agent Unit is designed that either agent can be discharged alone or simultaneously.
It is the recommendation of Burner that both agents are activated to the hose reel so that either can be discharged on a fire.
To discharge the unit you must do the following.
1) The Master valve on the AFFF manifold and the Master valve on the Dry Chemical Manifold will need to be moved to the open position
2) Open the Nitrogen Cylinder for the dry chemical and AFFF
3) Pull AFFF or dry chemical actuator handle (Yellow handled pushrods on either side of the unit) out to stop.
4) Pull the hose off of the hose reel to the desired length.
5) Open the appropriate valve and aim the discharge at the base of the fire and extinguish in a side-to-side sweeping motion. Before opening the hose end discharge valve be sure to have a good footing and a firm grip on the valve as there will be a significant nozzle reaction.
6) When the fire appears to be extinguished, close the discharge valve and slowly back away. NEVER TURN YOUR BACK TO THE FIRE!!!
PURGE INSTRUCTIONS
After discharge of the unit you will need to purge the hoses to remove any AFFF or Dry Chemical as well as to prepare the unit for recharging.
To purge the unit after discharge you will need to do the following.
1) Close both actuator levers (the Yellow handled push rods on either side of the unit).
2) On the AFFF manifold close the Master valve and open the Purge valve.
3) Open the hose end discharge valve until no AFFF comes out.
4) On the Dry Chemical Manifold close the master valve and open the Purge valve.
Open the hose end discharge valve until no chemical comes out.
5) Close AFFF and Dry Chemical Purge Valve.
After purging the system, make sure to refill and place the units back in the standby mode for future use.
RECHARGING INSTRUCTIONS
DO NOT ATTEMPT TO REMOVE THE FILLER CAPS BEFORE ENSURING THAT
THERE IS NO PRESSURE IN THE EXTINGUISHER CYLINDERS. ATTEMPTING TO
REMOVE THE FILLER CAPS WHILE THE EXTINGUISHER CYLINDERS ARE UNDER
PRESSURE CAN RESULT IN SERIOUS INJURY OR DEATH!!!
To recharge the unit you will need to do the following.
1) Close both actuator levers (the Yellow handled push rods on either side of the unit).
2) Close the nitrogen cylinder valves on both sides of the unit.
Close cylinder valve by rotating wheel valve clockwise to stop.
3) On the AFFF manifold you will need to make sure that the Master valve is Open, Close the Purge valve, Open the Tank Bleed valve and hose end discharge valve to release any pressure on the extinguisher cylinder and hose. Note that the pressure on the manifold gauge reads -0-. Close the master valve.
4) On the dry chemical manifold you will need to make sure that the Master valve is Open, Close the Purge valve. Open the tank bleed valve and hose end discharge valve to release any pressure on the extinguisher cylinder and hose. Note that the pressure on the manifold gauge reads -0-. Close the master valve.
5) Slowly remove the filler caps on both extinguisher cylinders noting that no pressure vents through the cap vent slot.
6) In the AFFF extinguisher cylinder fill with 145 gallons of water and 5 gallons of 3% AFFF foam.
7) In the dry chemical extinguisher cylinder fill with 450 lbs. of PK dry chemical or to the fill level indicated on the extinguisher cylinder.
8) Clean the threads on the filler cap and flange. Inspect the O-ring on both filler caps. If there is any damage to the O-ring replace it with a new one. Apply a small amount of general purpose lithium grease to the O-ring on both filler caps. Screw the filler caps back onto each extinguisher cylinder making sure they are tight.
9) On the AFFF manifold you must now close the Master valve and Tank Bleed valve.
Make sure the hose end discharge valve is closed.
10) Replace the nitrogen cylinder with a full one. To replace the nitrogen cylinder the pressure must first be relieved. Close the nitrogen cylinder and open the purge valve on manifold, Open the hose end discharge valve. This will allow the nitrogen to vent through the hose. Remove the regulator from the nitrogen cylinder. Place a cap over the cylinder valve to ensure it is not damaged. Remove the bolt from the nitrogen cylinder-retaining ring. Slide the cylinder out of the bracket and replace with a full one. Place the regulator back on the cylinder ensuring it is tight.
NEVER ATTEMPT TO OPERATE OR PURGE THE SYSTEM WITHOUT A
REGULATOR IN PLACE. FAILURE TO USE A REGULATOR IN THE OPERATION OR
PURGING OF THE UNIT CAN RESULT IN SERIOUS INJURY OR DEATH!!!
Once the nitrogen cylinder is replaced, close the master valve, open the cylinder valve.
Make sure the pressure on the high side gauge reads at least 2200 PSI, and regulator pressure gauge reads 200 PSI + OR – 5 PSI. Close cylinder valves by rotating counter clockwise.
11) For the dry chemical side make sure the hose end discharge valve is closed and that the master valve and Purge valves are closed.
12) Replace the nitrogen cylinder with a full one. To replace the nitrogen cylinder the pressure must first be relieved. Close the nitrogen cylinder and open the purge valve on manifold, Open the hose end discharge valve. This will allow the nitrogen to vent through the hose. Close the purge and Remove the regulator from the nitrogen cylinder by rotating counter clockwise. Place a cap over the cylinder valve to ensure it is not damaged. Remove the bolt from the nitrogen cylinder-retaining ring. Slide the cylinder out of the bracket and replace it with a full one. Place the regulator back on the cylinder ensuring it is tight. NEVER ATTEMPT TO OPERATE OR PURGE THE SYSTEM
WITHOUT A REGULATOR IN PLACE. FAILURE TO USE A REGULATOR IN THE
OPERATION OR PURGING OF THE UNIT CAN RESULT IN SERIOUS INJURY OR
DEATH!!! Once the nitrogen cylinder is replaced, close the master valve, open the cylinder valve. Make sure the pressure on the high side gauge reads at least 2200 PSI, and regulator pressure gauge reads 200 PSI + OR – 5 PSI. Close the cylinder valve.
13) Make sure the master valve, purge valve and the hose discharge valves are closed on the AFFF and Dry Chemical manifolds.
The unit is now in the stand by mode and ready for discharge.
INSPECTIONS AND MAINTENANCE
Maintenance and inspection frequency will be dependent upon the environmental conditions the unit is exposed to.
A daily inspection to ensure the unit is ready for discharge is recommended.
MONTHLY
1. Check the nitrogen cylinder gauges ensuring the hi-pressure gauge reads at least 1750 psi,
2. Check to see that both hose end discharge valves are fully closed.
3. Check to see that the manual pull actuators are unobstructed and that tamper seals are intact.
4. The system shows no physical damage, corrosion or condition that would prevent operation.
5. Check to see that the Master valve is CLOSED, The Purge Valve is CLOSE and the Bleed valve is CLOSED On both the Dry Chemical and AFFF Manifolds.
SIX MONTH INSPECTION
1. Check the nitrogen cylinder gauges ensuring the hi-pressure gauge reads at least 1750 psi, and the regulated pressure gauge reads 200 psi. To check the pressure gauges you must first close the master valve on the dry chemical and AFFF Manifolds. Open the nitrogen cylinder by rotating counter clockwise. After checking the gauge pressure you will need to close the nitrogen cylinder and open the bleed on both manifolds, this will allow the nitrogen to vent through the manifold. Close the bleed on both manifolds.
2. Check to make sure the hose end discharge valves operatively freely. Make sure the valves are closed after this procedure.
3. On the AFFF and Dry Chemical tank you will need to open the master and tank Bleed valves. Note that the pressure on the manifold gauge reads -0-. Slowly remove the filler cap noting that no pressure vents through the cap vent slot.
A. Check AFFF Foam premix level.
B. Check the Dry Chemical level and condition.
C. Close the bleed valves on Both Manifolds.
4. Pull the hose off of the hose reel and inspect the jacket for any abrasions or defects.
5. Check all system hoses and fittings for any deformities or wear.
6. Check to see that the Master valve is CLOSED, The Purge Valve is CLOSE and the Bleed valve is CLOSED On both the Dry Chemical and AFFF Manifolds.
Make sure the unit is placed back in the standby mode and is ready to fight fire.
YEARLY INSPECTION
1. Pull a sample of the AFFF foam solution for testing and analysis.
2. Grease the fittings on the hose reel with a general purpose lithium grease.
3. Test or replace the 250 PSI Tank Pressure relief valve.
5 YEAR INSPECTION
1. Pressure test the Chemical discharge hoses at 250 PSI
2. Completely discharge the AFFF Extinguisher cylinder and perform a complete internal inspection of the lining. On the AFFF tank, you will need to open the Master and Bleed valve. Note that the pressure on the manifold gauge reads -0-. Slowly remove the filler cap noting that no pressure vents through the cap vent slot. Inspect the internal lining of the AFFF tank for damage or peeling. Close the bleed valve and Master valve.