BSP_Bid Proposal_PANG Post Replacement 02.03.25.pdf

PDF 599 KB Posted

Attached to
PANG Perimeter Fence Repair
Solicitation number
S-24800-00013101
Issued by
Multnomah County, Oregon

About this file

This document is a proposal submission from Black Security Products, LLC (BSP) for a Pang-Post Replacement project for PANG (Pennsylvania Air National Guard), specifically involving Morgan Miller. The proposal details a comprehensive project to replace one PVB (Perimeter Vulnerability Barrier) post and extend a 300-foot chain link fence, including full removal of existing infrastructure, excavation, installation of new posts, concrete work, and reinstallation of fencing components. The project timeline indicates submittals and design will take 1-2 weeks from order receipt, fabrication/delivery will require 3-4 weeks after approved submittals, and installation is to be determined based on the construction schedule. The proposal is valid for 30 days from the date of submission (2/7/2025).

The total project cost is $66,960.00, which breaks down to $6,500.00 for stamped engineering design, $28,500.00 for post replacement (including removal, excavation, placement, and concrete work), and $14,100.00 for materials and $12,000.00 for installation of the chain link fence extension. The pricing includes one mobilization and material unload, assumes typical site conditions, and explicitly notes that certain elements like survey and locates, removal of spoils, and disposal of the existing post are not included. Payment terms are specified as "Per Contract," and the proposal includes a note that priced units cannot be awarded separately without BSP's written consent.

View the file

Other files

File Type Posted
Base Security Drawings.pdf PDF
deadman.pdf PDF
Repair Base Security Specifications.pdf PDF
Sole Source Contract Perimeter Fence.pdf PDF
RFP S-10700-00013102 ATTACHMENTS B and D-F.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

512-926-0800 www.blacksp.com

25-0203

Revision Number:

Proposal Submission

PROJECT NAME:

Pang-Post Replacement

PREPARED FOR:

SUBMITTED BY:

PANG - Morgan Miller

Black Security Products, LLC

2/7/2025Date:

Proposal Number:

9727 Tanner Rd Houston, TX 77041

Quantity Unit 1 6,500.00$ 1 28,500.00$

*Includes Removal of existing post, Excavation for larger foundation, Placement of new post, Concrete work, Materials *Shallow water table may require removal of ground water prior to contrete pour.

Quantity Unit 1 14,100.00$ 1 12,000.00$ 1 2,200.00$

Includes:

*Install 300' temp fence *Remove Barb Arms and Wire *Remove existing framing and fabric *Install sleeves *Reframe and install 10' fabric.

*Reinstall barb arms & wire Remove 300' Temp Fence

Notes: Sub-Total

Freight Taxes

TOTAL

Installation 12,000.00$ 300' Temp Fence 2,200.00$

Chain Link fence Extension Description Line Total

Materials 300' Full Length Sleeve, 10' fabric, barbed wire 14,100.00$

Replace 1 PVB post per plans 28,500.00$ 6,500.00$

PVB Post Replacement

Cost Breakdown

Description Line Total Stamped Engineering for replacement post design

3,660.00$ Not Included

Pricing in USD unless otherwise noted. All unites in imperial unless otherwise noted. Priced units cannot be awarded separately without the written consent of BSP.

66,960.00$

63,300.00$

Inclusions: Exclusions:

Prepared By:

Nathan Gray Black Security Products Email: ngray@blacksp.com Phone: 512-926-0800

Accepted by:

Printed Name:

Date:

General Terms

Submittals/Design:

Project Schedule

1-2 Weeks from Receipt of Order

By Signing below buyer agrees to pay the full amount for items listed within this proposal under the payment terms included herein.

Disposal of Existing Post

Conditions If installation included, price includes one mobilization and material unload. Installation of systems listed in this proposal only. Installation pricing assumes typical site conditions, scope of work, and standard terms and conditions. Anything not explicitly included is excluded. For material orders, pricing only includes what is listed in this proposal. All material orders do not include rebar, concrete or unload of materials at site. Purchaser must inspect all deliveries for damage and not it on the BOL. If you have any questions or comments please contact me directly.

Installation of quoted material Foundations for quoted material

30 Days from date of proposal

Scope

Submittals

Quoted material supply Survey and Locates Removal of spoils

Amendments: 0 Acknowledgments

Per Contract

Validity:

Fabrication/Delivery: 3-4 Weeks from approved submittals Installation/Commissioning: TBD per construction schedule

Payment Terms

File details come from the government source that posted it. Updated .