This document is a Vendor Questions and Answers addendum for the Maryland Department of Public Safety and Correctional Services (DPSCS) related to the EMMA Solicitation BPM051562 for carpet removal and carpet tile installation at the DPP Silver Springs location. The solicitation covers a carpet replacement project where new carpet tiles will be installed in currently carpeted areas, with work to be completed after business hours between 5:00 pm and 4:00 am Monday through Friday, and between Friday at 5 pm and Monday at 4 am. An initial site visit has already occurred, and additional site visits will not be scheduled. The document provides detailed responses to 12 vendor questions covering logistics such as furniture moving, personal item removal, work hours, and specific installation details.

The document clarifies key project parameters, including that staff will be responsible for removing personal items and boxing them up, but employees will not move furniture. The contractor is not permitted to unplug computer equipment, and staff will handle equipment disconnection after a phasing plan is provided. Only areas currently carpeted will receive new carpet tiles, excluding kitchen and lobby areas. The carpet tile installation will involve multiple product samples, with specific products to be specified for each room. No asbestos presence was reported, and the project has an urgent timeline. Vendors with additional questions are directed to contact Lloyd Houston, the Procurement Officer, via email.

View the file

Other files

File Type Posted
BPM051562-_Vendor_Q_A_1_of_2.pdf PDF
BPM051562_-_Appendix_3_Approved_Color_Examples.pdf PDF
BPM051562_-_Attachment-A.-Bid-Proposal-Affidavit.pdf PDF
BPM051562_-_Attachment-M.-List-of-Current-or-Prior-State-Contracts.pdf PDF
BPM051562_-_Attachment-U.-Contract-Affidavit__4_.pdf PDF
IMG_0202.jpeg JPEG file
Amendment__1_BPM051562_DPP_Carpet_Removal_and_Installation.pdf PDF
BPM051562_-_Attachment-F.-Bidder-Offeror-Information-Sheet__2_.pdf PDF
BPM051562_Facilities_Maintenance_Supplemental__Approved_.pdf PDF
IMG_0199.jpeg JPEG file
IMG_0204.jpeg JPEG file
IMG_0212.jpeg JPEG file
BPM051562_-_Appendix_2_Price_Form_w_Instructions.xlsx XLSX spreadsheet
BPM051562_-_Attachment-N.-Legal-Action-Summary.pdf PDF
IMG_0198.jpeg JPEG file
IMG_0203.jpeg JPEG file
BPM051562_-_DPP_Silver_Springs_Carpet_IFB_w_AMD__1.pdf PDF
BPM051562_Department_of_Parole_and_Probation__DPP__Silver_Springs_Carpet_Removal_and_Installation_Pre_Bid_Minutes__Approved_.pdf PDF
IMG_0205.jpeg JPEG file
IMG_0208.jpeg JPEG file
IMG_0209.jpeg JPEG file
IMG_0205.jpeg JPEG file
IMG_0208.jpeg JPEG file
IMG_0212.jpeg JPEG file
IMG_0198.jpeg JPEG file
IMG_0199.jpeg JPEG file
IMG_0202.jpeg JPEG file
IMG_0209.jpeg JPEG file
IMG_0203.jpeg JPEG file
IMG_0204.jpeg JPEG file
IMG_0199.jpeg JPEG file
IMG_0204.jpeg JPEG file
IMG_0202.jpeg JPEG file
IMG_0198.jpeg JPEG file
IMG_0203.jpeg JPEG file
IMG_0205.jpeg JPEG file
IMG_0208.jpeg JPEG file
IMG_0209.jpeg JPEG file
IMG_0212.jpeg JPEG file
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VENDOR QUESTIONS AND ANSWERS 2 of 2

EMMA SOLICITATION BPM051562

DPP SILVER SPRINGS

CARPET REMOVAL AND CARPET TILE INSTALLATION

Date of Issue: August 21, 2025

Dear Vendors:

This list of Questions from vendors and Responses from the State are provided to clarify the information contained in the above named IFB.

The statements and interpretations of contract requirements, which are stated in the following questions from potential Bidders, are not binding on the State, unless the State expressly amends the IFB. Nothing in the Department’s responses to these questions is to be construed as agreement to or acceptance by the Department of any statement or interpretation on the part of the vendor asking the question as to what the contract does or does not require.

1. Q. Can we do a walkthrough to assess the amount of furniture that will be moved for every room.

A. Due to the urgent need of this contract, an additional site visit will not be scheduled. The pictures of the previous site visit and floor plans uploaded on eMMA provide an adequate picture of the condition area and office space.

Most offices consist of desks, chairs and a file cabinet for each person assigned to the office with some offices having shared bookcases.

2. Q. Can we obtain a copy of the building floor plan layout to assess the direction that the carpet will be installed.

A. A picture of the floor plans has been uploaded with the solicitation in eMMA

3. Q. Is the customer aware of asbestos presence on the floor; if asbestos is known; has the customer contracted an asbestos abatement process prior to old carpet removal and new installation.

A. DPSCS is not aware of any asbestos present.

4. Q. Will the customer remove personal items from offices such as (peripherals, computers, books, documents, etc.). What is the plan for employee personal belongings?

STATE OF MARYLAND

WES MOORE

GOVERNOR

ARUNA MILLER

LT. GOVERNOR

CAROLYN J. SCRUGGS

SECRETARY

ANTHONY A. GASKINS

CHIEF OF STAFF

JOSEPH SEDTAL

DEPUTY SECRETARY

ADMINISTRATION

ANNIE D. HARVEY

DEPUTY SECRETARY

OPERATIONS

ANGELINA GUARINO

ASSISTANT SECRETARY

DATA, POLICY AND GRANTS

RENARD E. BROOKS

ASSISTANT SECRETARY

PROGRAMS, TREATMENT &

RE-ENTRY SERVICES

Department of Public Safety and Correctional Services

Office of the Secretary

6776 Reisterstown Road, Baltimore, Maryland 21215 410-585-3346 – TOLL FREE 877-379-8636 • www.dpscs.maryland.gov

A. Yes, staff will be required to remove and/or securely box up all personal items. Staff will be directed to remove personal items and/or securely place them in boxes.

5. Q. Will they have them packed up so it's only furniture and computers that have to be moved?

A. Yes

6. Q. Will the employees move as much of the furniture out of offices depending on the phase or area of removal/installation might be for the day's work?

A. No. Employees are not responsible for moving any furniture.

7. Q. If a computer is not unplugged, are we able to unplug it and then plug it back in?

A. No, staff will be directed to unplug equipment once a phasing plan has been provided.

8. Q. What product is being used in the different group samples? Why are there two different carpet tile samples?

A. The list of brands is included with the pictures of approved samples.

9. Q. Is someone able to specify what product is being installed into each room if a drawing/as-is plans are being provided?

A. Yes. The plan for installation should include what product will be installed in each room.

10. Q. Is the entire area getting carpet tile or just the areas that currently have carpet?

A. The areas currently carpeted will receive the new carpet tiles.

11. Q. During the site visit someone mentioned the tile areas are being carpeted.

Does that include the kitchen area and lobby area?

A. No these areas are not going to be carpeted.

12. Q. Will weekend hours be allowed to be worked?

A. The IFB says in section 2.3.1 states “The Contractor’s work is to be completed after business hours, between 5:00pm - 4:00am Monday through Friday and day and night work between Friday at 5pm - 4am Monday.”

If there are additional questions concerning this solicitation, please contact Lloyd Houston at Lloyd.houston@maryland.gov.

END OF ADDITIONAL QUESTIONS

Issued and Authorized by:

Lloyd Houston Procurement Officer I

Date

08/21/2025