Reflooring of an Office at the USUN Building, Rome, Italy
Solicitation number
191T7023Q0039
Issued by

About this file

This document contains a bill of quantities for reflooring an office at the USUN building in Rome, Italy. The scope of work includes removal of existing textile flooring and baseboards, preparation of the surfaces, supply and installation of new teak wood flooring over 150 square meters along with new solid wood baseboards totaling 120 linear meters. Safety and cleaning requirements are also specified. The total cost is 36,600 euros with 11,025 euros accounting for labor. The related federal contract opportunity is solicitation number 191T7023Q0039 for the reflooring work being conducted by the Department of State at the USUN building in Rome.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

No. DESCRIPTION UNIT COST

TOTAL COST

PERCENTAGE

MANPOWER

REMOVALS AND DEMOLITIONS

Removal by hand of existing textile floor covering all around the rooms, below the faincoil included (approx. 150 sqm). Removal the current glue and debris by the floor and proceed to prepare the surface for the wooden installation. The surface must be free from dust, wax, loose parts, oil residues, paints, etc.

lump sum 1 1,500.00 € -

2 Removal of existing baseboard (approx. 120 lm) lump sum 1 800.00 € -

Loading and transport to authorized landfills and / or plants including loading, round trip and unloading including landfill charges at authorized facilities lump sum 1 1,000.00 € -

Preparation of the work site, movement of existing furniture, store it and reinstall it at the end of the work lump sum 1 1,000.00 € -

CIVIL WORKS

Prepare the surface to spread the single-component glue for parquet. Apply single-component adhesive with a silanic termination that reduce noise, recommended for gluing of pre-finished wooden floor onto marble, grit, ceramic or marble-chip floor tiles and with acoustic insulation. Supply and install new wooden floor Teak Burma in Solid

Wood with board thickness of 15mm (approx. 150 sqm). T&G Decking joints. Design

Chevron 45°. Bevelled on 4 sides, hand brushed, hand planed and carved (length 600mm width 120mm), painted with polyurethane varnish matte vax effect. Included thresholds to connect the different quotes between the rooms. If the planing of the existing doors is too high, provide to levelled it. All samples shall be submitted to Embassy C.O.R.

lump sum 1 30,000.00 € 35%

(10,500.00 €)

Supply and install new Solid Wood Baseboard type Ducale white of 120mm height and

13mm thickness (approx. 120 lm). All the switches present along the baseboard way, shall cut in place. As th pieces below the windows and the faincoils. All samples shall be submitted to Embassy C.O.R.

lump sum 1 1,500.00 € 35%

(525.00 €)

Safety and Cleaning

7 Submit a Safety Plan for the entire project to the approval of the Embassy superintendent lump sum 1 500.00 € -

8 General and deep cleaning of the premise lump sum 1 300.00 € -

36,600.00 € 11,025.00 € Total

USUN DCM OFFICE FLOOR RENOVATION