This document is a Statement of Work (SOW) for engineering assessment and repair of concrete spalling at the U.S. Coast Guard Station in Destin, FL. The project requires a contractor to conduct a comprehensive inspection of concrete cracks in boathouse structural support pillars/columns, generate a detailed report with photographic documentation, crack mapping, and structural integrity assessment, and develop a certified repair plan sealed by a Florida-licensed Professional Engineer. The repair plan must include detailed drawings, material specifications, surface preparation methods, reinforcement repair techniques, concrete repair procedures, corrosion protection measures, and a structural analysis demonstrating that repaired columns will meet original design load capacity.
The solicitation is a small business set-aside using NAICS code 236118 with a size standard of $39.5M, resulting in a Firm-Fixed Price Construction Contract awarded to the lowest-price quoter. The project is for the Department of Homeland Security's U.S. Coast Guard, located at 2000 Miracle Strip Parkway in Destin, FL. Contractors must be registered in the System for Award Management (SAM) and will perform work Monday through Friday from 7:00 am to 4:00 pm, with potential for extended hours upon prior approval. Delivery is expected within 30 days ARO (After Receipt of Order) to the specified Coast Guard station, with specific requirements for environmental compliance, safety protocols, utility usage, and site security.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Constructions.Solicitation.1.docx | DOCX document | |
| Spalling.Concrete.Boat.House.vendor.Questions&Answers.docx | DOCX document | |
| Construction Clauses Provisions FAC 2023-01 (002).docx | DOCX document | |
| Constructions.Solicitation.1.docx | DOCX document | |
| Construction Clauses Provisions FAC 2023-01 (002).docx | DOCX document | |
| OPFAC.30327.C.SITE.PLAN.drawing#3.pdf | ||
| Destin.boathouse.drawing.#2.pdf | ||
| Destin.boathouse.drawings#1.pdf | ||
| Constructions.Solicitation.1.docx | DOCX document | |
| Constructions.Solicitation.1.docx | DOCX document | |
| SF.18.pdf | ||
| Constructions.Solicitation.1.docx | DOCX document | |
| wage.determination.FL.pdf | ||
| OF 336.continuation.pdf | ||
| Construction Clauses Provisions FAC 2023-01 (002).pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT SPECIFICATIONS
Engineering Assessment and Repair of Cracks in the Boat House Concrete Spalling’s
AT
UNITED STATES COAST GUARD
Station Destin, FL
PROJECT 26-081
December 2025
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 GENERAL DESCRIPTION:
A. Contractor shall conduct an inspection of any cracks in the concrete spalling’s for the boathouse structural support pillars/columns and document all findings.
B. The contractor shall generate a detailed report on their findings, including the following:
Photographic documentation of all cracks and spalling, with scale and location noted.
Crack mapping (length, width, depth, orientation).
Overall assessment of the structural integrity of the columns and the need for repair or replacement.
A description of the original construction, including the materials used and the construction methods, if known.
C. The contractor shall generate a certified repair plan signed and sealed by a qualified Professional Engineer (PE) licensed in the State of Florida. The repair plan shall include, at a minimum:
Detailed drawings showing the extent of repairs.
Specifications for all repair materials (including concrete mix design, reinforcement type, and coatings).
Surface preparation methods.
Reinforcement repair or replacement methods.
Concrete repair methods (patching, form and pour).
Corrosion protection measures (coatings, sealants, cathodic protection).
Installation procedures and quality control measures.
A structural analysis demonstrates that the repaired column will meet or exceed its original design load capacity.
D. The contractor shall complete repairs as per their certified repair plans and provide documentation of all work performed, including photos and material certifications.
1.1. TEMPORARY FACILITIES OR UTILITIES
None required.
1.2. LOCATION
The work is located at:
U.S. Coast Guard Station Destin 2000 Miracle Strip Pkwy Destin, FL 32541 Arrangements for visiting the site may be made by contacting:
MKC Daniel Flanigan Email: daniel.p.flanigan@uscg.mil Telephone: 315-406-2736
1.3. DRAWINGS ACCOMPANYING SPECIFICATION
There are no drawings accompanying this specification.
1.4. WORK HOURS
1.4.1. Normal Working Hours
A. Perform all work at the site from Monday through Friday from 7:00am to 4:00 pm, unless otherwise approved. This project requires a special schedule to prevent operational interruptions during the installation process. Please refer to the scope section for detailed coordination of working hours. The contractor shall plan a schedule to minimize disruptions to building operations.
B. Performing the work beyond the listed working hours is at the discretion of the Coast Guard unit and the contractor must gain prior approval.
1.5. SPECIFIC ENVIRONMENTAL REQUIREMENTS
There are no specific environmental requirements. Refer to section titled Environmental for general environmental requirements.
1.6. SAFETY PROGRAM
1.6.1. General
The Contractor is wholly responsible for work site safety. Implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property and avoids work interruptions. Provide appropriate safety measures including but not limited to barricades, signs and signal lights as well as complying with the requirements of all applicable federal, State and local safety laws, rules and regulations.
1.7. AVAILABILITY OF UTILITY SERVICES
A. Reasonable amounts of the following utilities will be made available to the Contractor without charge.
(1) Electricity, and
(2) Potable Water.
B. The Contractor shall pay all costs incurred in connecting, converting, and transferring the utilities to the work. The contractor shall be responsible for making connections including providing back flow preventers, transformers and for disconnection. The contractor shall provide temporary toilet facilities for their personnel.
1.8. UNDERGROUND AND CONCEALED UTILITIES
A. Any utility locations provided are diagrammatic, not exact.
B. Physically verify the location and elevation of the existing underground and concealed utilities local to the work area. Employ techniques to scan the construction site including electromagnetic and sonic equipment prior to commencing the work. Mark the surface of the ground where existing underground utilities are discovered.
1.9. UTILITY OUTAGES
Identify the utility, reason for interruption, proposed time of interruption, and duration of interruption. Do not interrupt utilities until authorized by the Contracting Officer’s Representative (COR).
1.10. CONTRACTOR USE OF PREMISES
The work shall be performed on a Coast Guard operational military installation. Become familiar with and obey station fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work or direct avenues of ingress and egress unless authorized in advance by the COR. Isolate each construction area with temporary partitions and dust controls. Provide movable high-visibility safety fencing about all work areas and equipment laydown areas located outdoors. Provide temporary covers on excavations that remain open overnight.
1.11. CLEANUP
The Contractor shall keep the work area, including the laydown and storage area, free from accumulations of waste materials on a daily basis and comply with all federal, state, and local regulations pertaining to the storage, transport, and disposal of wastes. The Contractor shall not use Coast Guard waste disposal facilities including garbage cans, trash piles, or dumpsters.
1.12. ENVIRONMENTAL
1.12.1. Protection of the Environment
The Contractor shall comply with all applicable federal, state, and local laws and regulations for the protection of the environment, including but not limited to the Endangered Species Act (ESA), Bald and Golden Eagle Protection Act (BGEPA), the Migratory Bird Treaty Act (MBTA), National Historic Preservation Act (NHPA), the Resource Conservation and Recovery Act (RCRA), and Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA).
1.12.2. Generated Waste
A. Any waste generated because of the project shall either be recycled or be disposed of in accordance with RCRA requirements.
B. Any hazardous waste shall be manifested off site with the Coast Guard unit listed as the Generator and signatory. Any hazardous waste shall be analyzed, characterized, stored, and disposed of in accordance with RCRA and all applicable federal, state, and local laws and ordinances.
C. Hazardous waste shall be properly transported and delivered to an appropriate facility. The Contractor shall submit for COR approval the proposed disposal facility, qualifications of the transporters, and the draft hazardous waste manifest.
1.13. DISPOSITION OF MATERIALS
A. All materials including construction debris and equipment shall be removed from Government property. The Government will not be responsible for the condition or loss of, or damage to, such property after notice to proceed. Materials and equipment shall not be viewed by prospective purchasers or sold on the site.
B. The Contractor shall submit the disposal receipt from the landfill within 10 working days of disposal.
1.14. STORM PROTECTION
The Contractor shall take every practicable precaution to minimize danger from storms to personnel, the work, and to adjacent property. Precautions shall include, but not be limited to, closing all opening, removing all loose materials, tools, and equipment from exposed locations, and removing or securing scaffolding and other temporary work.
1.15. RECEIPT OF MATERIALS
The Contractor is responsible to receive all equipment, materials, and supplies.
1.16. DELIVERY AND STORAGE
The Contractor is responsible for the proper transport and storage of all equipment and materials.
1.17. SECURITY
A. Submit a list of the names of all personnel working on the project site prior to the preconstruction conference for approval. The roster shall be submitted via email, and at a minimum, include the first name, last name, job description, and company of employment.
B. Immediately submit a new list upon a change in on-site project personnel. Refer to the paragraph titled, Special Notice Prior Notification, for notification requirements. Only personnel on the approved list are allowed onto the project site.
C. All approved personnel shall carry a valid, Government-issued identification while on Government property in conformance with the Real ID Act of 2005. Non-compliant personnel shall be escorted off Government property.
1.18. FINAL INSPECTION AND ACCEPTANCE
A. Electronically submit a written request for final acceptance to the Coast Guard.
1.19. WARRANTIES
A. Endorse all warranties or guarantees to the Government.
1.20. TRAINING
A. The Contractor shall provide training to unit personnel in the operation of the equipment. The Operation and Maintenance Manuals shall be approved and provided to the unit prior to the training.
1.21. SUBMITTALS
A. Submittals will be reviewed by the Coast Guard and returned within 10 working days after receipt, unless otherwise stated.
1.22. SUBMITTAL LIST
A. ROSTER OF PERSONNEL
(1) As required by the paragraph titled Security.
B. PROJECT SCHEDULE
(1) Prepare a Construction Progress Schedule. It shall include all major milestones and events for the entire duration of the construction contract.
C. SAFETY PLAN
(1) At a minimum, describe the general safety program and identify specific safety provisions for hazards incidental to the contract work such as elevated working surfaces, or similar conditions of the work. Comply with the paragraph titled Safety Program.
D. PRODUCT DATA
(1) Submit the product data sheet for each manufactured item. It shall include the manufacturer's descriptive literature of cataloged products, equipment drawings, diagrams, performance and characteristic curves and catalog cuts. Submit complete descriptive data for each type of material. Clearly mark data to indicate the type of material to be provided.
1.22.2. OPERATION AND MAINTENANCE MANUALS
A. Submit electronically and provide the following:
(1) Contact information for the prime contractor, sub-contractor, and major equipment vendor/supplier;
(2) Warranty information;
(3) Test procedures;
(4) Results of all testing and commissioning procedures;
(5) Performance data;
(6) A control sequence describing start-up, operation and shut-down instructions;
(7) Installation instructions;
(8) Maintenance instructions;
(9) Operating instructions;
(10) Parts list.
-- End of Section --