BLOOMINGTON POLICE DEPARTMENT GARAGE DOUBLE TEE STEM – IMMEDIATE REPAIRS 2025
Solicitation number
2026-07
Issued by
Mclean County, Illinois

About this file

The document is a comprehensive set of construction specifications for the Bloomington Police Department Garage Double Tee Stem Immediate Repairs project located in Bloomington, Illinois, prepared by Walker Consultants in June 2025. The project involves immediate repair work for a parking structure, specifically focusing on replacing a damaged double tee stem, performing concrete repairs, installing a new steel beam with shear studs, replacing joint sealants, and applying traffic bearing waterproofing membrane. The City of Bloomington is soliciting sealed bids through their e-Procurement Portal, with submissions due on Thursday, July 24, 2025, at 2:00 pm CST for a project estimated to be over $50,000.

The project includes specific technical requirements for concrete surface preparation, structural steel framing, traffic coatings, joint sealants, and pavement markings. A notable requirement is the potential implementation of a project labor agreement, which must adhere to Illinois Prevailing Wage Act standards and cannot mandate union membership. The specifications outline detailed technical requirements for materials, installation methods, quality control, and warranty provisions, with a focus on durability, proper surface preparation, and long-term performance of the parking structure repairs. The project appears to be publicly funded, with an emphasis on maintaining the structural integrity and functionality of the Bloomington Police Department parking garage.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Construction Specifications Volume 2: Technical Specifications

Bloomington Police Department Garage Double Tee Stem – Immediate Repairs Bloomington, Illinois

June 25, 2025

Bloomington Police Department Construction Documents Garage Double Tee Stem Immediate Repairs 2025 June 25, 2025 Project Number 31-010126.00

©2025, Walker Consultants. All rights reserved.

TABLE OF CONTENTS 00 01 10 - 1

PART 2 - TECHNICAL SPECIFICATIONS

SECTION 00 01 10 � TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 10 Summary of Work - Restoration 01 26 00 Contract Modification Procedures 01 29 00 Payment Procedures 01 31 00 Project Management and Coordination 01 32 00 Construction Progress Documentation 01 33 00 Submittal Procedures 01 40 00 Quality Control 01 50 00 Temporary Facilities and Controls 01 60 00 Product Requirements 01 73 00 Execution 01 77 00 Closeout Procedures 01 78 39 Project Record Documents

DIVISION 02 � EXISTING CONDITIONS

02 00 10 Work Items 02 51 30 General Concrete Surface Preparation 02 51 40 Surface Preparation for Patching

DIVISION 03 � CONCRETE

03 33 00 Cast-In-Place Concrete

DIVISION 05 � METALS

05 12 00 Structural Steel Framing

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 18 00 Traffic Coatings 07 92 33 Concrete Joint Sealants

DIVISION 09 � FINISHES

09 91 20 Pavement Marking

END OF SECTION 00 01 10

Copyright 2025. All rights reserved. No part of this document may be reproduced in any form or by any means without permission from Walker Consultants.

Project Number 31-010126.00

©2025, Walker Consultants. All rights reserved.

TABLE OF CONTENTS 00 01 10 - 1

PART 2 - TECHNICAL SPECIFICATIONS

SECTION 00 01 10 – TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 10 Summary of Work - Restoration 01 26 00 Contract Modification Procedures 01 29 00 Payment Procedures 01 31 00 Project Management and Coordination 01 32 00 Construction Progress Documentation 01 33 00 Submittal Procedures 01 40 00 Quality Control 01 50 00 Temporary Facilities and Controls 01 60 00 Product Requirements 01 73 00 Execution 01 77 00 Closeout Procedures 01 78 39 Project Record Documents

DIVISION 02 – EXISTING CONDITIONS

02 00 10 Work Items 02 51 30 General Concrete Surface Preparation 02 51 40 Surface Preparation for Patching

DIVISION 03 – CONCRETE

03 33 00 Cast-In-Place Concrete

DIVISION 05 – METALS

05 12 00 Structural Steel Framing

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 18 00 Traffic Coatings 07 92 33 Concrete Joint Sealants

DIVISION 09 – FINISHES

09 91 20 Pavement Marking

END OF SECTION 00 01 10

©Copyright 2025. All rights reserved. No part of this document may be reproduced in any form

SUMMARY OF WORK - RESTORATION 01 11 10 - 1

SECTION 01 11 10 - SUMMARY OF WORK - RESTORATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 01 Specification Sections apply to this Section.

1.2 PROJECT DESCRIPTION

A. Work will be performed at locations within parking structure as shown on Drawings.

B. Work required in these areas and estimated quantities are listed on Bid Form. Bid Quantities associated with Work Items listed on Drawings have been estimated and are subject to measurement as defined in Article "Measurements." Where additional Work Items are described, but not specifically located and/or shown on Drawings, Contractor shall be responsible for locating and marking areas to be repaired. Owner and/or Engineer/Architect reserves right to increase or decrease quantities up to 25% at same unit cost, as required by job conditions.

C. Work Item specifications and details shall govern all repair operations. Locations where Work Items apply are shown on Drawings as symbols.

D. Final payment shall be made on basis of actual approved Work performed as measured in place.

E. Project comprises a parking facility for the Bloomington Police Department Facility at 305 S. East Street in Bloomington, Illinois 61701.

F. Work consists of the following:

1. Remove damaged double tee stem and replace with new steel beam with shear studs. Perform full depth concrete repair of the topping slab within the designated area of the tee stem replacement. Perform partial depth concrete repairs as indicated at select locations by the engineer.

2. Replace sealant at select double tee joints and designated cove joints.

3. Install traffic bearing waterproofing membrane at designated double tee joints and at the area where the double tee stem is removed and replaced with the steel beam.

1.3 MEASUREMENTS

SUMMARY OF WORK - RESTORATION 01 11 10 - 2

A. Before ordering any material or doing any Work, Contractor shall verify all measurements at Project site and shall be responsible for correctness of same.

B. Before proceeding with each Work Item, Contractor shall locate, mark, and measure quantity of each item and report quantities to Engineer/Architect. If measured quantities exceed Engineer/Architect's estimate, Contractor shall obtain written authorization to proceed from Owner before executing Work required for that Work Item.

C. Measurement of quantities for individual Work Items will be performed by Contractor and reviewed by Engineer/Architect. Coordinate measurements with inspection as required in Section "Project Management and Coordination."

D. Cost of Work included in each Work Item for quantities as indicated in Contract Documents shall be included in Base Bid.

1. Additions to or deductions from lump sum price for quantities of each Work Item added to or deducted from Work respectively shall be at unit prices indicated in Bid Form and shall constitute payment or deductions in full for all material, equipment, labor, supervision and incidentals necessary to complete Work.

1.4 WORK SEQUENCE

A. Prior to commencement of work, meet with Engineer/Architect and Owner representatives to establish sequence and schedule of Work. Contractor shall give Owner notice of areas to be cleared of cars at least 2 working days in advance of actual Work.

B. Contractor shall notify Owner's representative at least 24 hr prior to beginning any abrasive blasting operations.

C. Contractor shall remove all broken concrete and debris from Work area on daily basis and dispose of same at authorized dump sites.

D. Contractor shall remove dust and air transported sand/debris from remainder of facility at conclusion of operations in Work area.

1.5 CONTRACTOR USE OF PREMISES

A. General: Limit use of premises to construction activities in areas indicated; allow for Owner occupancy and use by public.

1. Contractor shall limit the closed parking spaces to only those within the designated work area per the project drawings (2) on Level 1, (5) on Lower Level 1, and (5) on Lower Level 2.

SUMMARY OF WORK - RESTORATION 01 11 10 - 3

2. Confine operations to areas within Contract limits indicated. Portions of the site beyond areas in which construction operations are indicated are not to be disturbed.

3. Keep driveways and entrances serving the premises clear and available to the Owner and Owner's employees at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on site.

B. Contractor's use of premises shall not interfere with operation of same. Elevators shall not be used for transfer of materials or equipment.

C. Contractor's debris removal path shall be over non-repaired services unless physical restraints prevent use of such path.

D. Contractor shall confine its apparatus, materials, equipment, tool cribs, field offices and operations to areas designated by Owner and/or Engineer/Architect (see cover sheet of project drawings). Premises shall not be unreasonably encumbered with materials and equipment. Neat and orderly stockpiling and other operations shall be maintained and debris shall be regularly removed from site. Contractor shall not load or permit any part of structure to be loaded with weight that will endanger structural integrity or safety of facility. Contractor shall limit axle loads to maximum 4000 lb per axle and gross weight of 8000 lb, or stockpiling of materials and equipment to 50 lb per sq ft. Contractor to note existing height restrictions within parking structure.

E. Contractor Parking: Contractor's employees shall park in the parking area designated on the cover sheet of the project drawings.

F. On-Site Storage: Contractor shall not store materials or equipment at site of Work for more than one week prior to time that materials or equipment are incorporated into Work.

The designated material storage and staging area is shown on the cover sheet of the project drawings.

1.6 BARRICADES

A. Provide positive barricading to separate Work areas from areas open to public and to prevent the need for washing cars parked adjacent to the work area. Minimum acceptable separation: 4 ft. 0 in. high temporary barrier. Provide additional barriers as required to prevent damage to vehicle due to airborne debris. See "Temporary Facilities" for additional requirements.

1.7 CLAIMS

A. Contractor shall promptly address all damages claims. Owner reserves right to resolve any claims not addressed by Contractor within 3 wks after claim is received by Contractor. Any amounts paid by Owner will be deducted from Contractor's next progress payment.

SUMMARY OF WORK - RESTORATION 01 11 10 - 4

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

END OF SECTION 01 11 10

© Copyright 2025. All rights reserved. No part of this document may be reproduced in any form

CONTRACT MODIFICATION PROCEDURES 01 26 00 - 1

SECTION 01 26 00 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements for handling and processing contract modifications.

B. Related Requirements:

1. Division 01 Section "Unit Prices" for administrative requirements governing use of unit prices.

2. Division 01 Section "Submittal Procedures" for requirements for Contractor's Construction Schedule.

3. Division 01 Section "Payment Procedures" for administrative procedures governing applications for payment.

1.3 MINOR CHANGES IN THE WORK

A. Engineer will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710.

1.4 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Proposed changes in Work that will require adjustment to Contract Sum or Contract Time will be issued by Engineer, with detailed description of proposed change and supplemental or revised Drawings and Specifications, if necessary.

1. Work Change Proposal Requests issued by Engineer are not instructions either to stop work in progress or to execute the proposed change.

2. Within 10 days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

CONTRACT MODIFICATION PROCEDURES 01 26 00 - 2

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and supervision directly attributable to the change.

d. Include statement indicating effect proposed change in Work will have on

Contract Time.

B. Contractor-Initiated Change Order Proposal Requests: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Engineer.

1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Submit request no later than 5 working days after discovery of condition.

6. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

7. Comply with requirements in Division 01, Section "Contract Modification Procedures" if the proposed change requires substitution of one product or system for product or system specified.

C. Proposal Request Form: Use AIA Document G709 or form acceptable to Engineer.

1.5 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Work Change Proposal Request, Contractor shall proceed with the work within 5 days.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

END OF SECTION 01 26 00

PAYMENT PROCEDURES 01 29 00 - 1

SECTION 01 29 00 - PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements necessary to prepare and process Applications for Payment.

B. Related Requirements:

1. Division 01 Section "Unit Prices" for administrative requirements governing use of unit prices.

2. Division 01 Section "Construction Progress Documentation" for administrative requirements governing preparation and submittal of Contractor's Construction Schedule and Submittals Schedule.

1.3 APPLICATIONS FOR PAYMENT

A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by Owner and paid for by Owner.

B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.

C. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 as form for Applications for Payment.

D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Engineer will return incomplete applications without action.

1. Entries shall match data on the Schedule of Values and Contractor's Construction Schedule. Use updated schedules if revisions were made.

2. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

PAYMENT PROCEDURES 01 29 00 - 2

E. Transmittal: Submit electronically signed and notarized original copies of each Application for Payment to Owner. Include waivers of lien and similar attachments if required.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

F. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from entities lawfully entitled to file a mechanic's lien arising out of the Contract and related to the Work covered by the payment.

1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.

2. When an application shows completion of an item, submit conditional final or full waivers.

3. Owner reserves the right to designate which entities involved in the Work must submit waivers.

4. Waiver Delays: Submit each Application for Payment with Contractor's waiver of mechanic's lien for construction period covered by the application.

a. Submit final Application for Payment with or preceded by final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien.

5. Waiver Forms: Submit waivers of lien on forms, executed in a manner acceptable to Owner.

G. Application for Payment at Substantial Completion: After issuing the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This application shall reflect Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work.

H. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

3. Updated final statement, accounting for final changes to the Contract Sum.

4. AIA Document G706, "Contractor's Affidavit of Payment of Debts and Claims."

5. AIA Document G706A, "Contractor's Affidavit of Release of Liens."

6. AIA Document G707, "Consent of Surety to Final Payment."

7. Evidence that claims have been settled.

PAYMENT PROCEDURES 01 29 00 - 3

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

END OF SECTION 01 29 00

PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 1

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. General coordination procedures.

2. Coordination drawings.

3. RFIs.

4. Project meetings.

B. Related Sections: The following Sections contain requirements that relate to this Section:

1. Division 01 Section "Construction Progress Documentation" for preparing and sub-mitting the Contractor's Construction Schedule.

2. Division 01 Section "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Division 01 Section "Closeout Procedures" for coordinating Contract closeout.

1.3 INFORMATIONAL SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

B. Key Personnel Names: Within 5 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and cellular telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.

PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 2

1.4 COORDINATION

A. Coordination: Coordinate construction operations included in various Sections of the Specifications to ensure efficient and orderly installation of each part of the Work.

Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. If necessary, prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the schedule of values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Project closeout activities.

1.5 REQUEST FOR INFORMATION (RFI)

A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Engineer will return without response those RFIs submitted to Engineer by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 3

2. Project number.

3. Date.

4. Name of Contractor.

5. Name of Engineer.

6. RFI number, numbered sequentially.

7. RFI subject.

8. Specification Section number and title and related paragraphs, as appropriate.

9. Drawing number and detail references, as appropriate.

10. Field dimensions and conditions, as appropriate.

11. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

12. Contractor's signature.

13. Attachments: Include sketches, descriptions, measurements, photos, Product

Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Forms: AIA Document G716 or Software-generated form with substantially the same content as indicated above, acceptable to Engineer.

1. Attachments shall be electronic files in PDF format.

D. Engineer's Action: Engineer will review each RFI, determine action required, and respond. Allow seven working days for Engineer's response for each RFI. RFIs received by Engineer after 1:00 p.m. will be considered as received the following working day.

1. The following Contractor-generated RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract

Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Engineer's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Engineer's action may include a request for additional information, in which case Engineer's time for response will date from time of receipt by Engineer of additional information.

3. Engineer's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Division 01, Section "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Engineer in writing within 5 days of receipt of the RFI response.

PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 4

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly. Include the following:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Engineer.

4. RFI number including RFIs that were returned without action or withdrawn.

5. RFI description.

6. Date the RFI was submitted.

7. Date Engineer's response was received.

8. Identification of related Minor Change in the Work, Construction Change Directive, and Proposal Request, as appropriate.

9. Identification of related Field Order, Work Change Directive, and Proposal

Request, as appropriate.

F. On receipt of Engineer's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Engineer within seven days if Contractor disagrees with response.

1.6 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Engineer of scheduled meeting dates and times.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner and Engineer, within three days of the meeting.

B. Preconstruction Conference: Schedule and conduct a preconstruction conference before starting construction, at a time convenient to Owner and Engineer, but no later than 15 days after execution of the Agreement.

1. Attendees: Authorized representatives of Owner, Engineer, and their consultants;

Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

2. Agenda: Discuss items of significance that could affect progress, including the following:

a. Responsibilities and personnel assignments.

b. Tentative construction schedule.

c. Phasing.

d. Critical work sequencing and long lead items.

PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 5

e. Designation of key personnel and their duties.

f. Lines of communications.

g. Procedures for processing field decisions and Change Orders.

h. Procedures for RFIs.

i. Procedures for processing Applications for Payment.

j. Use of the premises.

k. Work restrictions.

l. Working hours.

m. Owner's occupancy requirements.

n. Responsibility for temporary facilities and controls.

o. Procedures for moisture and mold control.

p. Procedures for disruptions and shutdowns.

q. Construction waste management and recycling.

r. Parking availability.

s. Work and storage areas.

t. Equipment deliveries and priorities.

u. First aid.

v. Security.

w. Progress cleaning.

C. Project Closeout Conference: Schedule and conduct a project closeout conference, at a time convenient to Owner and Engineer, but no later than 10 days prior to the scheduled date of Substantial Completion.

1. Conduct the conference to review requirements and responsibilities related to Project closeout.

2. Attendees: Authorized representatives of Owner, Engineer, and their consultants;

Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting. Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:

a. Preparation of Record Documents.

b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.

c. Submittal of written warranties.

d. Preparation of Contractor's punch list.

e. Procedures for processing Applications for Payment at Substantial

Completion and for final payment.

f. Responsibility for removing temporary facilities and controls.

D. Progress Meetings: Conduct progress meetings at Monthly intervals.

1. Attendees: In addition to representatives of Owner and Engineer, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

PROJECT MANAGEMENT AND COORDINATION 01 31 00 - 6

2. Agenda: Review and correct or approve minutes of previous progress meeting.

Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting.

Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next period.

b. Review present and future needs of each entity present, including the following:

1) Construction Progress

2) Status of submittals.

3) Site use.

4) Quality and work standards.

5) Status of correction of deficient items.

6) Field observations.

7) Status of RFIs.

8) Status of Proposal Requests.

9) Status of Change Orders.

10) Documentation of information for payment requests.

3. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information.

a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

END OF SECTION 01 31 00

CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 1

SECTION 01 32 00 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Contractor's Construction Schedule.

B. Related Sections include the following:

1. Division 01 Section "Project Management and Coordination" for submitting and distributing meeting and conference minutes.

2. Division 01 Section "Submittal Procedures" for submitting schedules and reports.

3. Division 01 Section "Quality Control" for submitting a schedule of tests and inspections.

1.3 INFORMATIONAL SUBMITTALS

A. Format for Submittals: Submit required submittals in the following format:

1. Working electronic copy of schedule file, where indicated.

2. PDF file.

B. Contractor's Construction Schedule: Initial schedule of size required to display entire schedule for entire construction period.

1.4 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.

B. Coordinate Contractor's Construction Schedule with the Schedule of Values, submittals schedule, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from parties involved.

CONSTRUCTION PROGRESS DOCUMENTATION 01 32 00 - 2

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

1.5 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL

A. Contractor's Construction Schedule Updating: At monthly intervals, update schedule to reflect actual construction progress and activities. Issue schedule one week before each regularly scheduled progress meeting.

1. Revise schedule immediately after each meeting or other activity where revisions have been recognized or made. Issue updated schedule concurrently with the report of each such meeting.

2. Include a report with updated schedule that indicates every change, including, but not limited to, changes in logic, durations, actual starts and finishes, and activity durations.

3. As the Work progresses, indicate final completion percentage for each activity.

B. Distribution: Distribute copies of approved schedule to Engineer and Owner, separate contractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.

1. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.

1.6 GANTT-CHART SCHEDULE REQUIREMENTS

A. Gantt-Chart Schedule: Submit a comprehensive, fully developed, horizontal, Gantt-chart-type, Contractor's Construction Schedule within 10 days of date established for commencement of the Work.

B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line.

1. For construction activities that require 3 months or longer to complete, indicate an estimated completion percentage in 10 percent increments within time bar.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 01 32 00

SUBMITTAL PROCEDURES 01 33 00 - 1

SECTION 01 33 00 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.

B. Related Requirements:

1. Division 01 Section "Payment Procedures” For submitting Applications for Pay-ment and the schedule of values.

2. Division 01 Section "Project Management and Coordination" for submitting coordination drawings and subcontract list and for requirements for web-based Project software.

3. Division 01 Section "Construction Progress Documentation" for submitting schedules and reports, including Contractor's construction schedule.

4. Division 01 Section "Closeout Procedures" for submitting closeout submittals and maintenance material submittals.

1.3 DEFINITIONS

A. Action Submittals: Written and graphic information and physical samples that require Engineer's responsive action. Action submittals are those submittals indicated in individual Specification Sections as "action submittals."

B. Informational Submittals: Written and graphic information and physical samples that do not require Engineer's approval. Submittals may be rejected for not complying with requirements. Informational submittals are those submittals indicated in individual Specification Sections as "informational submittals."

1.4 SUBMITTAL SCHEDULE

A. Submittal Schedule: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates. Include additional time

SUBMITTAL PROCEDURES 01 33 00 - 2

required for making corrections or revisions to submittals noted by Engineer and additional time for handling and reviewing submittals required by those corrections.

1. Coordinate submittal schedule with list of subcontracts, the schedule of values, and Contractor's construction schedule.

2. Initial Submittal: Submit concurrently with startup construction schedule. Include submittals required during the first 60 days of construction. List those submittals required to maintain orderly progress of the Work and those required early because of long lead time for manufacture or fabrication.

3. Final Submittal: Submit concurrently with the first complete submittal of Contractor's construction schedule.

a. Submit revised submittal schedule to reflect changes in current status and timing for submittals.

4. Format: Arrange the following information in a tabular format:

a. Scheduled date for first submittal.

b. Specification Section number and title.

c. Submittal category: Action; informational.

d. Name of subcontractor.

e. Description of the Work covered.

f. Scheduled date for Engineer’s final release or approval.

g. Scheduled dates for purchasing.

h. Scheduled date of fabrication.

i. Scheduled dates for installation.

j. Activity or event number.

1.5 SUBMITTAL FORMATS

A. Submittal Information: Include the following information in each submittal:

1. Project name.

2. Date.

3. Name of Engineer.

4. Name of Contractor.

5. Name of firm or entity that prepared submittal.

6. Names of subcontractor, manufacturer, and supplier.

7. Unique submittal number, including revision identifier. Include Specification

Section number with sequential alphanumeric identifier; and alphanumeric suffix for resubmittals.

8. Category and type of submittal.

9. Submittal purpose and description.

10. Number and title of Specification Section, with paragraph number and generic name for each of multiple items.

11. Drawing number and detail references, as appropriate.

12. Indication of full or partial submittal.

13. Location(s) where product is to be installed, as appropriate.

SUBMITTAL PROCEDURES 01 33 00 - 3

14. Other necessary identification.

15. Remarks.

16. Signature of transmitter.

B. Identify options requiring selection by Engineer.

C. Deviations and Additional Information: On each submittal, clearly indicate deviations from requirements in the Contract Documents, including minor variations and limitations;

include relevant additional information and revisions, other than those requested by Engineer on previous submittals. Indicate by highlighting on each submittal or noting on attached separate sheet.

D. PDF Submittals: Prepare submittals as PDF package, incorporating complete information into each PDF file. Name PDF file with submittal number.

1.6 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.

3. Coordinate transmittal of submittals for related parts of the Work specified in different Sections so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Engineer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

B. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Engineer's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 7 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Engineer will advise Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Resubmittal Review: Allow 7 days for review of each resubmittal.

C. Resubmittals: Engineer will review each of Contractor’s submittals the initial time and, should resubmittal be required, one additional time to verify that reasons for resubmittal have been addressed by Contractor and corrections made. Resubmittal changes/revisions/corrections shall be circled. Engineer will review only circled items

SUBMITTAL PROCEDURES 01 33 00 - 4

and will not be responsible for non-circled changes/revisions/corrections and additions.

Should additional resubmittals be required, Contractor shall reimburse Owner for all costs incurred, including the cost of Engineer’s services made necessary to review such additional resubmittals. Owner will in turn reimburse Engineer.

1. Make resubmittals in same form and number of copies as initial submittal.

a. Note date and content of previous submittal.

b. Note date and content of revision in label or title block and clearly indicate extent of revision.

c. Resubmit submittals until they are marked with approval notation from

Engineer's action stamp.

D. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

E. Use for Construction: Retain complete copies of submittals on Project site. Use only final action submittals that are marked with approval notation from Engineer's action stamp.

1.7 SUBMITTAL REQUIREMENTS

A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard published data are unsuitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's catalog cuts.

b. Manufacturer's product specifications.

c. Standard color charts.

d. Statement of compliance with specified referenced standards.

e. Testing by recognized testing agency.

f. Application of testing agency labels and seals.

g. Notation of coordination requirements.

h. Availability and delivery time information.

4. Submit Product Data before Shop Drawings, and before or concurrent with Samples.

B. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

SUBMITTAL PROCEDURES 01 33 00 - 5

1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:

a. Identification of products.

b. Schedules.

c. Compliance with specified standards.

d. Notation of coordination requirements.

e. Notation of dimensions established by field measurement.

f. Relationship and attachment to adjoining construction clearly indicated.

g. Seal and signature of professional engineer if specified.

C. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other materials.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

2. Identification: Permanently attach label on unexposed side of Samples that includes the following:

a. Project name and submittal number.

b. Generic description of Sample.

c. Product name and name of manufacturer.

d. Sample source.

e. Number and title of applicable Specification Section.

f. Specification paragraph number and generic name of each item.

3. Email Transmittal: Provide PDF transmittal. Include digital image file illustrating Sample characteristics, and identification information for record.

4. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.

a. Samples that may be incorporated into the Work are indicated in individual Specification Sections. Such Samples must be in an undamaged condition at time of use.

b. Samples not incorporated into the Work, or otherwise designated as Owner's property, are the property of Contractor.

D. Product Schedule: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location.

Include the following information in tabular form:

1. Type of product. Include unique identifier for each product indicated in the Contract Documents or assigned by Contractor if none is indicated.

2. Manufacturer and product name, and model number if applicable.

3. Number and name of room or space.

SUBMITTAL PROCEDURES 01 33 00 - 6

4. Location within room or space.

1.8 REQUESTS FOR INFORMATION

A. Engineer reserves the right to reject, unprocessed, any Request for Information (RFI) that the Engineer, at its sole discretion, deems frivolous.

B. Engineer reserves the right to reject, unprocessed, any RFI that the Engineer, at its sole discretion, deems already answered in the Contract Documents.

C. RFI process shall not be used for requesting substitutions. Procedures for substitutions are clearly specified elsewhere in the contract documents.

1.9 CONTRACTOR'S REVIEW

A. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Engineer.

B. Project Closeout and Maintenance Material Submittals: See Requirements in Division 01 Section “Closeout Procedures.”

C. Contractor's Approval: Indicate Contractor's approval for each submittal with a uniform approval stamp. Include name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

1. Engineer will not review submittals received from Contractor that do not have Contractor's review and approval.

1.10 ENGINEER'S ACTION

A. General: Engineer will not review submittals that do not bear Contractor's approval stamp and will return them without action.

B. Action Submittals: Engineer or its subconsultant will review each submittal, make marks to indicate corrections or revisions required, and return it.

1. PDF Submittals: Engineer will indicate, via markup on each submittal, the appropriate action.

C. Informational Submittals: Engineer will review each submittal and will not return it, or will return it if it does not comply with requirements. Engineer will forward each submittal to appropriate party.

SUBMITTAL PROCEDURES 01 33 00 - 7

D. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from Engineer.

E. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be returned for resubmittal without review.

F. Engineer will discard submittals received from sources other than Contractor.

G. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 01 33 00

©Copyright 2025. All rights reserved. No part of this document may be reproduced in any form

QUALITY CONTROL 01 40 00 - 1

SECTION 01 40 00 - QUALITY CONTROL

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 01 Specification Sections apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements for quality control services.

B. Testing and inspection services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.

1. Specific quality-assurance and quality-control requirements for individual work results are specified in their respective Specification Sections. Requirements in individual Sections may also cover production of standard products.

2. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and quality-control procedures that facilitate compliance with the Contract Document requirements.

3. Requirements for Contractor to provide quality-assurance and quality-control services required by Engineer, Owner, or authorities having jurisdiction are not limited by provisions of this Section.

4. Specific test and inspection requirements are not specified in this Section.

1.3 DEFINITIONS

A. Experienced: When used with an entity or individual, "experienced" unless otherwise further described means having successfully completed a minimum of five previous projects similar in nature, size, and extent to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.

B. Field Quality-Control Tests: Tests and inspections that are performed on-site for installation of the Work and for completed Work.

C. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, assembly, and similar operations.

QUALITY CONTROL 01 40 00 - 2

1. Use of trade-specific terminology in referring to a trade or entity does not require that certain…