Slick Rock Substation Construction
Solicitation number
26-283
Issued by
Washington County, Utah

About this file

This is an Invitation for Bid (IFB) document for the City of St. George, Utah, for the construction of the Slick Rock Substation (Reference #26-283). The project encompasses site preparation and construction of concrete foundations, transformer containment pads, a control building, access gates, and a precast perimeter wall, with the contractor responsible for all excavation, grading, material installation, and site restoration in accordance with project drawings and specifications. The bid schedule includes multiple line items: mobilization, site earthwork and grading, structural fill material (700 cubic yards), six concrete foundations of three types (totaling 12 units), 34 concrete piers across three categories, two chain link gates (8' high by 20' wide), one man gate (8' high by 4' wide), 681 linear feet of precast concrete decorative wall, and one control building. The opportunity opened May 12, 2026, at 10:00 AM MDT with a mandatory pre-bid meeting scheduled for May 18, 2026, from 11:00 AM to 12:00 PM MDT. Questions are due by May 29, 2026, at 2:00 PM MDT, and bid submissions close June 5, 2026, at 2:00 PM MDT. Award will be made to the lowest responsible bidder as determined by the City using criteria contained in City ordinances.

Each bid must be accompanied by a 5% bid bond naming the City of St. George as obligee, issued by a surety company licensed in Utah on a form acceptable to the City. One hundred percent payment and performance bonds are required for contract execution. Required bid documents include a completed bid schedule with unit prices and total costs for all line items, a bid bond, and a list of major subcontractors. Optional supporting documents include a certificate of insurance if not already included in vendor registration, E-Verify certification of legal work status if not previously submitted, and any additional information deemed necessary by the bidder. The City of St. George reserves the right to reject any or all proposals or to waive any formality or technicality in any proposal in the interest of the city.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IFB - SLICK ROCK

SUBSTATION

CONSTRUCTION

May 12th 2026, 10:00AM MDT - Jun 5th 2026, 2:00PM MDT

Table of Contents

Contents Page #

Project Details 3

1. REQUESTED INFORMATION 5

1.1. BID SCHEDULE 5

Project Details

Project IFB - SLICK ROCK SUBSTATION CONSTRUCTION

Ref. # 26-283

Type IFB

Description The City of St George is requesting bids for the construction of the Slick Rock Substation.Project involves site preparation and construction of concrete foundations, transformer containment pads, a control building, access gates, and a precast perimeter wall. The contractor is responsible for all excavation, grading, material installation, and site restoration in accordance with project drawings and specifications.

Every BID shall be accompanied by a bid bond in the amount of 5% of the BID, naming the City of St. George as obligee, this bid bond must be issued by a surety company licensed to do business in the State of Utah and be on a bond form acceptable to the City of St. George.

100% payment and performance bonds will be required on this project.

The City of St. George reserves the right to reject any or all PROPOSALS or to waive any formality or technicality in any PROPOSAL in the interest of the city.

Open Date May 12th 2026, 10:00AM MDT

Questions Due Date May 29th 2026, 2:00PM MDT

Close Date Jun 5th 2026, 2:00PM MDT

Project Owner Braden Williams

Basis of award Award will be made to the lowest responsible BIDDER as determined by the City using the criteria contained in City ordinances governing the award of contracts.

Events

Event Name Duration Description

Open Date May 12th 2026, 10:00AM MDT

Posting date for the Opportunity

MANDATORY PRE-BID

MEETING - 26-283 SLICK

ROCK SUBSTATION

CONSTRUCTION

May 18th 2026, 11:00AM MDT -

May 18th 2026, 12:00PM MDT

MANDATORY PRE-BID

MEETING - 26-260 SLICK

ROCK SUBSTATION

CONSTRUCTION

Questions Due Date May 29th 2026, 2:00PM MDT

Deadline to submit Questions

Close Date Jun 5th 2026, 2:00PM MDT

Deadline for Submissions

1. REQUESTED INFORMATION

1.1 BID SCHEDULE

1.1.1 26-283 BID SCHEDULE [Required]

BASE BID

ITEM

DESCRIPTION

Quantity Required

Unit of Measure Unit Price Total Cost

Mobilization 1 L.S.

Site Earthwork , Over Excavation, and Grading

1 L.S.

Furnish and Install Structural Fill Material

700 C.Y.

Furnish and Install Concrete Foundation F1

6 Each

Furnish and Install Concrete Foundation F2

4 Each

Furnish and Install Concrete Foundation F3

2 Each

Furnish and Install Concrete Pier P1

6 Each

Furnish and Install Concrete Pier P2

4 Each

Furnish and Install Concrete Pier P3

24 Each

Furnish and Install 8’ High 20’ Wide Chain Link Gate

2 L.S.

Furnish and Install 2 8’ High 4’ Wide Man Gate

1 L.S.

Furnish and Install 8’ High Precast Concrete Decorative Wall

681 L.F.

Furnish and Install Control Building

1 L.S.

1.1.2 BID BOND [Required] [PDF]

(Vendor file uploads)

1.1.3 LIST OF MAJOR SUBCONTRACTORS [Required] [PDF]

1.1.4 CERTIFICATE OF INSURANCE (if not included in vendor registration) [Optional] [P

DF]

(Vendor file uploads)

1.1.5 E-VERIFY - CERTIFICATION OF LEGAL WORK STATUS (if not included in vendor registration) [Optional] [PDF]

(Vendor file uploads)

1.1.6 ADDITIONAL INFORMATION (if needed) [Optional] [PDF]

IFB - SLICK ROCK SUBSTATION CONSTRUCTION
Table of Contents
Project Details
Events
1. REQUESTED INFORMATION
1.1 BID SCHEDULE
1.1.2 BID BOND[Required][PDF]
1.1.3 LIST OF MAJOR SUBCONTRACTORS[Required][PDF]
1.1.4 CERTIFICATE OF INSURANCE (if not included in vendor registration)[Optional][PDF]
1.1.5 E-VERIFY - CERTIFICATION OF LEGAL WORK STATUS (if not included in vendor registration)[Optional][PDF]
1.1.6 ADDITIONAL INFORMATION (if needed)[Optional][PDF]

File details come from the government source that posted it. Updated .