Bid tab~2.xlsx

XLSX spreadsheet 19 KB Posted

Attached to
Pilot Project - Staff Training and Support
Solicitation number
S-10000-00007775
Issued by
Marion County, Oregon

About this file

This is a bid tabulation sheet for Request for Bid No. S-10900-00007777 issued by the state of Oregon on January 10, 2024, for pavement maintenance and repair services across four airports in PMP Region 3 Northern Airports. The project encompasses work at Bend Municipal Airport, Madras Municipal Airport, Prineville Airport, and Sunriver Airport, with services including mobilization, crack sealing, joint repair, pavement marking, and AC patching across the four sites. Estimated quantities vary by location and service type, ranging from 237 to 26,952 linear feet for crack sealing and joint repair work. Bids were due on January 10, 2024, at 2:00 p.m., with five contractors submitting proposals: KNL Industries Inc, Hybrid Construction LLC, C.R. Contracting, Carter & Company, Inc., and O'Malley Brothers Corporation.

The bid tabulation presents unit prices and total prices for each line item across all five bidders. KNL Industries Inc submitted the lowest grand total bid at $254,848.00, followed by Hybrid Construction LLC at $268,809.03. The remaining three bidders submitted significantly higher bids, with C.R. Contracting at $484,410.10, Carter & Company, Inc. at $506,516.80, and O'Malley Brothers Corporation at $634,405.55. Unit pricing varies considerably among bidders, particularly for specialized items such as joint repair and AC patching, where prices range from as low as $17.29 per linear foot to as high as $150.00 per linear foot across different contractors. The bid tab does not indicate specific set-asides, contract term details, or funding sources within the document itself.

View the file

Other files

File Type Posted
5748_7775 Intent to Award Notice.docx DOCX document
5748_7775 SSD Final.docx DOCX document
5748_7775 SOW.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Date Issued:1/10/24
RFB No.:S-10900-00007777BIDDER
NAME:KNL Industries IncHybrid Construction LLCC.R. ContractingCarter & Company, Inc.O'Malley Brothers Corporation
Bids due:1/10/2024 2:00 pm
Description:PMP Region 3 - Northern Airports
Bid Item #DescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

SCHEDULE A - BEND MUNICIPAL AIRPORT
1Mobilization1LS$ 10,000.00$ 10,000.00$ 7,995.00$ 7,995.00$ 25,685.00$ 25,685.00$ 20,000.00$ 20,000.00$ 19,500.00$ 19,500.00
2Crack Sealing19,742LF$ 1.52$ 30,007.84$ 1.61$ 31,784.62$ 1.95$ 38,496.90$ 2.50$ 49,355.00$ 4.95$ 97,722.90
3Joint Repair902LF$ 22.18$ 20,006.36$ 28.50$ 25,707.00$ 54.50$ 49,159.00$ 49.00$ 44,198.00$ 42.50$ 38,335.00
4Pavement Marking1,109SF$ 7.66$ 8,494.94$ 3.47$ 3,848.23$ 4.95$ 5,489.55$ 5.25$ 5,822.25$ 8.00$ 8,872.00
TOTAL$ 68,509.14$ 69,334.85$ 118,830.45$ 119,375.25$ 164,429.90
SCHEDULE B - MADRAS MUNICIPAL AIRPORT
1Mobilization1LS$ 10,000.00$ 10,000.00$ 7,995.00$ 7,995.00$ 23,665.00$ 23,665.00$ 13,500.00$ 13,500.00$ 17,500.00$ 17,500.00
2Crack Sealing5,156LF$ 1.45$ 7,476.20$ 2.00$ 10,312.00$ 3.50$ 18,046.00$ 3.50$ 18,046.00$ 8.00$ 41,248.00
3Joint Repair267LF$ 56.18$ 15,000.06$ 38.50$ 10,279.50$ 150.00$ 40,050.00$ 80.10$ 21,386.70$ 47.50$ 12,682.50
4Pavement Marking432SF$ 15.16$ 6,549.12$ 6.00$ 2,592.00$ 8.00$ 3,456.00$ 5.25$ 2,268.00$ 12.00$ 5,184.00
TOTAL$ 39,025.38$ 31,178.50$ 85,217.00$ 55,200.70$ 76,614.50
SCHEDULE C - PRINEVILLE AIRPORT
1Mobilization1LS$ 10,000.00$ 10,000.00$ 7,995.00$ 7,995.00$ 29,884.00$ 29,884.00$ 20,000.00$ 20,000.00$ 17,500.00$ 17,500.00
2Crack Sealing26,952LF$ 1.30$ 35,037.60$ 1.65$ 44,470.80$ 2.10$ 56,599.20$ 2.50$ 67,380.00$ 4.95$ 133,412.40
3Joint Repair1,736LF$ 17.29$ 30,015.44$ 20.00$ 34,720.00$ 32.75$ 56,854.00$ 45.00$ 78,120.00$ 42.50$ 73,780.00
4AC Patching555SF$ 13.52$ 7,503.60$ 34.00$ 18,870.00$ 45.00$ 24,975.00$ 65.00$ 36,075.00$ 39.50$ 21,922.50
5Pavement Marking3,453SF$ 5.43$ 18,749.79$ 3.28$ 11,325.84$ 3.15$ 10,876.95$ 5.25$ 18,128.25$ 8.00$ 27,624.00
TOTAL$ 101,306.43$ 117,381.64$ 179,189.15$ 219,703.25$ 274,238.90
SCHEDULE D - SUNRIVER AIRPORT
1Mobilization1LS$ 10,000.00$ 10,000.00$ 7,995.00$ 7,995.00$ 22,500.00$ 22,500.00$ 15,000.00$ 15,000.00$ 20,500.00$ 20,500.00
2Crack Sealing3,424LF$ 1.46$ 4,999.04$ 2.46$ 8,423.04$ 3.75$ 12,840.00$ 4.90$ 16,777.60$ 8.00$ 27,392.00
3Joint Repair1,393LF$ 18.67$ 26,007.31$ 20.00$ 27,860.00$ 34.50$ 48,058.50$ 45.00$ 62,685.00$ 42.50$ 59,202.50
4Pavement Marking237SF$ 21.10$ 5,000.70$ 28.00$ 6,636.00$ 75.00$ 17,775.00$ 75.00$ 17,775.00$ 50.75$ 12,027.75
TOTAL$ 46,007.05$ 50,914.04$ 101,173.50$ 112,237.60$ 119,122.25
GRAND TOTAL$ 254,848.00$ 268,809.03$ 484,410.10$ 506,516.80$ 634,405.55

Sheet2

Sheet3