Bid tab.xlsx

XLSX spreadsheet 17 KB Posted

Attached to
ITB - Toledo State Airport Apron Reconstruction Project
Solicitation number
S-10900-00003385
Issued by
Klamath County, Oregon

About this file

This document is a bid tab spreadsheet for the Toledo State Airport Apron Reconstruction Project, a state contract opportunity in Oregon involving Lincoln County. The project includes apron and north taxiway reconstruction, as well as additive alternates for hangar taxilanes, asphalt concrete pavement access road, and gravel access road. The bid tab shows preliminary bid results for two bidders, Kodiak Pacific Construction Co. and Laskey-Clifton Corp., across various bid items including mobilization, erosion control, excavation, base course, asphalt paving, and pavement markings. The total base bid amounts range from $341,117 to $429,775.

The pricing in the bid tab includes unit prices and quantities for the various bid items. The contract appears to be a competitive sealed bid with the low bidder likely to be awarded the contract. No information is provided on set-asides, incumbents, funding sources, or contract term and renewal options.

View the file

Other files

File Type Posted
Attachment C_Bid Pricing Form.xlsx XLSX spreadsheet
Notice of Intent to Award-ORPIN.doc~1.docx DOCX document
00003385_Add 1.docx DOCX document
Attachment A_Special Provisions.pdf PDF
Attachment D_Geotechnical Report.pdf PDF
35330_00003385_ITB.docx DOCX document
Attachment B_Plans~1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

S-10900-00003385 Toledo State Airport Apron Reconstruction Project
PRELIMINARY BID RESULTSKodiak Pacific Construction Co.Laskey-Clifton Corp.
Bid Item #DescriptionEst
QTYUNITUNIT
PRICETOTAL
PRICEUNIT
PRICETOTAL

PRICE

SCHEDULE A – BASE BID – APRON AND NORTH TAXIWAY RECONSTRUCTION
1Mobilization1LS$ 64,000.00$ 64,000.00$ 82,676.00$ 82,676.00
2Erosion Control1LS$ 7,500.00$ 7,500.00$ 9,983.00$ 9,983.00
3Contractor’s Staging Area and Restoration1LS$ 7,500.00$ 7,500.00$ 2,517.00$ 2,517.00
4Access Road Restoration (If Schedule C/D Not Constructed)1LS$ 3,800.00$ 3,800.00$ 6,000.00$ 6,000.00
5Construction Survey Work1LS$ 9,000.00$ 9,000.00$ 39,540.00$ 39,540.00
6Removal of Surfacings700SY$ 7.00$ 4,900.00$ 61.67$ 43,169.00
7General Excavation, Stripping350CY$ 62.00$ 21,700.00$ 49.25$ 17,237.50
8General Excavation250CY$ 51.00$ 12,750.00$ 66.50$ 16,625.00
9Embankment in Place300CY$ 98.00$ 29,400.00$ 46.50$ 13,950.00
10General Excavation, Unsuitable100CY$ 62.00$ 6,200.00$ 49.50$ 4,950.00
1118-Inch Subgrade Stabilization75SY$ 77.00$ 5,775.00$ 51.00$ 3,825.00
126-Inch C900 Pipe100FT$ 74.00$ 7,400.00$ 105.50$ 10,550.00
13Geotextile Fabric500SY$ 1.30$ 650.00$ 2.46$ 1,230.00
143/4-Inch Aggregate Base390CY$ 105.00$ 40,950.00$ 130.40$ 50,856.00
15Level 3, 1/2-Inch Asphalt Concrete Pavement585TON$ 122.00$ 71,370.00$ 146.50$ 85,702.50
16Tie-Down Anchors27EA$ 1,400.00$ 37,800.00$ 714.00$ 19,278.00
17Permanent Seeding, Mix No. 2840SY$ 3.30$ 2,772.00$ 4.00$ 3,360.00
18Pavement Marking (First Application)850SF$ 4.50$ 3,825.00$ 10.78$ 9,163.00
19Pavement Marking (Final Application)850SF$ 4.50$ 3,825.00$ 10.78$ 9,163.00
TOTAL SCHEDULE A$ 341,117.00$ 429,775.00
SCHEDULE B – ADDITIVE ALTERNATE – HANGAR TAXILANES
20General Excavation, Stripping50CY62.00$ 3,100.00$ 65.25$ 3,262.50
214-Inch C900 Pipe60FT87.00$ 5,220.00$ 150.50$ 9,030.00
22Embankment in Place60CY98.00$ 5,880.00$ 58.00$ 3,480.00
233/4-Inch Aggregate Base20CY105.00$ 2,100.00$ 225.00$ 4,500.00
24Level 3, 1/2-Inch Asphalt Concrete Pavement25TON122.00$ 3,050.00$ 148.00$ 3,700.00
TOTAL SCHEDULE B$ 19,350.00$ 23,972.50
SCHEDULE C – ADDITIVE ALTERNATE – ACP ACCESS ROAD
25Geotextile Fabric300SY1.30$ 390.00$ 2.46$ 738.00
26General Excavation25CY51.00$ 1,275.00$ 148.00$ 3,700.00
27Embankment in Place25CY98.00$ 2,450.00$ 94.00$ 2,350.00
283/4-Inch Aggregate Base30CY105.00$ 3,150.00$ 132.00$ 3,960.00
29Level 3, ½-Inch Asphalt Concrete Pavement35TON122.00$ 4,270.00$ 148.00$ 5,180.00
TOTAL SCHEDULE C$ 11,535.00$ 15,928.00
SCHEDULE D – ADDITIVE ALTERNATE – GRAVEL ACCESS ROAD (if Schedule C NOT funded)
30Geotextile Fabric300SY1.3$ 390.00$ 2.46$ 738.00
31General Excavation25CY51$ 1,275.00$ 148.00$ 3,700.00
32Embankment in Place25CY98$ 2,450.00$ 94.00$ 2,350.00
333/4-Inch Aggregate Base30CY105$ 3,150.00$ 132.00$ 3,960.00
343/4-Inch Aggregate Base (Gravel Surfacing)30CY105$ 3,150.00$ 132.00$ 3,960.00
TOTAL SCHEDULE D$ 10,415.00$ 14,708.00
A + B + C$ 372,002.00$ 469,675.50
A + B + D$ 370,882.00$ 468,455.50

File details come from the government source that posted it. Updated .