This is a bid sheet for Group 4 of a construction project involving traffic signal installation and related infrastructure work across five districts (Districts 8, 9, 10, 11, and 12). The project encompasses furnishing and installing conduit, electrical services, cabinets, junction boxes, piezoelectric sensors, wooden poles, loop wire, and ground wire, along with associated civil work including trench excavation, sidewalk replacement, and lane and shoulder closures. The scope varies by district, with Districts 8 and 9 requiring the most extensive work (including 4,000 linear feet of loop wire installation each) and District 10 requiring the least (1,000 linear feet of loop wire). Common items across all districts include furnishing 2-inch bore and jack pipe (50 linear feet each), installing electrical service (one per district), and conducting loop tests. The bid sheet provides detailed item descriptions, units of measure, and quantities for each district but does not include unit prices, extended prices, response dates, bidders' meetings, or contract award information within the document.

The bid sheet structure indicates that contractors are expected to complete unit pricing for each of the 23 line items across the five districts, with separate totals calculated for each district and a combined Group 4 total. The document does not contain information regarding pricing terms, set-asides, incumbent contractors, funding sources, or contract duration and renewal options. The reference to "Bid Count Station Maintenance RFB 04-28-23.pdf" at the document's conclusion suggests this bid sheet is part of a larger Request for Bid package issued on April 28, 2023, but detailed procurement terms and conditions are not included in this excerpt.

View the file

Other files

File Type Posted
How to Submit an Online Response - March 2023.pdf PDF
Final_RFB_605_2300000780_1_SO_FORM.PDF PDF
Annual Affidavit for Bidders, Offerors and Contractors - Jan 2023.docx DOCX document
District Map.pdf PDF
Bid Sheets Group 1.pdf PDF
Bid Sheet Group 2.pdf PDF
Bid Sheets Group 3.pdf PDF
FHWA-1273.pdf PDF
Drawings.pdf PDF
Final_RFB_605_2300000780_2_SO_FORM.PDF PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Group 4: District 8

Item Description Unit D08 Quantity

D08 Unit Price

D08 Extended

Price 1 Furnish, Bore and Jack Pipe – 2 Inch LIN FT 50

2 Furnish and Install Conduit 1¼ Inch LIN FT 250

3 Furnish and Install Conduit 2 Inch LIN FT 125

4 Furnish and Install Electrical Service EACH 1

5 Furnish and Install Galvanized Steel Cabinet EACH 1

6 Install Pad Mount Cabinet EACH 1

7 Install Pole Mount Cabinet EACH 1

8 Furnish and Install Junction Box 10x8x4 EACH 1

9 Furnish and Install Junction Box Type A EACH 7

10 Furnish and Install Junction Box Type B EACH 7

11 Saw Slot and Fill LIN FT 900

12 Furnish, Install and Remove Lane Closure EACH 10

13 Furnish, Install and Remove Shoulder Closure EACH 5

14 Furnish and Install Piezoelectric Sensor EACH 10

15 Install Piezoelectric Sensor EACH 5

16 Furnish and Install 35’ Wooden Pole EACH 1

17 Excavate Trench and Backfill LIN FT 325

18 Furnish and Install Cable No. 14/1 Pair LIN FT 250

19 Furnish and Install Loop Wire LIN FT 4000

20 Furnish and Install Ground Wire LIN FT 25

21 Furnish and Install Wood Post EACH 3

22 Remove and Replace Sidewalk SQYD 1

23 Loop Test EACH 1

Group 4: District 8 Total

Group 4: District 9

Item Description Unit D09 Quantity

D09 Unit Price

D09 Extended

Price 1 Furnish, Bore and Jack Pipe – 2 Inch LIN FT 50

2 Furnish and Install Conduit 1¼ Inch LIN FT 250

3 Furnish and Install Conduit 2 Inch LIN FT 125

4 Furnish and Install Electrical Service EACH 1

5 Furnish and Install Galvanized Steel Cabinet EACH 1

6 Install Pad Mount Cabinet EACH 1

7 Install Pole Mount Cabinet EACH 1

8 Furnish and Install Junction Box 10x8x4 EACH 1

9 Furnish and Install Junction Box Type A EACH 7

10 Furnish and Install Junction Box Type B EACH 7

11 Saw Slot and Fill LIN FT 900

12 Furnish, Install and Remove Lane Closure EACH 10

13 Furnish, Install and Remove Shoulder Closure EACH 5

14 Furnish and Install Piezoelectric Sensor EACH 10

15 Install Piezoelectric Sensor EACH 5

16 Furnish and Install 35’ Wooden Pole EACH 1

17 Excavate Trench and Backfill LIN FT 325

18 Furnish and Install Cable No. 14/1 Pair LIN FT 250

19 Furnish and Install Loop Wire LIN FT 4000

20 Furnish and Install Ground Wire LIN FT 25

21 Furnish and Install Wood Post EACH 3

22 Remove and Replace Sidewalk SQYD 1

Group 4: District 9 Total

Group 4: District 10

Item Description Unit D10 Quantity

D10 Unit Price

D10 Extended

Price 1 Furnish, Bore and Jack Pipe – 2 Inch LIN FT 50

2 Furnish and Install Conduit 1¼ Inch LIN FT 50

3 Furnish and Install Conduit 2 Inch LIN FT 25

4 Furnish and Install Electrical Service EACH 1

5 Furnish and Install Galvanized Steel Cabinet EACH 1

6 Install Pad Mount Cabinet EACH 1

7 Install Pole Mount Cabinet EACH 1

8 Furnish and Install Junction Box 10x8x4 EACH 1

9 Furnish and Install Junction Box Type A EACH 2

10 Furnish and Install Junction Box Type B EACH 2

11 Saw Slot and Fill LIN FT 200

12 Furnish, Install and Remove Lane Closure EACH 2

13 Furnish, Install and Remove Shoulder Closure EACH 1

14 Furnish and Install Piezoelectric Sensor EACH 5

15 Install Piezoelectric Sensor EACH 5

16 Furnish and Install 35’ Wooden Pole EACH 1

17 Excavate Trench and Backfill LIN FT 75

18 Furnish and Install Cable No. 14/1 Pair LIN FT 50

19 Furnish and Install Loop Wire LIN FT 1000

20 Furnish and Install Ground Wire LIN FT 10

21 Furnish and Install Wood Post EACH 3

22 Remove and Replace Sidewalk SQYD 1

Group 4: District 10 Total

Group 4: District 11

Item Description Unit D11 Quantity

D11 Unit Price

D11 Extended

Price 1 Furnish, Bore and Jack Pipe – 2 Inch LIN FT 50

2 Furnish and Install Conduit 1¼ Inch LIN FT 150

3 Furnish and Install Conduit 2 Inch LIN FT 75

4 Furnish and Install Electrical Service EACH 1

5 Furnish and Install Galvanized Steel Cabinet EACH 1

6 Install Pad Mount Cabinet EACH 1

7 Install Pole Mount Cabinet EACH 1

8 Furnish and Install Junction Box 10x8x4 EACH 1

9 Furnish and Install Junction Box Type A EACH 5

10 Furnish and Install Junction Box Type B EACH 5

11 Saw Slot and Fill LIN FT 525

12 Furnish, Install and Remove Lane Closure EACH 6

13 Furnish, Install and Remove Shoulder Closure EACH 3

14 Furnish and Install Piezoelectric Sensor EACH 5

15 Install Piezoelectric Sensor EACH 5

16 Furnish and Install 35’ Wooden Pole EACH 1

17 Excavate Trench and Backfill LIN FT 225

18 Furnish and Install Cable No. 14/1 Pair LIN FT 150

19 Furnish and Install Loop Wire LIN FT 3000

20 Furnish and Install Ground Wire LIN FT 20

21 Furnish and Install Wood Post EACH 3

22 Remove and Replace Sidewalk SQYD 1

Group 4: District 11 Total

Group 4: District 12

Item Description Unit D12 Quantity

D12 Unit Price

D12 Extended

Price 1 Furnish, Bore and Jack Pipe – 2 Inch LIN FT 50

2 Furnish and Install Conduit 1¼ Inch LIN FT 100

3 Furnish and Install Conduit 2 Inch LIN FT 50

4 Furnish and Install Electrical Service EACH 1

5 Furnish and Install Galvanized Steel Cabinet EACH 1

6 Install Pad Mount Cabinet EACH 1

7 Install Pole Mount Cabinet EACH 1

8 Furnish and Install Junction Box 10x8x4 EACH 1

9 Furnish and Install Junction Box Type A EACH 3

10 Furnish and Install Junction Box Type B EACH 3

11 Saw Slot and Fill LIN FT 350

12 Furnish, Install and Remove Lane Closure EACH 4

13 Furnish, Install and Remove Shoulder Closure EACH 2

14 Furnish and Install Piezoelectric Sensor EACH 5

15 Install Piezoelectric Sensor EACH 5

16 Furnish and Install 35’ Wooden Pole EACH 1

17 Excavate Trench and Backfill LIN FT 150

18 Furnish and Install Cable No. 14/1 Pair LIN FT 100

19 Furnish and Install Loop Wire LIN FT 2000

20 Furnish and Install Ground Wire LIN FT 10

21 Furnish and Install Wood Post EACH 3

22 Remove and Replace Sidewalk SQYD 1

Group 4: District 12 Total

Group 4: Districts 8, 9, 10, 11, and 12

District 8 Total

District 9 Total

District 10 Total

District 11 Total

District 12 Total

Group 4 Total Bid