This document contains a pre-solicitation notice and related project files for the stabilization of Building 129 for the National Historic Archives at the Dayton VA Medical Center.
The Department of Veterans Affairs Network Contracting Office 10 is seeking proposals for the complete construction services to stabilize Building 129, including all necessary tools, equipment and personnel. The scope of work involves performing all work specified in the design drawings, specifications and attachments. The contractor must complete all work within 270 calendar days of receiving the notice to proceed.
The solicitation documents will be posted on SAM.gov on or around June 22, 2020, with proposals due approximately 30 days later. This opportunity is set aside only for service-disabled veteran-owned small businesses. The assigned NAICS code is 236220 with a small business size standard of $36.5 million. At least 15% of the construction work must be performed by the SDVOSB contractor or subcontractor. Bid, payment and performance bonds will be required.
The related project files include specification revisions and drawing revisions involving roofing materials, demolition notes, and other details.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S07. Bid Abstract - Stabilize Building 129 for National Historic Archives.pdf | ||
| 36C25020B0054 0004.docx | DOCX document | |
| 36C25020B0054 0003.docx | DOCX document | |
| Stabilize Bldg. 129 Questions and Answers.pdf | ||
| Stabilize Bldg. 129 Sign-in Sheet.pdf | ||
| 36C25020B0054 0002.docx | DOCX document | |
| Updated Project Manual.pdf | ||
| 36C25020B0054 0001.docx | DOCX document | |
| Updated Statement of Work (SOW).pdf | ||
| Updated Bid Drawings.pdf | ||
| 36C25020B0054_1.docx | DOCX document | |
| Bid Set Addendum 1 Drawings.pdf | ||
| Bid Set Specifications.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Guidon Design Inc.
905 N. Capitol Avenue, Suite 100 Indianapolis, IN 46204
February 8, 2019
Re: STABILIZE BLDG 129 FOR NHA (PHASE 2) Project No. 552-18-202
ADDENDUM NO. 1
GENERAL: The following changes, additions or deletions for the above project shall be made to the Contract Documents; all other Conditions shall remain the same. Note: the additions, deletions or changes listed in this Addendum may affect more than the specific instance(s) mentioned. Coordination may be necessary to fully revise cases of duplicate information. The
Addendum supersedes current conditions shown. Acknowledge receipt of this Addendum by inserting its number and date in the 'Bid Form'. This addendum forms a part of the Contract
Documents and modifies them as follows:
SPECIFICATIONS
01 00 00: STATEMENT OF BID ITEMS, REMOVE BID ITEM 4 IN ITS ENTIRITY. REVISE BID
ITEM 3 TO READ:
‘BID ITEM 3, (DEDUCT ALTERNATE NO. 2): Contractor shall perform all work as described in BID ITEM 2 (BASE BID and DEDUCT ALTERNATE NO. 1) except deduct all work associated with the purchase and installation of
Granite Stone steps. Provide cast in place concrete stairs and landings. Contractor shall have 260 days from Notice to Proceed to complete Work associated with BID ITEM 3, (DEDUCT ALTERNATE NO. 2).’
07 31 13: REVISE 2.1 PRODUCTS – GENERAL; A. BASIS OF DESIGN: TO READ
‘CERTAINTEED HIGHLAND SLATE, COLOR: SMOKY QUARTZ’
07 31 26: REMOVE SPECIFIACTION SECTION 073126 SYNTHETIC SLATE SHINGLES IN ITS
ENTIRITY. SEE REVISED TABLE OF CONTENTS
09 06 00: REPLACE 2.5 DIVISION 07 – THERMAL AND MOISTURE PROTECTION; A.
SECTION 07 31 26, SYNTHETIC SLATE SHINGLES WITH:
A. SECTION 07 31 13, ASPHALT SHINGLES
Size Shape Manufacturer Mfg. Color Name/No.
18 x 36 Uniform size Certainteed Highland Slate/ Smokey
Quartz
Guidon Design Page. 2
Printed: 2/8/2019
DRAWINGS
AD101, AD102, AD103, AD104:
REVISED DEMOLITION PLAN NOTE 1 TO READ: ‘REMOVE AND DISPOSE OF EXISTING
WINDOW SASH, EXTERIOR FRAME AND HARDWARE.’
REVISED DEMOLITION PLAN NOTE 2 TO READ: ‘REMOVE AND DISPOSE OF EXISTING
DOOR LEAF, EXTERIOR FRAME AND HARDWARE.’
REVISED DEMOLITION PLAN NOTE 4 TO READ: ‘RETAIN AND PROTECT EXISTING
METAL FIRE ESCAPE IN PLACE.’ REFERNCE PLANS.
AS121 & AS201:
REVISE ROOF PLAN NOTE 1 TO READ: ‘PROVIDE NEW ASPHALT SHINGLES. BASIS OF
DESIGN: CERTAINTEED, HIGHLAND SLATE, COLOR: SMOKY QUARTZ.’
ATTACHMENTS:
Specifications: 000110, 010000, 073113, 090600
Drawing Sheets: AD101, AD102, AD103, AD104, AS121, AS201