Bid Schedule - Gold Creek Project.pdf

PDF 70 KB Posted

Attached to
PKAA, Gold Creek Project
Solicitation number
DQ1 PKAA 2026000532 1
Issued by
Colorado

About this file

This is a bid schedule document for the Gold Creek Project, a state and local contract opportunity in Colorado administered through the Colorado VSS (Vendor Self Service) bidding platform. The project involves mine closure work across multiple sites with both U.S. Forest Service (USFS) and private ownership. Bidders are required to submit bids exclusively through the Colorado VSS online system, with mail and fax submissions prohibited unless VSS becomes unavailable and alternative methods are specified in the project's Special Conditions. The scope of work includes four main line items: mobilization/demobilization, development of a Project Safety, Health and Environmental Action Plan, installation of mine closures across 15 identified features, and provision of up to 9 cubic yards of additional polyurethane use fill (PUF) material on a non-guaranteed basis. The bid schedule, updated February 24, 2026, requires submission of all pages completed with line items filled in, and the bid must be signed by an authorized representative of the offeror.

The mine closure work encompasses 15 distinct features (labeled GC-01 through GC-15) utilizing two primary closure methods: bat grates with access doors for adits and polyurethane foam application for shafts and select adits. Bidders must provide individual bid amounts for each feature and calculate a total lump sum amount for Item 3.0, which consolidates all mine closure installation costs. The ownership of closure sites is divided between USFS properties and privately owned locations. All pages of the bid schedule must be completed and returned; amendments to any section are not permitted. Pricing is structured on a lump sum basis for mine closures with unit pricing for additional materials, though specific unit prices and total amounts are to be entered by the bidding contractor based on their cost proposals.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submit Bids via Colorado VSS at the following link: http://www.colorado.gov/vss Submitting Bids by mail or fax is not permitted.

If VSS is unavailable, please see project Special Conditions for alternative Bid Submittal method.

Item Description Qty Unit Per Unit Price ($) Total Price ($)

Item 1.0 - Mobilize/Demobilize 1 Job N/A

Item 2.0 - Project Safety, Health and Environmental Action Plan

1 Job N/A

Item 3.0 - Install Mine Closures (See total from page 2)

1 Lump Sum N/A

Item 4.0 - Additional PUF not guaranteed

9 Cubic Yard

Grand Total:

Legal Business Name

Address

City, State Zip

Phone

Email

Signer Printed Name

Title

Date

The Bid shall be signed by a person authorized to bind the Offeror.

Do not amend any part of this bid schedule all pages of this bid schedule must be returned all line items must be completed.

Updated February 24, 2026.

Bid Schedule Gold Creek

DQ1 PKAA 2026*0532

Complete all pages in the spreadsheet as applicable.

Offeror Information

Signature:

Feature ID Feature Type Closure Method Ownership Bid Amount ($)

GC-01 Adit Bat Grate w/access door USFS

GC-02 Adit Bat Grate USFS

GC-03 Shaft Polyurethane Foam USFS

GC-04 Adit CSP Bulkhead Private

GC-05 Adit Bat Grate w/access door Private

GC-06 Shaft Polyurethane Foam Private

GC-07 Shaft Polyurethane Foam

USFS

GC-08 Adit Bat Grate w/access door Private

GC-09 Adit Bat Grate w/access door Private

GC-10 Adit Bat Grate w/access door Private

GC-11 Adit Polyurethane Foam Private

GC-12 Adit Polyurethane Foam

USFS

GC-13 Adit Polyurethane Foam Private

GC-15 Adit Polyurethane Foam

USFS

Bid Schedule Gold Creek

DQ1 PKAA 2026*0532

Item 3.0 - Install Mine Closures:

Total (enter here and on Bid Schedule, Item 3.0):

Do not amend any part of this bid schedule all pages of this bid schedule must be returned all line items must be completed.