Bid Schedule - 25-0317.pdf
PDF 68 KB Posted
- Attached to
- Secured Entrance Bid
- Solicitation number
- RFP-ONE-250000001945-1
- Issued by
- Monroe County, Michigan
About this file
This document is a Milestone Construction Schedule for the Onekama Secure Entry Renovations project by The Christman Company, focusing on Glen Lake facility improvements. The project is scheduled to run from March 17, 2025, to July 14, 2025, spanning 84 total days with a comprehensive phased construction approach. The bidding process will occur from March 17 to April 11, 2025, including bid document publication, bid receipt, and post-bid interviews. The primary construction phase is set for Summer 2025, starting June 9, 2025, and will involve interior renovations including demolition, mechanical and electrical work, metal framing, drywall and painting, storefront and glazing installations, ceiling repairs, technology installations, and flooring work.
The construction schedule details a methodical workflow with specific durations for each task, including 3 days for temporary protection, 1 day for demolition, 2 days for metal framing, 2 days for mechanical and electrical rough-in, and 7 days for drywall and painting. Additional phases include aluminum storefront and glazing, mechanical and electrical fit-out, technology installation, and flooring repairs. The project concludes with a punch list, inspections, owner training, and final project completion on July 14, 2025. The schedule indicates precise task dependencies and sequential work processes, suggesting a carefully planned renovation of the secure entry area with minimal disruption to ongoing operations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Name Duration Start Finish Predecessors Successors
1 Onekama Secure Entry Renovations 84 d Mon 3/17/25 Mon 7/14/25
2 Bidding 20 d Mon 3/17/25 Fri 4/11/25
3 Publish Bid Documents 1 d Mon 3/17/25 Mon 3/17/25 4
4 Bidding 15 d Tue 3/18/25 Mon 4/7/25 3 5FF
5 Reciept of Bids 1 d Mon 4/7/25 Mon 4/7/25 4FF 6FS+2 d
6 Post Bid Interviews/Recommend. for Award 2 d Thu 4/10/25 Fri 4/11/25 5FS+2 d 8FS+10 d
7 Submittal & Material Procurement 20 d Mon 4/28/25 Fri 5/23/25
8 Typical Submittal Process 20 d Mon 4/28/25 Fri 5/23/25 6FS+10 d
9 Construction- Phase 1- Summer 2025 22 d Mon 6/9/25 Wed 7/9/25
10 Start of Construction 1 d Mon 6/9/25 Mon 6/9/25 12SS
11 Interior Renovations 22 d Mon 6/9/25 Wed 7/9/25
12 Temp Protection 3 d Mon 6/9/25 Wed 6/11/25 10SS 13
13 Demolition / M&E Removal 1 d Thu 6/12/25 Thu 6/12/25 12 14
14 Metal framing 2 d Fri 6/13/25 Mon 6/16/25 13 15
15 Mechanical & Electrical Rough-In 2 d Tue 6/17/25 Wed 6/18/25 14 16
16 Drywall & Painting 7 d Thu 6/19/25 Fri 6/27/25 15 18,17
17 Aluminum Storefront / Glazing 4 d Mon 6/30/25 Thu 7/3/25 16
18 Ceiling Repair 2 d Mon 6/30/25 Tue 7/1/25 16 19,20
19 Mechanical / Electrical Fit Out & Fixtures 3 d Wed 7/2/25 Mon 7/7/25 18 21
20 Technology Installation 3 d Wed 7/2/25 Mon 7/7/25 18 22,24
21 Flooring Repair / Installation 2 d Tue 7/8/25 Wed 7/9/25 19 22
22 Punch List 1 d Thu 7/10/25 Thu 7/10/25 20,21 23
23 Inspections 1 d Fri 7/11/25 Fri 7/11/25 22 25
24 Owner Training 1 d Tue 7/8/25 Tue 7/8/25 20 25
25 Project Complete 1 d Mon 7/14/25 Mon 7/14/25 23,24
Onekama Secure Entry Renovations
3/17
Bidding
4/7
Post Bid Interviews/Recommend. for Award
Typical Submittal Process
6/9
Temp Protection
Demolition / M&E Removal
Metal framing
Mechanical & Electrical Rough-In
Drywall & Painting
Aluminum Storefront / Glazing
Ceiling Repair
Mechanical / Electrical Fit Out & Fixtures
Technology Installation
Flooring Repair / Installation
Punch List
Inspections
Owner Training
7/14
1/5 2/2 3/2 3/30 4/27 5/25 6/22 7/20 8/17 9/14 10/12 11/9 12/7 1/4 January Februa March April May June July August Septem Octobe Novem DecembJanuary 2025 2026
The Christman Company Glen Lake Boiler & Steam Piping Renovations
Milestone Construction Schedule
File: Onekama - Vestibule Renovations - 25-0317 Page 1 of 1 Current Date: Mon 3/17/25
File details come from the government source that posted it. Updated .