About this file

This is a bid form for Lead Service Line Replacements Year 4, Event 1 of 2, a public works project in Minnesota. The project involves the replacement of water service lines in four geographic packages designated as Green, Gold, Yellow, and Purple. Bidders must submit unit prices for all line items within each work package to be considered responsive. Line items are categorized by diameter (1", 1-1/4", 1-1/2", and 2") and type of service (Main to Meter, Main to Curb Stop, Curb Stop to Meter, Blind Run, and Discontinue Only). Estimated quantities vary by package: the Green package includes 234 total estimated line items plus 5 exploratory excavations; the Gold package includes 121 total estimated line items plus 5 exploratory excavations; the Yellow package includes 355 total estimated line items plus 5 exploratory excavations; and the Purple package includes 358 total estimated line items plus 5 exploratory excavations. All bids must be submitted in the provided Excel format with auto-calculated totals, and no handwritten prices are acceptable.

Each work package includes a base bid and an add/alternate option for contractor-performed testing and documentation services provided by a geotechnical testing company in lieu of standard density testing provisions. Bidders are required to provide both a unit price for all base bid line items and a lump sum price for the add/alternate. Mathematical errors will be resolved by unit price prevailing over extended price. The bid form specifies that estimated quantities are not guaranteed and that award may be based on the total of the base bid plus the add/alternate for each work package. Bidders must also indicate their package preferences, ranking the four packages by preference level (1 being most preferred). All calculated base bid and add/alternate amounts must be submitted in eSupplier on specified line numbers for each corresponding package.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID FORM
Lead Service Line Replacements Year 4, Event 1 of 2
Green, Gold, Yellow, Purple Packages
Event # 4361
Bid Form Information:
- Enter Company name in "Company" Field.
- If you are bidding on a work package, a Unit Price must be entered for all line items listed in that work package to be considered Responsive.
- Bid Form line items listed with an Estimated Quantity of zero (0) require a bid price. The price does not calculate into the bid total and is for owner review.
- The Bid Form includes an add/alternate for each work package. If you are bidding on a work package, a lump Sum bid price for the add/alternate is required.
- The Bid Form spreadsheet will auto-calculate the total bid amount for each package. No handwritten prices will be accepted.
- The auto-calculated total bid amount for each work package and add/alternate you are bidding on should be entered on the specified line number in eSupplier.
- Award of bid may be based on the total of the base bid plus the add/alternate for each work package.
- In the event of a mathematical error, the unit price shall prevail.
- The Bid Form quantities are estimates and are not a guarantee of future orders.
- The Bid Form must be filled out in the provided Excel format and a copy attached with your bid response.

Company:

GREEN PACKAGE
* NOTE: * Line items listed with an Estimated Quantity of zero (0) require a bid price. The price is not included in the bid total and is for owner review.
Item NumberItem NameDiameterEstimated QuantityUnit of MeasureUnit PriceExtended Price
1Main to Meter (Short Water)1"22EA$ - 0$ - 0
2Main to Meter (Long Water)1"22EA$ - 0$ - 0
3Main To Curb Stop (Short Water)1"97EA$ - 0$ - 0
4Main To Curb Stop (Long Water)1"89EA$ - 0$ - 0
5Curb Stop to Meter (Short Water)1"1EA$ - 0$ - 0
6Curb Stop to Meter (Long Water) *1"0EA$ - 0$ - 0
7Main to Curb Stop (Blind Run)1"1EA$ - 0$ - 0
8Main to Meter (Blind Run) *1"0EA$ - 0$ - 0
9Main to Meter (Short Water)1-1/4"1EA$ - 0$ - 0
10Main to Meter (Long Water) *1-1/4"0EA$ - 0$ - 0
11Main To Curb Stop (Short Water)1-1/4"1EA$ - 0$ - 0
12Main To Curb Stop (Long Water) *1-1/4"0EA$ - 0$ - 0
13Curb Stop to Meter (Short Water) *1-1/4"0EA$ - 0$ - 0
14Curb Stop to Meter (Long Water) *1-1/4"0EA$ - 0$ - 0
15Main to Curb Stop (Blind Run) *1-1/4"0EA$ - 0$ - 0
16Main to Meter (Blind Run) *1-1/4"0EA$ - 0$ - 0
17Main to Meter (Short Water) *1-1/2"0EA$ - 0$ - 0
18Main to Meter (Long Water) *1-1/2"0EA$ - 0$ - 0
19Main to Box (Short Water) *1-1/2"0EA$ - 0$ - 0
20Main to Box (Long Water) *1-1/2"0EA$ - 0$ - 0
21Curb Stop to Meter (Short Water) *1-1/2"0EA$ - 0$ - 0
22Curb Stop to Meter (Long Water) *1-1/2"0EA$ - 0$ - 0
23Main to Curb Stop (Blind Run) *1-1/2"0EA$ - 0$ - 0
24Main to Meter (Blind Run) *1-1/2"0EA$ - 0$ - 0
25Main to Meter (Short Water) *2"0EA$ - 0$ - 0
26Main to Meter (Long Water) *2"0EA$ - 0$ - 0
27Main To Curb Stop (Short Water) *2"0EA$ - 0$ - 0
28Main To Curb Stop (Long Water) *2"0EA$ - 0$ - 0
29Curb Stop to Meter (Short Water) *2"0EA$ - 0$ - 0
30Curb Stop to Meter (Long Water) *2"0EA$ - 0$ - 0
31Main to Curb Stop (Blind Run) *2"0EA$ - 0$ - 0
32Main to Meter (Blind Run) *2"0EA$ - 0$ - 0
33Discontinue Only *N/A0EA$ - 0$ - 0
34Exploratory ExcavationN/A5EA$ - 0$ - 0
GREEN PACKAGE BASE BID AMOUNT: SUBMIT THIS AMOUNT ON LINE # 1 IN ESUPPLIER:$ - 0
Add/Alternate: Bidders must provide a lump sum bid price for the below add/alternate for owner review and selection: "Contractor to Perform Testing and Documentation" (See Part 3 - Execution, Section 3.10 of Specifications)
Add Alternate No. 1Add - CONTRACTOR TO PERFORM TESTING AND DOCUMENTATION: In lieu of the Density Testing provisions described in Section 3.08, the contractor may provide the services of a Geotechnical Testing Company to supply all labor, equipment, and requirements to test and document the contractors backfill and compaction work for excavations performed for this contract. See Part 3, Sections 3.10.1 - 3.10.4 for requirements.$ - 0$ - 0
GREEN PACKAGE ADD/ALTERNATE AMOUNT: SUBMIT THIS AMOUNT ON LINE # 2 IN ESUPPLIER:$ - 0
GOLD PACKAGE
* NOTE: * Line items listed with an Estimated Quantity of zero (0) require a bid price. The price is not included in the bid total and is for owner review.
Item No.Item NameDiameterEstimated QuantityUnit of MeasureUnit PriceExtended Price
1Main to Meter (Short Water)1"13EA$ - 0$ - 0
2Main to Meter (Long Water)1"6EA$ - 0$ - 0
3Main To Curb Stop (Short Water)1"52EA$ - 0$ - 0
4Main To Curb Stop (Long Water)1"50EA$ - 0$ - 0
5Curb Stop to Meter (Short Water) *1"0EA$ - 0$ - 0
6Curb Stop to Meter (Long Water) *1"0EA$ - 0$ - 0
7Main to Curb Stop (Blind Run) *1"0EA$ - 0$ - 0
8Main to Meter (Blind Run) *1"0EA$ - 0$ - 0
9Main to Meter (Short Water) *1-1/4"0EA$ - 0$ - 0
10Main to Meter (Long Water) *1-1/4"0EA$ - 0$ - 0
11Main To Curb Stop (Short Water) *1-1/4"0EA$ - 0$ - 0
12Main To Curb Stop (Long Water) *1-1/4"0EA$ - 0$ - 0
13Curb Stop to Meter (Short Water) *1-1/4"0EA$ - 0$ - 0
14Curb Stop to Meter (Long Water) *1-1/4"0EA$ - 0$ - 0
15Main to Curb Stop (Blind Run) *1-1/4"0EA$ - 0$ - 0
16Main to Meter (Blind Run) *1-1/4"0EA$ - 0$ - 0
17Main to Meter (Short Water) *1-1/2"0EA$ - 0$ - 0
18Main to Meter (Long Water) *1-1/2"0EA$ - 0$ - 0
19Main to Box (Short Water) *1-1/2"0EA$ - 0$ - 0
20Main to Box (Long Water) *1-1/2"0EA$ - 0$ - 0
21Curb Stop to Meter (Short Water) *1-1/2"0EA$ - 0$ - 0
22Curb Stop to Meter (Long Water) *1-1/2"0EA$ - 0$ - 0
23Main to Curb Stop (Blind Run) *1-1/2"0EA$ - 0$ - 0
24Main to Meter (Blind Run) *1-1/2"0EA$ - 0$ - 0
25Main to Meter (Short Water) *2"0EA$ - 0$ - 0
26Main to Meter (Long Water) *2"0EA$ - 0$ - 0
27Main To Curb Stop (Short Water) *2"0EA$ - 0$ - 0
28Main To Curb Stop (Long Water) *2"0EA$ - 0$ - 0
29Curb Stop to Meter (Short Water) *2"0EA$ - 0$ - 0
30Curb Stop to Meter (Long Water) *2"0EA$ - 0$ - 0
31Main to Curb Stop (Blind Run) *2"0EA$ - 0$ - 0
32Main to Meter (Blind Run) *2"0EA$ - 0$ - 0
33Discontinue Only *N/A0EA$ - 0$ - 0
34Exploratory ExcavationN/A5EA$ - 0$ - 0
GOLD PACKAGE BASE BID AMOUNT: SUBMIT THIS AMOUNT ON LINE # 3 IN ESUPPLIER:$ - 0
Add/Alternate: Bidders must provide a lump sum bid price for the below add/alternate for owner review and selection: "Contractor to Perform Testing and Documentation" (See Part 3 - Execution, Section 3.10 of Specifications)
Add Alternate No. 1Add - CONTRACTOR TO PERFORM TESTING AND DOCUMENTATION: In lieu of the Density Testing provisions described in Section 3.08, the contractor may provide the services of a Geotechnical Testing Company to supply all labor, equipment, and requirements to test and document the contractors backfill and compaction work for excavations performed for this contract. See Part 3, Sections 3.10.1 - 3.10.4 for requirements.$ - 0$ - 0
GOLD PACKAGE ADD/ALTERNATE AMOUNT: SUBMIT THIS AMOUNT ON LINE # 4 IN ESUPPLIER:$ - 0
YELLOW PACKAGE
* NOTE: * Line items listed with an Estimated Quantity of zero (0) require a bid price. The price is not included in the bid total and is for owner review.
Item No.Item NameDiameterEstimated QuantityUnit of MeasureUnit PriceExtended Price
1Main to Meter (Short Water)1"16EA$ - 0$ - 0
2Main to Meter (Long Water)1"14EA$ - 0$ - 0
3Main To Curb Stop (Short Water)1"171EA$ - 0$ - 0
4Main To Curb Stop (Long Water)1"152EA$ - 0$ - 0
5Curb Stop to Meter (Short Water)1"1EA$ - 0$ - 0
6Curb Stop to Meter (Long Water) *1"0EA$ - 0$ - 0
7Main to Curb Stop (Blind Run) *1"0EA$ - 0$ - 0
8Main to Meter (Blind Run) *1"0EA$ - 0$ - 0
9Main to Meter (Short Water)1-1/4"1EA$ - 0$ - 0
10Main to Meter (Long Water) *1-1/4"0EA$ - 0$ - 0
11Main To Curb Stop (Short Water) *1-1/4"0EA$ - 0$ - 0
12Main To Curb Stop (Long Water) *1-1/4"0EA$ - 0$ - 0
13Curb Stop to Meter (Short Water) *1-1/4"0EA$ - 0$ - 0
14Curb Stop to Meter (Long Water) *1-1/4"0EA$ - 0$ - 0
15Main to Curb Stop (Blind Run) *1-1/4"0EA$ - 0$ - 0
16Main to Meter (Blind Run) *1-1/4"0EA$ - 0$ - 0
17Main to Meter (Short Water) *1-1/2"0EA$ - 0$ - 0
18Main to Meter (Long Water) *1-1/2"0EA$ - 0$ - 0
19Main to Box (Short Water) *1-1/2"0EA$ - 0$ - 0
20Main to Box (Long Water) *1-1/2"0EA$ - 0$ - 0
21Curb Stop to Meter (Short Water) *1-1/2"0EA$ - 0$ - 0
22Curb Stop to Meter (Long Water) *1-1/2"0EA$ - 0$ - 0
23Main to Curb Stop (Blind Run) *1-1/2"0EA$ - 0$ - 0
24Main to Meter (Blind Run) *1-1/2"0EA$ - 0$ - 0
25Main to Meter (Short Water) *2"0EA$ - 0$ - 0
26Main to Meter (Long Water) *2"0EA$ - 0$ - 0
27Main To Curb Stop (Short Water) *2"0EA$ - 0$ - 0
28Main To Curb Stop (Long Water) *2"0EA$ - 0$ - 0
29Curb Stop to Meter (Short Water) *2"0EA$ - 0$ - 0
30Curb Stop to Meter (Long Water) *2"0EA$ - 0$ - 0
31Main to Curb Stop (Blind Run) *2"0EA$ - 0$ - 0
32Main to Meter (Blind Run) *2"0EA$ - 0$ - 0
33Discontinue Only *N/A0EA$ - 0$ - 0
34Exploratory ExcavationN/A5EA$ - 0$ - 0
YELLOW PACKAGE BASE BID AMOUNT: SUBMIT THIS AMOUNT ON LINE # 5 IN ESUPPLIER:$ - 0
Add/Alternate: Bidders must provide a lump sum bid price for the below add/alternate for owner review and selection: "Contractor to Perform Testing and Documentation" (See Part 3 - Execution, Section 3.10 of Specifications)
Add Alternate No. 1Add - CONTRACTOR TO PERFORM TESTING AND DOCUMENTATION: In lieu of the Density Testing provisions described in Section 3.08, the contractor may provide the services of a Geotechnical Testing Company to supply all labor, equipment, and requirements to test and document the contractors backfill and compaction work for excavations performed for this contract. See Part 3, Sections 3.10.1 - 3.10.4 for requirements.$ - 0$ - 0
YELLOW PACKAGE ADD/ALTERNATE AMOUNT: SUBMIT THIS AMOUNT ON LINE # 6 IN ESUPPLIER:$ - 0
PURPLE PACKAGE
* NOTE: * Line items listed with an Estimated Quantity of zero (0) require a bid price. The price is not included in the bid total and is for owner review.
Item No.Item NameDiameterEstimated QuantityUnit of MeasureUnit PriceExtended Price
1Main to Meter (Short Water)1"26EA$ - 0$ - 0
2Main to Meter (Long Water)1"29EA$ - 0$ - 0
3Main To Curb Stop (Short Water)1"189EA$ - 0$ - 0
4Main To Curb Stop (Long Water)1"111EA$ - 0$ - 0
5Curb Stop to Meter (Short Water) *1"0EA$ - 0$ - 0
6Curb Stop to Meter (Long Water)1"2EA$ - 0$ - 0
7Main to Curb Stop (Blind Run) *1"0EA$ - 0$ - 0
8Main to Meter (Blind Run) *1"0EA$ - 0$ - 0
9Main to Meter (Short Water) *1-1/4"0EA$ - 0$ - 0
10Main to Meter (Long Water) *1-1/4"0EA$ - 0$ - 0
11Main To Curb Stop (Short Water) *1-1/4"0EA$ - 0$ - 0
12Main To Curb Stop (Long Water) *1-1/4"0EA$ - 0$ - 0
13Curb Stop to Meter (Short Water) *1-1/4"0EA$ - 0$ - 0
14Curb Stop to Meter (Long Water) *1-1/4"0EA$ - 0$ - 0
15Main to Curb Stop (Blind Run) *1-1/4"0EA$ - 0$ - 0
16Main to Meter (Blind Run) *1-1/4"0EA$ - 0$ - 0
17Main to Meter (Short Water) *1-1/2"0EA$ - 0$ - 0
18Main to Meter (Long Water) *1-1/2"0EA$ - 0$ - 0
19Main to Box (Short Water) *1-1/2"0EA$ - 0$ - 0
20Main to Box (Long Water) *1-1/2"0EA$ - 0$ - 0
21Curb Stop to Meter (Short Water) *1-1/2"0EA$ - 0$ - 0
22Curb Stop to Meter (Long Water) *1-1/2"0EA$ - 0$ - 0
23Main to Curb Stop (Blind Run) *1-1/2"0EA$ - 0$ - 0
24Main to Meter (Blind Run) *1-1/2"0EA$ - 0$ - 0
25Main to Meter (Short Water) *2"0EA$ - 0$ - 0
26Main to Meter (Long Water) *2"0EA$ - 0$ - 0
27Main To Curb Stop (Short Water) *2"0EA$ - 0$ - 0
28Main To Curb Stop (Long Water) *2"0EA$ - 0$ - 0
29Curb Stop to Meter (Short Water) *2"0EA$ - 0$ - 0
30Curb Stop to Meter (Long Water) *2"0EA$ - 0$ - 0
31Main to Curb Stop (Blind Run) *2"0EA$ - 0$ - 0
32Main to Meter (Blind Run) *2"0EA$ - 0$ - 0
33Discontinue Only *N/A0EA$ - 0$ - 0
34Exploratory ExcavationN/A5EA$ - 0$ - 0
PURPLE PACKAGE BASE BID AMOUNT: SUBMIT THIS AMOUNT ON LINE # 7 IN ESUPPLIER:$ - 0
Add/Alternate: Bidders must provide a lump sum bid price for the below add/alternate for owner review and selection: "Contractor to Perform Testing and Documentation" (See Part 3 - Execution, Section 3.10 of Specifications)
Add Alternate No. 1Add - CONTRACTOR TO PERFORM TESTING AND DOCUMENTATION: In lieu of the Density Testing provisions described in Section 3.08, the contractor may provide the services of a Geotechnical Testing Company to supply all labor, equipment, and requirements to test and document the contractors backfill and compaction work for excavations performed for this contract. See Part 3, Sections 3.10.1 - 3.10.4 for requirements.$ - 0$ - 0
PURPLE PACKAGE ADD/ALTERNATE AMOUNT: SUBMIT THIS AMOUNT ON LINE # 8 IN ESUPPLIER:$ - 0
PACKAGE PREFERENCE INFORMATION
Enter your work package preference(s) for the LSLR Year 4, Event 1 of 2:
Item No.Item DescriptionPreference: (1, 2, 3, 4, or NA)
1GREEN PACKAGE: Preference (1 is most preferred, 2 is second most, etc.)
2GOLD PACKAGE: Preference (1 is most preferred, 2 is second most, etc.)
3YELLOW PACKAGE: Preference (1 is most preferred, 2 is second most, etc.)
4PURPLE PACKAGE: Preference (1 is most preferred, 2 is second most, etc.)

File details come from the government source that posted it. Updated .