Bid.Pricing.Form (11)~1.xlsx
XLSX spreadsheet 24 KB Posted
- Solicitation number
- S-73000-00009939
- Issued by
- Hood River County, Oregon
About this file
This document is a Bid Pricing Form for an Invitation to Bid (ITB) issued by the Oregon Department of Transportation (ODOT) for geotechnical investigation services for the I-84 (Westbound) over Union Pacific Railroad bridge replacement project in Hood River, Oregon. The scope of work includes accessing and drilling up to ten geotechnical borings, some of which are located within a wetland subject to in-water work restrictions. The bid items include administration, mobilization/demobilization, temporary protection and direction of traffic, hollow-stem auger/mud rotary drilling, rock core drilling, undisturbed soil samples, geotechnical hole reports, and standby hours. Bidders must provide unit prices and total bid amounts for each line item. The contract opportunity is being re-bid under ITB # S-73000-00009939.
The Bid Pricing Form indicates that the total bid amount must be based on meeting the delivery requirements stated in the ITB. The pricing sheet provides a detailed breakdown of the estimated quantities and unit prices for the various bid items. Bidders must submit their total bid amount on the form. This contract opportunity is being administered by ODOT and is open to qualified contractors in the state of Oregon, specifically in the jurisdictions of Hood River County and Idaville CDP.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Coversheet~22.docx | DOCX document | |
| Exhibit A - Specifications~1.pdf | ||
| 245019 Bid Tabulation.pdf | ||
| 00009939_Invitation to Bid.docx | DOCX document | |
| Intent to Award~27.xlsx | XLSX spreadsheet | |
| Sample Contract~39.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 Bid Pricing Form ITB #:S-73000-00009939 Name of Firm:_______________________ Bid pricing must be based on meeting the Delivery Requirements stated in ITB section 2.4.
Bidder offers to furnish all materials, equipment and labor in strict accordance with the ITB and its attached Specifications on the basis of the total bid amount and/or unit prices as follows:
| Bid Item | Description | |||
| Unit | Quantity | Unit Price | Total Price | |
| 1 | Administration | Lump Sum | 1 | $0.00 |
| 2 | Mobilization/Demobilization | Lump Sum | 1 | $0.00 |
| 3 | Temporary Protection and Direction of Traffic (TP-DT) | Day | 4 | $0.00 |
| 4 | Hollow-Stem Auger/Mud Rotary Drilling | Feet | 860 | $0.00 |
| 5 | Rock Core Drilling | Feet | 40 | $0.00 |
| 6 | 3” Undisturbed Samples (Shelby Tubes) | Each | 16 | $0.00 |
| 7 | OWRD Geotechnical Hole Reports | Each | 10 | $0.00 |
| 8 | Drums | Each | 4 | $0.00 |
| 9 | Standby | Hours | 4 | $0.00 |
| TOTAL BID AMOUNT | $0.00 |
Sheet2
| EST. | UNIT | TOTAL | |||
| ITEM | DESCRIPTION | QTY. | UNIT | PRICE | PRICE |
| 1 | |||||
| 2 | |||||
| 3 | |||||
| 4 | |||||
| 5 | |||||
| 6 | |||||
| 7 | |||||
| 8 | |||||
| 9 | |||||
| 10 | |||||
| TOTAL BID AMOUNT |
Sheet3
File details come from the government source that posted it. Updated .