Bid Cost Breakout by Line Items for PROJECT 589-19-503 rev5.xls
XLS spreadsheet 81 KB Posted
- Attached to
- Z2DA-- 589-19-503, Correct Deficiencies in BAS for Legionella Prevention (VA-20-00028966)
- Solicitation number
- 36C25520R0078_1
About this file
This document provides details for a federal construction contract opportunity to correct deficiencies in the building automation system for Legionella prevention at the Kansas City VA Medical Center. The project involves installing approximately 120 new flow meters and 204 temperature sensors connected to an existing Schneider Electric EcoStruxure building automation system. It also requires upgrading 22 universal network controllers to the newer Schneider Electric EcoStruxure control system. The electrical scope includes power for new controls and sensors from existing or new panelboards. Minimal abatement and patching is required. The contract type is firm fixed price with an estimated cost between $2 million and $5 million. The solicitation will be set aside for service-disabled veteran-owned small businesses and have a North American Industry Classification Code of 236220. The completion period is 180 calendar days from notice to proceed. The solicitation and site visit are scheduled for May 21, 2020 and July 2, 2020 respectively. Questions are due by email to the point of contact by the response deadline.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25520R0078 0002.docx | DOCX document | |
| S04-Project 589-19-503 Construction Pre-Bid Presentation rev 3.pdf | ||
| S04- Pre-Bid Meeting and Site Visit Attendance Sheet.xlsx | XLSX spreadsheet | |
| 36C25520R0078 0001.docx | DOCX document | |
| 36C25520R0078_1.docx | DOCX document | |
| Vol 2 CD Specifications- Project 589-19-503 (262 Pages).pdf | ||
| Vol 1 CD Specifications rev1- Project 589-19-503 (331 pages).pdf | ||
| P09- Statment of Work - PROJECT 589-19-503 (56 pages).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid #1
| CONSTRUCTION BID DOCUMENTS | Contracting Officer's Representative: Marcus Stevenson | ||||||||||||
| Title: | 589-19-503: CORRECT DEFICIENCIES IN BAS FOR LEGIONELLA PREVENTION | Name of Bidding General Contractor(GC): | |||||||||||
| Date: | Working Facility: Kansas City VA | Labor Burden: KCMO | SUB 1 | 0% | GC | 0% | |||||||
| Comments: | Project Schedule is 180 calendar days from contractors Notice-To-Proceed (N.T.P.) | ||||||||||||
| RSMeans | Unit Cost | Total Cost | |||||||||||
| Line Item | System/Subsystem | Unit | Quantity | Page | Table | Unit Material Cost | Unit Equipment Cost | Unit Labor Cost | Material | Equipment | Labor | Total | |
| 02000 EXISTING CONDITIONS | |||||||||||||
| 02200 Environmental Abatement | |||||||||||||
| 02200-1 | Remove 3'-0" section of ACM pipe insulation via glove bag method | EA | 70 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 09000 FINISHES | |||||||||||||
| 09900 Miscellaneous Finishes | |||||||||||||
| 09000-1 | Cutting and patching allowance of finished surfaces related to plumbing/BAS work | LS | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 22000 PLUMBING | |||||||||||||
| 22300 Plumbing Equipment & Specialties | |||||||||||||
| 22300-1 | BTU meter and flow meter, insertion type, turbine, including pipe cutting and new (installation only, material provided by EC) | ||||||||||||
| bypass (installation only, material provided by EC) | EA | 11 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| 22300-2 | BTU meter and flow meter, inline, including pipe cutting and new bypass piping(installation only, material provided by EC) | EA | 107 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 22300-3 | BTU meter (installation only, material provided by EC) | EA | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 22300-4 | Temperature sensors, strap on type (installation only, material provided by EC) | EA | 321 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 22300-5 | Labor Rate for hrly support after water utility outage | HR | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 22400 Domestic Water, Waste & Vent, & Storm Drainage Piping | |||||||||||||
| 22400-1 | Provide new taps in CW piping in Mechanical Rooms for chlorine injection, 3/4" capped valve | EA | 119 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| Reinsulate piping where sensors were installed | EA | 440 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| 23000 HEATING VENTILATION & AIR CONDITIONING | |||||||||||||
| 23600 Temperature Controls | |||||||||||||
| 22600-1 | Miscellaneous points & devices | LS | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 23700 Testing, Balancing, & Commissioning | |||||||||||||
| 22700-1 | Pipe system testing | LS | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 22700-2 | Commissioning | LS | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 26000 ELECTRICAL | |||||||||||||
| 26200 Main Power Distribution | |||||||||||||
| 26200-1 | Install 20A/1P breaker in existing panel | EA | 6 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 26200-2 | Install 3P, 60A breaker in existing panel to feed new 60A sub-panel | EA | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 26200-3 | Sub-panel, 60A | EA | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 26200-4 | Feeder installation 600 V, including conduit and XHHW wire, 60A | LNFT | 25 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 26200-5 | 26600 Branch Power Distribution & Devices | ||||||||||||
| 26200-6 | MNL network control panels, including installation and programming | EA | 42 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 26200-7 | Temperature sensors, 2" and under (material only, provided to PC for installation) | EA | 283 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 26200-8 | Temperature sensors, 2-1/2" and over (material only, provided to PC for | ||||||||||||
| installation) | EA | 38 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| 26200-9 | System 10 BTU meter and F-1100 flow meter, insertion type, turbine; 6" (material | ||||||||||||
| only, provided to PC for installation) | EA | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| 26200-10 | System 10 BTU meter and F-1100 flow meter, insertion type, turbine; 4" (material | ||||||||||||
| only, provided to PC for installation) | EA | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| 26200-11 | System 10 BTU meter and F-1100 flow meter, insertion type, turbine; 3" (material | ||||||||||||
| only, provided to PC for installation) | EA | 9 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| 26200-12 | System 10 BTU meter and F-4600 flow meter, in-line; 2-1/2" (material only, | ||||||||||||
| provided to PC for installation) | EA | 19 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| 26200-13 | System 10 BTU meter and F-4600 flow meter, in-line; 2" (material only, provided | ||||||||||||
| to PC for installation) | EA | 48 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| 26200-14 | System 10 BTU meter and F-4600 flow meter, in-line; 1-1/2" (material only, provided to PC for installation) | EA | 17 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 26200-15 | System 10 BTU meter and F-4600 flow meter, in-line; 1-1/4" (material only, provided to PC for installation) | EA | 5 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 26200-16 | System 10 BTU meter and F-4600 flow meter, in-line; 1" (material only, provided to PC for installation) | EA | 18 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 26200-17 | System 40 BTU meter; 2" (material only, provided to PC for installation) | EA | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 26200-18 | 20A emergency/normal power circuit to panels/devices as indicated | LNFT | 1800 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 26900 Special Electrical | |||||||||||||
| 26900-1 | Universal network controller, including disconnection and removal of existing power wiring, disconnection of CAT5 network cabling, reprogramming, data | ||||||||||||
| transfer and commissioning | EA | 22 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| 27000 COMMUNICATIONS | |||||||||||||
| 27200 Tele/Data Systems | |||||||||||||
| 27200-1 | Floor core in IT closet for 3/4" conduit riser | EA | 15 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 27200-2 | Electric metallic tubing, 3/4" diameter, to 15' high, including fittings and supports | LNFT | 320 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 27200-3 | Extend network cabling from nearest LON trunk to new meters | LNFT | 42000 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| 27200-4 | Modify existing LON network repeaters as needed, provide all testing, terminations | ||||||||||||
| and engineering as required | LNFT | 7 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| GC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| GC | GENERAL CONDITIONS | LS | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| GC | CONTRACTOR'S FEES | LS | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| GC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| GC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Prof Srvcs | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Prof Srvcs | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Prof Srvcs | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| SUBCONTRACTOR 1 | GENERAL CONTRACTOR | ||||||||||||
| MATERIAL | $ - 0 | MATERIAL | $ - 0 | ||||||||||
| EQUIPMENT | $ - 0 | EQUIPMENT | $ - 0 | ||||||||||
| LABOR | $ - 0 | LABOR | $ - 0 | ||||||||||
| SUBTOTAL | $ - 0 | SUBTOTAL | $ - 0 | ||||||||||
| OVERHEAD | $ - 0 | OVERHEAD | $ - 0 | ||||||||||
| SUBTOTAL | $ - 0 | SUBTOTAL | $ - 0 | ||||||||||
| PROFIT | $ - 0 | PROFIT | $ - 0 | ||||||||||
| SUBTOTAL | $ - 0 | SUBTOTAL | $ - 0 | ||||||||||
| LABOR BURDEN | $ - 0 | LABOR BURDEN | $ - 0 | ||||||||||
| SUB 1 TOTAL | $ - 0 | GC TOTAL | $ - 0 | ||||||||||
| SUB 1 TOTAL | $ - 0 | ||||||||||||
| PROF SERVICES | $ - 0 | ||||||||||||
| SUBTOTAL | $ - 0 | ||||||||||||
| GC OH & PROFIT | $ - 0 | ||||||||||||
| BOND/INSURANCE | $ - 0 | ||||||||||||
| ESTIMATOR SIGNATURE ___________________________________________________________________ | TOTAL | $ - 0 |
&R&F Department of Veterans Affairs:
Enter COMBINED SUBCONTRACTORS LABOR BURDEN PERCENTAGE Department of Veterans Affairs:
Enter GENERAL CONTRACTOR LABOR BURDEN PERCENTAGE Department of Veterans Affairs:
Note to the Preparer: Areas highlighted in Green: Subs Combined Yellow: General Contractor
Bid Deduct #1
| CONSTRUCTION BID DOCUMENTS | Contracting Officer's Representative: Marcus Stevenson | ||||||||||||
| Title: | 589-19-503: CORRECT DEFICIENCIES IN BAS FOR LEGIONELLA PREVENTION | Name of Bidding General Contractor(GC): | |||||||||||
| Date: | Working Facility: Kansas City VA | Labor Burden: KCMO | SUB 1 | 0% | GC | 0% | |||||||
| Comments: | Project Schedule is 180 calendar days from contractors Notice-To-Proceed (N.T.P.) | ||||||||||||
| RSMeans | Unit Cost | Total Cost | |||||||||||
| Line Item | System/Subsystem | Unit | Quantity | Page | Table | Unit Material Cost | Unit Equipment Cost | Unit Labor Cost | Material | Equipment | Labor | Total | |
| 26900-1 | Universal network controller, including disconnection and removal of existing power wiring, disconnection of CAT5 network cabling, reprogramming, data | ||||||||||||
| transfer and commissioning | EA | 22 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||
| GC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| GC | GENERAL CONDITIONS | LS | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| GC | CONTRACTOR'S FEES | LS | 1 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | |||
| GC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Prof Srvcs | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Prof Srvcs | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| Prof Srvcs | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 | ||||||
| SUBCONTRACTOR 1 | GENERAL CONTRACTOR | ||||||||||||
| MATERIAL | $ - 0 | MATERIAL | $ - 0 | ||||||||||
| EQUIPMENT | $ - 0 | EQUIPMENT | $ - 0 | ||||||||||
| LABOR | $ - 0 | LABOR | $ - 0 | ||||||||||
| SUBTOTAL | $ - 0 | SUBTOTAL | $ - 0 | ||||||||||
| OVERHEAD | $ - 0 | OVERHEAD | $ - 0 | ||||||||||
| SUBTOTAL | $ - 0 | SUBTOTAL | $ - 0 | ||||||||||
| PROFIT | $ - 0 | PROFIT | $ - 0 | ||||||||||
| SUBTOTAL | $ - 0 | SUBTOTAL | $ - 0 | ||||||||||
| LABOR BURDEN | $ - 0 | LABOR BURDEN | $ - 0 | ||||||||||
| SUB 1 TOTAL | $ - 0 | GC TOTAL | $ - 0 | ||||||||||
| George Karaboyias | SUB 1 TOTAL | $ - 0 | |||||||||||
| PROF SERVICES | $ - 0 | ||||||||||||
| SUBTOTAL | $ - 0 | ||||||||||||
| GC OH & PROFIT | $ - 0 | ||||||||||||
| BOND/INSURANCE | $ - 0 | ||||||||||||
| ESTIMATOR SIGNATURE ___________________________________________________________________ | TOTAL | $ - 0 |
&L&8&F Department of Veterans Affairs:
Note to the Preparer: Areas highlighted in Green: Subs Combine Yellow: General Contractor Department of Veterans Affairs:
Enter COMBINED SUBCONTRACTORS LABOR BURDEN PERCENTAGE Department of Veterans Affairs:
Enter GENERAL CONTRACTOR LABOR BURDEN PERCENTAGE