S04-Project 589-19-503 Construction Pre-Bid Presentation rev 3.pdf
PDF 1 MB Posted
- Attached to
- Z2DA-- 589-19-503, Correct Deficiencies in BAS for Legionella Prevention (VA-20-00028966)
- Solicitation number
- 36C25520R0078_1
About this file
This document provides details of a federal construction contract opportunity to correct deficiencies in the building automation system for legionella prevention at the Kansas City VA Medical Center. The scope of work involves installing approximately 120 new flow meters and 204 temperature sensors connected to an existing Schneider Electric EcoStruxure building automation system across three buildings. It also requires upgrading 22 universal network controllers to Schneider Electric Automation Servers and integrating existing programming. Estimated costs range from $2-5 million. Electrical work includes power for new controls from existing or new panels. Minimal patching and abatement is required. Commissioning is also included. The pre-bid meeting agenda reviews the solicitation, schedule, site tour and question submission process. The opportunity is a total SDVOSB set-aside with proposals due around July 2nd and award utilizing best value tradeoff. The NAICS is 236220 and period of performance is 180 days.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25520R0078 0002.docx | DOCX document | |
| S04- Pre-Bid Meeting and Site Visit Attendance Sheet.xlsx | XLSX spreadsheet | |
| 36C25520R0078 0001.docx | DOCX document | |
| 36C25520R0078_1.docx | DOCX document | |
| Vol 2 CD Specifications- Project 589-19-503 (262 Pages).pdf | ||
| Bid Cost Breakout by Line Items for PROJECT 589-19-503 rev5.xls | XLS spreadsheet | |
| Vol 1 CD Specifications rev1- Project 589-19-503 (331 pages).pdf | ||
| P09- Statment of Work - PROJECT 589-19-503 (56 pages).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project 589-19-503 Correct Deficiencies in BAS for Legionella Prevention
Construction Pre-Bid Meeting June 2, 2020
U.S. Department of Veterans Affairs Facilities Management Services
Kansas City VA Medical Center 4801 Linwood Blvd.
Kansas City, MO 64128
Construction Pre-Bid Meeting June 2, 2020
Agenda: Pre-Bid Meeting
1. General & VA – A/E Introductions (David Sterrett - CO)
2. Role Call (Marcus Stevenson - COR)
3. Solicitation Review and Timeline (CO)
4. Statement of Work Overview (A/E Team)
5. Site Tour and Site Specifics (COR/Engineering)
6. Questions and Answers (Contractors/ A/E/ VA)
Introductions
KCVA Team David Sterrett -Contracting Officer (CO) Marcus Stevenson- Contracting Officer’s Technical Representative (COR) Zach Homan- Backup COR and HVAC Supervisor (COR) Ryan Recker- Plumbing Supervisor
Nagel Architects + Engineers Team Joe Heinowski, Principle Architect Tom King, Principle Engineer Marty Kimball, Mechanical Engineer (plumbing focus)
Project 589-19-503
Construction Pre-Bid Meeting June 2, 2020
Role Call
Solicitation Review and Timeline
(CO)
Project 589-19-503
Project Specific Information
• Set Aside: Service Disabled Veteran Owned Small Business (SDVOSB)
• Project Title: Correct Deficiencies in BAS for Legionella Prevention
• Project Number: 589-19-503
• Solicitation Number: 36C25520R0078
• Location: Kansas City VA Medical Center
4801 Linwood Blvd Kansas City, MO 64128
Project 589-19-503
Project Specific Information (continued)
• Magnitude of Project: $2 to $5 Million
• Type of Construction: General Construction
• NAICS: 236220, Commercial & Institutional Building Construction
• Small Business Size: $39.5 Million
• Period of Performance: 180 Days
• Proposal Due Date: July 2, 2020 2:00 pm CDT
• Technical Question Submittal Date: June 12, 2020 by 2:00pm CDT
Project 589-19-503
Proposal Submittal Instructions
I. Preparation and Submittal of Proposals
– General Information
– The Offer
– Award Based on Initial Offers
– Number of Copies and Document Content
II. Documentation of Acceptability
– Relative Importance of Evaluation Factors
– 5 Factors
Project 589-19-503
Proposal Submittal Instructions (continued)
III. Price Proposal IV. Basis for Award- Best Value with Tradeoff V. Special Factors:
– Substitution of Subcontractors or Key Personnel
– Safety or Environmental Violations and EMR Rate
– Vets 4212, VIP and SAMs Reports- Must be filed and Current
– Self Perform 15% of Work (NAICS Code Dependent)
– Bonds and Insurance- Required
Project 589-19-503
Statement of Work Overview (A/E Team)
Project 589-19-503
Building Automation System (BAS):
Overview I. Temperature Sensors, Flow Meters
A. Buildings 1, 26 and 56 II. Universal Network Controllers
A. Buildings 1, 2, 4, 15, 26 B. Replace with Schneider Electric Automation Servers (AS) C. One for one replacement
III. Connection to the Schneider Electric EcoStruxure A. Both new sensors/meters and the 22 UNCs B. C&C Group currently services the VA control system
TOM SLIDESLIDE
Project 589-19-503
Design Criteria – Electrical:
I. Extend new circuits to serve new control panels II. A new panel in Bldg. 1 on first floor III. Bldg. 26 – re-feed some of the replacement UNCs with power from EM source IV. Provide data drops in select locations
TOM SLIDESLIDE
Project 589-19-503
Design Criteria - Plumbing
I. Temperature Sensors II. Flow Sensors III. Main Risers IV.Branch Taps Offs Temperature Sensors V. Shut Off Valves
MARTY
Project 589-19-503
Commissioning Activities:
I. Commissioning Plan II. Verification
I. Progress visits and Pre-functional checklists III. Integration into BAS
I. Functional checklists IV. Document Deficiencies
I. Work with OAC team on resolutions V. Final Report
TOM
Project 589-19-503
SUMMARY:
I. Buildings 1, 26 and 56.
II. Placement of new flow meters , temperature sensors to provide monitoring/alarm capabilities.
III. Existing Schneider Electric EcoStruxure BAS IV.22 Universal Network Controllers (UNCs) V. Electrical power to new controls from existing or new electrical panelboards.
VI.Minimal patching and abatement VII.Commissioning activities
TOM SLIDE
Project 589-19-503
Design Criteria - Environmental
I. ACM Survey Available II. Lead-Based Paint Survey Available III.Assumption is at 70 locations it will be necessary to abate approximately 3 linear feet of ACM by glove bag methods.
JOE SLIDE
Project 589-19-503
Design Criteria - Phasing
I. a. Building 1, contractor to have no more than 4 shutdowns to install new piping.
II. b. Building 26, contractor to have no more than 3 shutdowns.
III. c. Building 56, only 1 building shutdown.
If you have creative ways to prevent or reduce outages with minimal risk to the hospital, please include such methods in your Bid Submission.
Example: Cryogenics
JOE SLIDE
Project 589-19-503
Site Tour and Site Specifics (COR/Engineering)
Project 589-19-503
JUNE 3, 2020 – Site Tour/Walk-through:
Tour times will (1) 8am to 11am & (2) Noon to 3pm
1.Tour 1: 8am – 11am 1.Group A - Electrical/Controls – Zach Homan 2.Group B - Plumbing – Ryan Recker
2.Tour 2: Noon – 3pm 1.Group A - Electrical/Controls – Zach Homan 2.Group B - Plumbing – Ryan Recker
Project 589-19-503
Parking Garage
Project 589-19-503 Correct Deficiencies in BAS for Legionella Prevention Construction Pre-Bid Meeting June 2, 2020
Hospital Protocol:
• All individuals (employees and patients) entering our buildings are required to wear a barrier mask covering their mouth and nose at all times. Visitors are asked to provide their own mask, but if you do not have one, a mask will be provided. In addition to social distancing and proper hand hygiene, universal barrier masking can help to slow the spread of COVID-19 in our organization and our community.
• Beards - requiring all male employees to remain clean shaven, ready and able to wear an N95 mask as required to meet the duties of their job.
• The use of makeup when using an N95 mask. In order to protect and maintain mask integrity, foundation, facial powder, lipstick and blush are not to be worn when using an N95 mask as required to meet the duties of your job. This memo is in effect until August 31, 2020.
Construction Pre-Bid Meeting June 2, 2020
Questions and Answers Disclaimer Statements:
Remarks and explanations made during today’s meeting or tomorrows site visit walkthrough shall not qualify the terms of the solicitation
Terms of the scope of work, solicitation and specifications remain unchanged unless the solicitation is amended in writing and posted to Beta SAM.gov.
Construction Pre-Bid Meeting June 2, 2020
Questions and Answers Send all Questions to David.Sterrett@va.gov no later than 2pm June 12, 2020
If you have more than one question, please number them 1, 2, 3 in your e-mail.
1. Otherwise, you may not get an answer to each of them.
2. An amendment will be issued to provide the answers to questions as well as to provide a copy of the attendance roster.
3. If any questions warrant an amendment, one will be issued and posted to beta.SAM.gov.
4. All interested contractors are responsible to check the beta.SAM.gov website prior to submitting a proposal to ensure that they have seen and addressed all amendments.