Bid_25-08._Addenda_1.pdf
PDF 130 KB Posted
- Solicitation number
- Bid 25-08
- Issued by
- Polk County, Florida
About this file
Addenda #1 for Bid 25-08 is issued by the Putnam County Procurement Department for the East Putnam Regional RO Membrane Replacement Project - Rebid. The document provides responses to 12 key questions from potential bidders regarding the membrane replacement project, which involves replacing three RO membrane trains. The addendum clarifies critical project details such as membrane specifications, storage capabilities, and project requirements. Substitute membranes will be considered if they meet dimensional specifications and are functionally equivalent, and the current membranes are Toray TMG20D-440.
The addendum confirms several important project parameters: no permits or contractor's licenses are required, power and water will be available at the plant, and the contractor will be responsible for disposing of old membranes. For train completion, contractors must thoroughly purge the system, bring it to operating pressure, and conduct a 1-hour trial run, collecting data on permeate flow rate, operation pressure, pressure drop, and recovery ratio. The project allows flexibility for legitimate long lead times, and no liquidated damages will be assessed. Additionally, there is limited space for a scissor lift, with scaffolding potentially needed to access certain vessels.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PUTNAM COUNTY
PROCUREMENT DEPARTMENT
2509 CRILL AVE, STE 200
PALATKA, FL 32177
Bid 25-08 East Putnam Regional RO Membrane Replacement Project - Rebid
Addenda # 1 January 10, 2025
TO ALL BIDDERS SUBMITTING A RESPONSE ON THIS PROJECT
The changes, additions, substitutions, and/or deletions contained in Addenda #1 are hereby made part of the Contract Documents fully and completely for this Bid.
1. Question:
The specifications list “Toray TMG20D-440 membrane elements” are to be provided. Is this sole sourced? Are other suppliers to be considered?
Answer:
Substitute membranes will be considered if they meet the dimensional specifications of those currently installed and they are functionally equivalent or better.
2. Question:
What membranes are currently installed?
Answer:
The membranes are Toray TMG20D-440.
3. Question:
Is the county aware of any permits or licenses needed for this project?
No permits are required and no licenses are needed.
4. Question:
What is the per-diem rate for damages under liquidated damages?
Liquidated damages are not being assessed on this project.
5. Question:
Can the plant store all three trains of membranes or do we need to have 3 shipments?
There is room for membrane storage for all 3 trains if needed at the plant or at the adjacent warehouse.
6. Question:
Can we include consideration/negotiation in timeline for procurement? (if any components have long lead time)
For legitimate long lead times, the timeline may be adjusted.
7. Question:
To achieve train completion: what data needs to be noted, and what is design criteria for passing?
Answer:
For completion, the train will need to be thoroughly purged for 1hr, brought up to operating pressure, and inspected for proper sealing. A 1 hour trial run under normal conditions will be conducted after purging. During the trial run, the data to be collected will be: Permeate flow rate; Operation pressure;
pressure drop across each vessel; recovery ratio. Sufficient test ports are currently installed on the system to allow for the required measurements.
8. Question:
Do we need a contractor’s license?
No contractor’s license is needed.
9. Question:
Do we need a safety representative for this project?
A safety representative is not required. The Operator will verify safety measures during installation.
10. Question:
Who is responsible for disposal of old membranes?
The contractor will take ownership and will need to dispose of all removed membranes.
11. Question:
Will power and water be available for use if needed?
Power and water are available at the plant.
12. Question:
Is there room for a scissor lift, or will scaffolding be needed to access higher vessels?
There is minimal room for a lift at one end of the vessels. The other end is not accessible by a lift.
| PUTNAM COUNTY |
| PROCUREMENT DEPARTMENT |
| 2509 CRILL AVE, STE 200 |